MK4A LOUVRE WINDOW (Optional)

 

Step 2:

 

On  the  inside  of  the  shed,  position  studs 
and  Nog  centrally  on  window  opening. 
Make  sure  the  studs  are  parallel  and  nail 
into Top Plate and end wall Nog.

 

Step 3:

 

Nail  wall  Sheets  to  window  framing  using 
30mm  clouts.  (return  to  step  4  on  page  7 
and  complete).  Then  fit  Window  Frame). 
Position  Window  Frame  centrally  on  win-
dow  opening  and  rivet  it  to  ribs.  Pre

-

drill 

holes  in  each  corner  and  nail  Window 
Frame to framing, using 50mm nails.

 

Step 4:

 

If  the  Window  is  in  the  gable  end,  tempo-
rarily  position  the  Over  Panel  above  Win-
dow  Frame.  Following  the  same  angle  as 
the gable, mark and cut to suit.

 

Step 5:

 

Rivet  Over  Panel  to  the  Window  Frame 
with rivets.

 

588mm

 

Step 1:

 

Lay out the two window studs (883mm) and 
Nog  (634mm)  on  a  flat  surface.  Position 
Nog and nail in place using 2x 75mm nails 
at each end.

 

Step 6:

 

From  the  inside  of  the  shed,  slide  Louvre 
Glass  into  Louvre  Units  attached  to  the 
Window  Frame.  Bend  up  tabs  to  keep 
Glass in position.

 

50mm

 

NAILS

 

RIVITS

 

Summary of Contents for SHEDS MK4A

Page 1: ...Quality Built In ASSEMBLY INSTRUCTIONS MK4A BASE SIZE 4 210mm x 2545mm...

Page 2: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools wi...

Page 3: ...0 710 x 0 240m 1 Fixed Window Frame Glaze Beads Glass Louvre Window Frame Glass Over Panel Window Hardware Pack 2 830m 1 415m 1 415m 1 175m 1 Roof Sheets Flat Roof Sheet Clear Roof Panel Ridge Flashin...

Page 4: ...Base Plate only YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW 1 810 45 45 45 45 1185 1185 1660 4210 45 45 45 FRONT WALL 45 45 45 45 1343 1343 1343 4210 45 45 45 BACK WALL 1900...

Page 5: ...75mm nails per end Note If fitting a window there will be no centre stud on the window side Instead nail in a full length nog 2 405 in Gable or 4 120 in Back Wall using window studs 883 to get correct...

Page 6: ...ack on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be re positioned the nails can easily be prized out If a window is require...

Page 7: ...lap as shown in fig 1 Ensuring Wall Sheet is flush with top of Top Plate tack in place Re peat with remaining three sheets Step 4 Nailing Off Nail one 30mm Clout each side of the Rib two per Pan into...

Page 8: ...ill holes in each corner and nail Window Frame to framing using 50mm nails Step 4 If the Window is in the gable end tempo rarily position the Over Panel above Win dow Frame Following the same angle as...

Page 9: ...tom Plates and hard against Stud Attach Door Jamb Flashing with three rivets into Rib on the outside and three 30mm clouts into studs on the inside Repeat with the other Door Jamb Step 3 Fit Corner Fl...

Page 10: ...gs Also make sure the Wheels are cleaned of drill filings Re hang Doors Fit outer door stops Predrill a hole at each end of track into rib of cladding and screw outer door stops in using one Roofing s...

Page 11: ...ed with pieces of timber from the packaging Step 3 Starting from the left hand end centralize Roof on Ridge Beam Ensure Roof is tight against end Wall Sheets predrill then nail one 50mm Clout through...

Page 12: ...ews Screw one 50mm roofing screw into ridge beam through each rib on overlap one screw per sheet Mould the soft edge on the flashing down into the pans of the roof sheet to prevent roof leaks Step 4 C...

Page 13: ...Rib MK4A FLOOR Step 1 Place shed in final position Check the diagonal measurements are the same and the shed is level before fitting Floor It is recommended that the shed is anchored down with either...

Page 14: ...Door without the weather strip Slide hook onto square shaft and secure with a lock washer Hook Lock Washer Step 2 Once doors are hung position the Locking Stays so they slide into the Locking Brackets...

Page 15: ...Plate This will stop water flowing in between the Base Plate and Floor The Floor should be made 15mm smaller than Base Size Note Although it is not essential fitting Damp Proof Course in between the B...

Page 16: ...rried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the d...

Reviews:

Related manuals for SHEDS MK4A