background image

6

Instructional Leafl et 

IL03901003E

Effective May 2011

DS7 series soft start controllers, Frame 1 (4–12A) 

  
  

EATON CORPORATION

 www.eaton.com

LED operation and troubleshooting

The operation, warning, and fault status of the controller may be 
determined by observing the pattern of LED illuminations. Only one 
condition may exist at any one time, with fault indications taking 
priority over others.

As conditions change, LED status will also change.

For example, during the initialization stage, the RED and GREEN 
LED’s will flash alternately. When initialization is complete and the 
Enable signal is present, the GREEN LED will then flash one time 
per second and the RED LED will be off.

LED operations/warning indications

Table 11. 

Operation

 

1 Second 

Initialization

Off

Supply voltage connection without enable

Supply voltage connection with enable

In ramp

TOR

Warnings

Overtemperature for next start

Start without enable

Potentiometer not effective, network operation

In the event of a motor stop due to a trip condition by the soft start 
controller, the FAULT status LED will be illuminated (flashing). In this 
case, one or more conditions found in 

Table 12

 may have occurred.

Tables 13

14

 and 

15

 may be used for evaluation or troubleshooting 

and contain additional information on operations and operating 
conditions.

LED fault indications

Table 12. 

Faults

 

1 Second 

Overtemperature, thyristor (I2t)

Overtemperature electronic

Over/under temperature heat sink

Thyristor is defective

Phase failure

Bypass is defective

Supply voltage faulty

Normal operation indications

Table 13. 

Status

LED

Condition

Action

Off

GREEN—Off 
RED—Off  

Control voltage is not applied to 
terU

s

 and –A2.

No action required. 

Note:

 Possible device failure if power is applied to these terminals and no LED’s are illuminated.

Initialization

GREEN—4x/s, pulse 1/8s
RED—4x/s, pulse 1/8s
alternating

Control power is applied to terminals 
+U

s

 and –A2. 

If the unit fails to properly initialize, verify that the notes 
LED indicates are correct. If the LED indications are not 
correct, the unit requires service.

Note:

 When control power is applied to terU

s

 and –A2, the unit enters a short initialization period. If the initialization sequence fails, 

remove and reapply power.

Supply voltage connection 
without enable

GREEN—1x/s, pulse 1/8s
RED – 1x/s, pulse 1/8s
simultaneous

No control power signal at terminal EN.

Apply control power enable signal to terminal EN to allow 
RUN command

Note:

 Enable signal may be tied to RUN command signal.

Supply voltage connection 
with enable

GREEN—1x/s, pulse 1/8s
RED—Off

Unit ready for RUN command.

Apply RUN command to teA1 to perform start.

Note:

 After successful initialization, the soft start controller is ready to perform START and RUN functions.

In ramp

GREEN—1x/s, pulse 1/2s
RED—Off

Unit is in START ramp.
Unit is in STOP ramp.

START ramp and STOP ramp (if selected) operation is 
indicated.

Note:

 Set ramp times as short as practical. Ramp times should be adjusted to expire approximately 2 seconds after the motor has achieved 

synchronous RPM. Motor rotation (START) should occur within 2 seconds of RUN command. STOP ramp cannot shorten coast-to-stop time (no 
braking function). Motor acceleration/deceleration times are load dependent.

TOR (Top of Ramp)

GREEN—Continuous 
RED—Off

Start ramp complete bypass contacts 
closed.

Unit is in normal operation.

Note:

 After a successful START ramp, the bypass relays close and the soft start controller is in a RUN condition. TOR will remain illuminated 

until RUN command is removed for coast stop or STOP ramp. Auxiliary relay contacts will change state at the same time as the TOR LED.

Summary of Contents for DS7 Series

Page 1: ...specifications set forth by UL 508 IEC 60947 4 2 CE C Tick and CSA This leaflet covers basic installation and setup No publication can take into account every possible situation If you require further...

Page 2: ...ARD Mounting hardware and torque specifications Table 1 Screw Size Flat and Lock Washer Quantity Torque Requirements Unit Weight Lbs kg M4 4 10 lb in 1 2 Nm 0 8 0 35 Environmental requirements Table 2...

Page 3: ...TOB010BC1 XTOE020BCS XTPR010BC1 XTPAXTPCB DS7 340SX012NO N DS7 342SX012NO N Product selection kW ratings according to IEC 60947 4 2 Please refer to Application Note AP03901006E for additional informat...

Page 4: ...13 A2 TOR Start and stop ramp functions Figure 5 Terminal designations Table 8 Terminal Description Us Control ground or circuit common Us Power of AC load A2 Common with Us A1 Run command 13 Top of...

Page 5: ...will be performed Adjusting the soft start controller parameters There are three adjustments to the DS7 soft start controller t Start ramp time u Start initial voltage torque t Stop stop ramp time DS7...

Page 6: ...ce failure if power is applied to these terminals and no LED s are illuminated Initialization GREEN 4x s pulse 1 8s RED 4x s pulse 1 8s alternating Control power is applied to terminals Us and A2 If t...

Page 7: ...move the controller to an optimum location to reduce operating temperatures Over under temperature heat sink GREEN Continuous RED Continuous Temperature of the SCR heat sink is not within operating sp...

Page 8: ...ers Instructional Leaflet IL03901003E Effective May 2011 DS7 series soft start controllers Frame 1 4 12A Service For additional information on this product please call the Eaton Technical Resource Cen...

Reviews: