3 - Initialization & Check Points
Once all of the cabling and installation procedures are finished, initialize
the system and perform the functional test in the following order.
Check carefully if there are any service failures or alarms during the test.
1) Check that all of the power switches have been turned off, and check polarity and
cable connection status using DVM.
2) Check that the input power has been correctly connected using DVM.
3) Check that the DC Output cables have been correctly connected, and check polarity.
4) Turn on the AC main Circuit Breaker.
5) Check that each installed Rectifier Module front panel LED is green, and verify that the
DC output voltage is correct.
3.1 Installation Check List
To check installation of the system, use the following procedure:
1) Check that the equipmment rack has been properly and firmly mounted to the floor.
2) Check that the dry contact alarms cable (optional) of the Control unit is connected.
3) Check if CIRCUIT BREAKER has been installed in the distribution frame of the
system.
4) Check if audible alarm switch of the control panel is ON.
5) Verify that the rack Frame Ground has been connected to the main ground busbar.
6) Check if the AC power ground is connected to the surge protector ground.
7) Check if the I/O cable has been correctly connected.
8) Verify that all installed rectifier modules have been fully inserted.
3.2 Rectifier Module Insertion & Removal
3.2.1 Rectifier Module Installation
Each Rectifier Module should be inserted into the shelf from the front. Insert each
module until it reaches the mating connector then push in the ejector to fully seat the
connectors. The ejector will easily lock into place when inserted and seated.