MK4A WALL CLADDING

 

Step 1:

 

Front  Wall:

 Start at the left hand side. Position 

the  Wall  Sheet  with  the  LIP  on  the  left  hand 
side.  Ensuring  the  LIP  is  flush  with  side  of  the 
Stud and the top of the Top Plate, tack in place. 
Repeat  with Wall  Sheet  on  the  right  hand  side 
of  doorway.  Ensure  Rib  without  LIP  is  on  the 
right hand side of stud then tack in place. Posi-
tion 1/2 Wall Sheets as shown  in the Cladding 
Detail and tack in place.

 

Step 2:

 

Back  Wall:

  Position  the  first  Wall  Sheet  with 

the LIP on the right hand side. Ensuring the LIP 
is flush with the side of the Studs and the top of 
the Wall  Sheet  is  flush  with  the  top  of  the  Top 
Plate,  tack  in  place.  Position  the  next  Wall 
Sheet with the LIP on the right hand side. Over-
lap as shown in (fig 1). Ensuring Wall Sheet is 
flush  with  top  of  Top  Plate,  tack  in  place.  Re-
peat with remaining three sheets.

 

Step 4:

 

Nailing  Off:

 Nail one 30mm Clout each side of the Rib (two per Pan) into the Top Plates and Bottom Plates. Nail       

Wall Sheets to mid wall Nogs (one per pan). Nail each corner Wall Sheet to Studs using two 30mm Clouts evenly 
spaced.

 

 

Gable Ends: When nailing Gable Wall Sheets to the Top Plate, use a String Line. At the top of the gable nail two 
30mm Clouts into the end of the Ridge Beam. This will stop it from twisting.

 

Step 3:

 

End  Walls:

  Lean  Gable  Wall  Sheets  against 

the  shed  to  form  gable  shape.  With  the  LIP 
flush  with  side  of  Stud  tack  in  place  ensuring 
the  bottom  of  the  Wall  Sheet  is  10mm  above 
the  bottom  of  the  Bottom  Plate.  Tack  on  re-
maining Wall  Sheets.  Repeat  with  other  gable 
end.  If  fitting  a  window,  nail  in  Window  Studs 
and Nog now. Refer to Window instructions.

 

7

 

EDGE 

 

FLUSH

 

TOP

 

FLUSH

 

Summary of Contents for SHEDS MK4A

Page 1: ...Quality Built In ASSEMBLY INSTRUCTIONS MK4A BASE SIZE 4 210mm x 2545mm...

Page 2: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools wi...

Page 3: ...0 710 x 0 240m 1 Fixed Window Frame Glaze Beads Glass Louvre Window Frame Glass Over Panel Window Hardware Pack 2 830m 1 415m 1 415m 1 175m 1 Roof Sheets Flat Roof Sheet Clear Roof Panel Ridge Flashin...

Page 4: ...Base Plate only YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW 1 810 45 45 45 45 1185 1185 1660 4210 45 45 45 FRONT WALL 45 45 45 45 1343 1343 1343 4210 45 45 45 BACK WALL 1900...

Page 5: ...75mm nails per end Note If fitting a window there will be no centre stud on the window side Instead nail in a full length nog 2 405 in Gable or 4 120 in Back Wall using window studs 883 to get correct...

Page 6: ...ack on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be re positioned the nails can easily be prized out If a window is require...

Page 7: ...lap as shown in fig 1 Ensuring Wall Sheet is flush with top of Top Plate tack in place Re peat with remaining three sheets Step 4 Nailing Off Nail one 30mm Clout each side of the Rib two per Pan into...

Page 8: ...ill holes in each corner and nail Window Frame to framing using 50mm nails Step 4 If the Window is in the gable end tempo rarily position the Over Panel above Win dow Frame Following the same angle as...

Page 9: ...tom Plates and hard against Stud Attach Door Jamb Flashing with three rivets into Rib on the outside and three 30mm clouts into studs on the inside Repeat with the other Door Jamb Step 3 Fit Corner Fl...

Page 10: ...gs Also make sure the Wheels are cleaned of drill filings Re hang Doors Fit outer door stops Predrill a hole at each end of track into rib of cladding and screw outer door stops in using one Roofing s...

Page 11: ...ed with pieces of timber from the packaging Step 3 Starting from the left hand end centralize Roof on Ridge Beam Ensure Roof is tight against end Wall Sheets predrill then nail one 50mm Clout through...

Page 12: ...ews Screw one 50mm roofing screw into ridge beam through each rib on overlap one screw per sheet Mould the soft edge on the flashing down into the pans of the roof sheet to prevent roof leaks Step 4 C...

Page 13: ...Rib MK4A FLOOR Step 1 Place shed in final position Check the diagonal measurements are the same and the shed is level before fitting Floor It is recommended that the shed is anchored down with either...

Page 14: ...Door without the weather strip Slide hook onto square shaft and secure with a lock washer Hook Lock Washer Step 2 Once doors are hung position the Locking Stays so they slide into the Locking Brackets...

Page 15: ...Plate This will stop water flowing in between the Base Plate and Floor The Floor should be made 15mm smaller than Base Size Note Although it is not essential fitting Damp Proof Course in between the B...

Page 16: ...rried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the d...

Reviews: