3
EATON
IB519013EN
Installation instructions
Installation Instructions - Steeler LED Battery Pack
Figure 6.
Ground
Input AC
To unswitched
circuit
QD
Figure 8.
Threaded
Pipe Shown
Connect Battery pack
charging circuit
Figure 7.
Junction Box
(by others)
Test Switch
Figure 9.
Fitting
To Test
Switc
h
Sensor
3. Wire input AC to the fixture, including the unswitched
circuit for the battery pack. Wire according to code.
(Figure 6).
4. Connect wires from test switch to wires from Battery
pack and fasten test switch mounted plate to Junction
box (not supplied). Wire according to code. (Figure 7).
5. Connect wires coming out of KO hole and push wires
back in to fixture. (Figure 8).
6. Cover KO with fitting provided. (Figure 9).