11
3.6.2. Installation of the sensing probe into the MultiController
Make sure that the pipe line is depressurized!
•
Remove transport protection cap of the head of the sensing probe.
•
Mount the sensing probe in the MultiController in such a way that the alignment pin fits in the
recess on the MultiController.
•
Screw the retainer nut by hand so far that a certain resistance is noticeable.
•
Check the correct installation position of the flowmeter. The alignment pin must fit in the recess on
the ball valve.
•
Tighten the red coloured retainer nut by hand. Tightening by hand should be sufficient. However, if
the seal is not leak tight carefully tighten the nut with an appropriate tool a bit further
•
The mechanical installation of the flowmeter is therewith completed.