5.  Special Conditions for Safe Use 

 

Repair of the flamepath / flameproof joints is not permitted. 

 

The  enclosure  is  non-conducting  and  may  generate  an 
ignition-capable  level  of  electrostatic  charges  under  certain 
extreme conditions (such as high-pressure steam). The user 
should ensure that the equipment is not installed in a location 
where  it  may  be  subjected  to  external  conditions  that  might 
cause  a  build-up  of  electrostatic  charges  on  non-conducting 
surfaces. 

 

Additionally,  cleaning  of  the  equipment  should  be  done  only 
with a damp cloth. 

 

6.  Product Mounting and Access 

 

The location of the unit should be made with due regard to the 
area  over  which  the  warning  signal  must  be  visible.  They 
should only be fixed to services that can carry the weight of the 
unit. 

 

The BEx combined sounder beacon should be secured to any 
flat surface using at least two of the three 7mm fixing holes on 
the stainless steel U shaped mounting bracket. See Figure 1. 
The required angle can be achieved by loosening the two large 
bracket screws in the side of the unit, which allow adjustment 
of the sounder in steps of 18°. On completion of the installation 
then two large bracket adjustment screws on the side of the 
unit must be fully tightened to ensure that the unit cannot move 
in service. 

 

 

Fig. 1 Fixing Location for Combined Beacon/Beacon 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

7.  Access to the Flameproof Enclosure 

 

 

 

To  access  the  Ex  d  chamber,  remove  the  four  M6  hexagon 
socket head screws and withdraw the flameproof cover taking 
extreme  care  not  to  damage  the  flameproof  joints  in  the 
process. M6 cover screws are Class A4-80 stainless steel and 
only screws of this category can be used for the enclosure. 

 

Fig. 2 Accessing the Explosion proof Enclosure. 

 

On completion of the installation, the flameproof joints should 
be inspected to ensure that they are clean and that they have 
not been damaged during installation. 

 

Check that the earth bonding wire between the two castings is 
secure  and  the  ‘O’  ring  seal  is  in  place.  When  replacing  the 
flameproof  cover  casting  ensure  that  it  is  square  with  the 
flameproof  chamber  casting  before  inserting.  Carefully  push 
the cover in place allowing time for the air to be expelled. Only 
after  the  cover  is  fully  in  place  should  the  four  M6  Stainless 
Steel  A4-80  cover  bolts  and  their  spring  washer  be  inserted 
and tightened down. If the cover jams while it is being inserted, 
carefully remove it and try again. Never use the cover bolts to 
force the cover into position. 

 
 

 

Warning – High voltage may be present, 
risk of electric shock. DO NOT open when 
energised, disconnect power before 
opening. 

Warning – Hot surfaces. External surfaces 
and internal components may be hot after 
operation, take care when handling the 
equipment. 

(Appropriate cable glands 
to be customer supplied) 

Flameproof cover  

M6 Cover 
Screws 

M6 Spring 
Washer 

Flameproof 
Chamber  

Summary of Contents for BExCBL2-L2D-P

Page 1: ...ent taken by the various units Nominal current at nominal voltage Table 1 Electrical Ratings It is important that a suitable power supply is used to run the equipment The power supply selected must have the necessary capacity to provide the input current to all of the units The above table shows the input current taken by the various units and shows the maximum voltage at which they can be operate...

Page 2: ...ccur in normal operation and if it does it will only exist for a short time Gas Groupings Group IIA Propane Group IIB Ethylene Group IIC Hydrogen Acetylene Temperature Classification for Gas Applications T1 450o C T2 300o C T3 200o C T4 135o C T5 100ºC T6 85ºC up to 55ºC ambient Area Classification Dust Zone 21 Explosive dust air mixture likely to occur in normal operation Zone 22 Explosive dust a...

Page 3: ...d to ensure that the unit cannot move in service Fig 1 Fixing Location for Combined Beacon Beacon 7 Access to the Flameproof Enclosure To access the Ex d chamber remove the four M6 hexagon socket head screws and withdraw the flameproof cover taking extreme care not to damage the flameproof joints in the process M6 cover screws are Class A4 80 stainless steel and only screws of this category can be...

Page 4: ...n using the internal earth terminal ensure that the stainless steel M4 flat washer is between the incoming earth wire and the enclosure Internal earthing connections should be made to the Internal Earth terminal in the base of the housing using a ring crimp terminal to secure the earth conductor under the earth clamp The earth conductor should be at least equal in size and rating to the incoming p...

Page 5: ...mum resistance value of 3k3Ω and a minimum power rating of 0 5 watts or a minimum resistance value of 500Ω and a minimum power rating of 2 watts The resistor must be connected directly across the ve and ve terminals as shown in the following drawing The resistor leads should be kept as short as possible Fig 7 End of Line Resistor Placement 13 Flash Rate Settings The BExB2L2D beacons can produce di...

Page 6: ... Repair Maintenance repair and overhaul of the equipment should only be carried out by suitably qualified personnel in accordance with the current relevant standards EN60079 19 IEC60079 19 Explosive atmospheres Equipment repair overhaul and reclamation EN 60079 17 IEC60079 17 Explosive atmospheres Electrical installations inspection and maintenance The acoustic horn is made out of ABS plastic ther...

Page 7: ...5W MIN MINIMUM VALUES R1 Single Stage Configuration Simultaneous Operation Config 1a Line Monitoring Stage 1 only Negative switching Stage 1 Flash Pattern Apply Power to Stage 1 ve Stage 1 ve Stage 2 Flash Pattern Apply Power to Stage 1 ve Stage 1 ve Connect Stage 2 to ve Stage 3 Flash Pattern Apply Power to Stage 1 ve Stage 1 ve Connect Stage 3 to ve 24 03 2022 24 03 2022 24 03 2022 BExBGL2D BExC...

Page 8: ...NTS 1 1 Single Stage Configuration Simultaneous Operation Config 1a Line Monitoring Stage 1 only Negative switching Stage 1 Flash Pattern Apply Power to Stage 1 ve Stage 1 ve Stage 2 Flash Pattern Apply Power to Stage 1 ve Stage 1 ve Connect Stage 2 to ve Stage 3 Flash Pattern Apply Power to Stage 1 ve Stage 1 ve Connect Stage 3 to ve 24 03 2022 24 03 2022 24 03 2022 BExBGL2D BExCBL2 L2D DC LED LE...

Page 9: ...uality Assurance Notification ModuleD SIRA 05 ATEX M342 Provisions fulfilledby theequipment II 2G Ex db IIB T6 to T4 Gb II 2D Ex tb IIIC T65 C to T130 CDb IP6X Dust Protectionto EN60079 0 EN60079 31 Standards applied EN 60079 0 2012 A11 2013 EN IEC 60079 0 2018 EN 60079 1 2014 EN 60079 31 2014 IP6X Dust Protectionto EN60079 0 EN60079 31 Directive 2014 30 EU Electromagnetic Compatibility Directive ...

Page 10: ...er Date andPlace of Issue London 23 12 2020 EU Declaration of Conformity On behalf of European SafetySystems Ltd I declarethat on the date the equipment accompanied by this declaration is placed onthemarket theequipment conforms with alltechnical andregulatory requirements oftheabovelisteddirectives regulations and standards This Declaration is issued under thesole responsibility ofthemanufacturer...

Page 11: ... Chester CH4 9JN UK Quality Assurance Notification Module D CSAE 22UKQAN0046 Provisions fulfilled by the equipment II 2G Ex db IIB T6 T4 Gb II 2D Ex tb IIIC T65 C T130 Db IP6X Dust Protection to EN60079 0 EN60079 31 Standards applied EN IEC 60079 0 2018 EN 60079 1 2014 EN 60079 31 2014 Directive 2014 30 EU Electromagnetic Compatibility Directive EMC Standards applied EN 61000 6 1 2007 EN 61000 6 2...

Page 12: ... and Place of Issue London 12 09 2022 UKCA Declaration of Conformity On behalf of European Safety Systems Ltd I declare that on the date the equipment accompanied by this declaration is placed on the market the equipment conforms with all technical and regulatory requirements of the above listed directives regulations and standards This Declaration is issued under the sole responsibility of the ma...

Reviews: