10
3.5. Assembly of the measurement section
In order to install or remove the measurement section the pipeline system
should be depressurized.
•
All connections to be made with appropriated sealing material on the threads.
•
The sealing material should not change the area of the inner cross section of the pipe. It must be
warranted that the connections after installation are free of leaks.
•
All fittings must be tested on seal tightness.
•
Make sure during the assembly of the measurement section that the arrows on the pipe section
and the ball valve are pointing in the same direction as the flow.
•
The recess for the alignment pin must be at the side of the outlet.
3.5.1. Assembly without flowmeter, but with screw cap instead (blind cap)
In order to use the measurement section without the flowmeter, the blind screw cap
(in the scope of supply) must be screwed tight onto the opening of the MultiController.
If not needed the screw cap can be screwed and stored on the side of the
MultiController.
recess for
alignment pin
3.6. Installation of the flowmeter sensing probe
3.6.1. Flow direction
The flow direction is indicated with an arrow on the tip of the probe. Due to the alignment pin is the installation
of the sensing probe in the MultiController only possible in the direction of the flow. After a removal, the sens-
ing probe will be re-installed in the measurement section in exactly the same position as done at the factory.
Hence, the highest reproducibility is guaranteed.
Use sealing
material!
Flow Direction
Flow
Direction