4.0 

Assembled Fitting Inspection

4.1 

Ring Advancement Inspection

After fitting installation, ring advancement should be verified using 

the inspection gauge P/N RTSG0-51-SIZE. The inspection gauge 

should fit over the ring area as shown in Figure 6A. Figure 6B shows 

an incomplete/incorrect swage.

Figure 6A

Complete ring advancement inspection.

Figure 6B

Complete ring advancement inspection.

4.1.1    Insertion Inspection Mark Position

The inspector should verify that the edge of the fitting is touching 

or over the insertion inspection marks after assembly as shown 

in Figure 6A. This is to ensure that the tube was inserted to the 

required depth.

4.2  

 Shared Insertion - Unions

In the case of unions, the tube insertion allowance is shared by each 

leg of the union. If one tube end is inserted to maximum depth, then 

the opposite tube end can only be inserted to a minimum depth, as 

shown in Figure 7. This shared insertion condition is only applicable 

to unions, which have a through bore to allow placement onto cut 

lines during repair. All other fittings have a positive stop in each leg, 

and the entire positioning length is available for each leg.

Note: 

Under maximum insertion condistions it will not be possible 

to see the inspection mark until after swage.

Figure 7

Shared insertion conditions

4.2.1  

Over Insertion Condition — Fittings Other Than Unions

All fittings other than unions, are designed with a positive tube stop 

or bottoming feature which prevents over insertion of the tube end 

during assembly, as shown in Figure 8. The exceptions are special 

bulkhead fittings, configurations of fittings with deep bores to save 

weight, special repair and penetration fittings, etc.. In these circum-

stances, the tube insertion guidelines and marking must be strictly 

adhered to in accordance with Figure 6A to ensure proper inspection 

procedures.

Note:

 It is necessary that tube marking procedures be adhered to 

for all Rynglok fittings.

Figure 8

Fittings with over insertion conditions

Summary of Contents for Aeroquip Rynglok Fitting System

Page 1: ...Rynglok Fitting System Installation Guide Aeroquip Rynglok Fittings...

Page 2: ...ressure 3 4 1 Pressure Level 4 0 Assembled Fitting Inspection 6 4 1 Ring Advancement Inspection 4 1 1 Insertion Inspection Mark Position 4 2 Shared Insertion Unions 4 2 1 Over Insertion Condition Fitt...

Page 3: ...tallation A suitable method such as ink stamp electro etch laser etc may be used Should the tube ends be unmarked the appropriate marks should be applied using Eaton s Aeroquip brand tube marking gaug...

Page 4: ...itting ring may be anywhere along the length of the positioning mark 2 1 1 End Fittings In general end fittings are designed to have the tube end bottomed into the fitting and do not have as much posi...

Page 5: ...nestled into the movable jaw of the tool and the front opening of the tool bottomed into the fitting body as shown in Figure 5A The tool is designed to access the fitting leg from any radial angle as...

Page 6: ...inserted to a minimum depth as shown in Figure 7 This shared insertion condition is only applicable to unions which have a through bore to allow placement onto cut lines during repair All other fitti...

Page 7: ...05 10 0 6250 3 18 11 0 6875 3 44 12 0 7500 3 56 13 0 8125 3 71 14 0 8725 3 88 15 0 9375 3 99 16 1 0000 4 15 20 1 2500 4 81 24 1 5000 5 42 Table 5 Figure 9 Defect Length Figure 10A Cutting through def...

Page 8: ...where there is an opposite fitting end or forging body size greater than the dash size of the fitting end being swaged as shown in Figure 13 These special Reversed Tools will be marked with a colored...

Page 9: ...reless Fitting Tube cut dimension as shown in Figure 16 shall use dimensions per Table 7 for proper installation Part No A 030 in Part No A 030 in R82101T03 0 602 R82101T10 979 R82101T04 0 616 R82101T...

Page 10: ...T R81101T Reducer R80151T R81171T R81191T R81151T 45 ELBOW Non Reducer R80102T R81122T R81142T R81102T Reducer R80152T R81172T R81192T R81152T 90 ELBOW Non Reducer R80103T R81123T R81143T R81103T Redu...

Page 11: ...2141T R82101T R83121T R83141T R83101T R82171T R82191T R82151T R83171T R83191T R83151T R82122T R82142T R82102T R83122T R83142T R83102T R82172T R82192T R82152T R83172T R83192T R83152T R82123T R82143T R8...

Page 12: ...ch 2013 Eaton Aerospace Group 9650 Jeronimo Road Irvine California 92618 Ph 949 452 9500 Fax 949 452 9555 www eaton com aerospace Eaton Aerospace Group Fluid Electrical Distribution Division 300 South...

Reviews: