background image

TUF 50 WALL CLADDING 

fig. 1 

fig. 2 

To Avoid Corrosion: 

Where at all possible try not to trap metal filings between two sheets. Remove all metal filings before riveting. 

Carbon in pencils reacts with the Zinc/Aluminium coating on steel. Use ink to mark steel. 

Step 1:

 Door  Jambs:  Position  left  hand  Door  Jamb  Flashing  at 

correct  measurement  from  left 

(cladding  detail)

  and  nail 

to Top Plate using a 30mm clout. Do not fit 50mm nails at 
this stage. Pre-drill holes to make nailing easier 

(fig. 1)

 

 

Position Door Jamb Flashing and nail at the bottom. Posi-
tion  right  hand  Door  Jamb  Flashing  903mm  from  left 
hand  Door  Jamb  Flashing 

(cladding  detail)

  and  nail  in 

place. 

 

903mm 

180mm 

D008 

CLADDING DETAIL 

Birds Eye View 

FRONT VIEW 

DOOR JAMB 
FLASHING 

Summary of Contents for TUF 50

Page 1: ...Quality Made Affordable ASSEMBLY INSTRUCTIONS TUF 50 BASE SIZE 1140mm x 1355mm...

Page 2: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools w...

Page 3: ...lashing Hardware Pack 2 1 1 890 1 160 1 1 175 Red 45 x 45 H1 Red 70 x 45 H1 Red 45 x 45 H1 Yellow 45 x 45 H1 FLASHINGS Door Jambs Top Plate Flashing PACKED BY DATE BASE SIZE 1 140 x 1 355 TOP PLATES T...

Page 4: ...ns to Red See fig 2 for nailing detail on Top Front Plate 70x45mm Step 3 Position remaining End Frame on top of plates While someone sup ports frame nail in place using two 75mm nails per join Step 4...

Page 5: ...oor Jambs Position left hand Door Jamb Flashing at correct measurement from left cladding detail and nail to Top Plate using a 30mm clout Do not fit 50mm nails at this stage Pre drill holes to make na...

Page 6: ...clout top and bottom Step 5 Drill a hole through Door Jamb Flashings and Wall Sheets top and bottom Nail with 50mm nails fig 1 Nail left hand Door Jamb Flashing to Stud using three 30mm Clouts at equ...

Page 7: ...nd back Fit one more rivet evenly spaced in centre of each join Step 3 Line up ribs on the roof with ribs on the walls While someone holds the Front Plate straight nail the roof to Top Plate using one...

Page 8: ...ate Flashing and fit one rivet to top hinge While still holding in position fit one rivet to bottom hinge Step 3 Close door and check it fits correctly If not drill out rivets and make necessary adjus...

Page 9: ...RITY DOOR Optional Step 1 Place shed in final position Check diagonal meas urements are equal and shed is level before fitting door Step 2 Hold Door in position approximately 5mm down from Top Plate F...

Page 10: ...Floor Joist For sheds being placed on a purpose built floor we recommend that the studs are shortened by 30mm The Wall Sheets will then protrude 20mm below the Base Plate This will stop water flowing...

Page 11: ...in most environments The surface must be dry and free of dirt oil grease and other contaminants prior to painting but no weathering of the surface is required Zinc rich primers are recommended for use...

Page 12: ...nd very severe environmental situations or in any area where the mild steel corrosion rate as published by BRANZ exceeds 200g m2 3 Minimum maintenance must be carried out in accordance with instructio...