Unpacking
Parts Checklist
Mounting
Carefully remove all equipment from the packing
cartons and inspect all parts for damage in
shipment. Check packing cartons for all items
shown on the packing list. Keep the cartons and
packing materials for future shipment.
Report any damage to the carrier who delivered the
equipment, then contact your Cutler-Hammer
distributor. If you purchased the equipment from
Cutler-Hammer, call the Order Processing
Department at (614) 882-3282. Note: The Interstate
Commerce Commission has a time limit on
reporting concealed damage.
Your packing carton contains one parts kit
containing:
1 Packet of mounting nuts and washers
2 Two-terminal connectors (audio output &
security keyswitch)
1 Three-terminal connector (24VDC power)
1 Four-terminal connector (fault relay)
Your PanelMate unit is designed for NEMA 4, 4X,
and 12 installations when properly mounted in a
correspondingly-rated enclosure.
Proper installation and enclosure sizing is essential
to ensure long life and trouble-free operation.
Refer to Cutler-Hammer's PanelMate Installation
Guide for installation recommendations. The Guide
is available on the Cutler-Hammer web site:
Panel cutout dimensions and stud torque limits are
shown on the reverse side of this Express Setup
sheet.
Stud nuts must be tightened enough to
obtain a proper seal, but not over-tightened
to the point where the threads are stripped
or the gasket is rendered useless. Always
use a torque wrench when installing your
PanelMate unit.
!
!
!
!
Your
PanelMate unit should always be mounted in a
vertical position. Flat or angled mounting positions
will shorten the unit's life.
www.cutlerhammer.eaton.com/automation
Note:
Safety Considerations
This equipment is suitable for Class I, Division 2,
Groups (A,B,C,D) or non-hazardous locations only.
EXPLOSION HAZARD. SUBSTITUTION OF
COMPONENTS MAY IMPAIR SUITABILITY FOR
CLASS 1, DIVISION 2.
RISQUE D'EXPLOSION. LA SUBSTITUTION DE
COMPOSANTS PUET RENDRE CE MATERIAL
INACCEPTABLE POUR LES EMPLACEMENTS
DE CLASSE 1, DIVISION 2.
EXPLOSION HAZARD. DO NOT REPLACE
COMPONENTS UNLESS POWER HAS BEEN
SWITCHED OFF OR AREA IS KNOWN TO BE
NON-HAZARDOUS.
RESQUE D'EXPLOSION. COUPER LE COURANT
OU S'ASSURER QUE L'EMPLACEMENT ES
DESIGNE NON DANGEREUX AVANT DE
REPLACER LE COMPOSANTS.