Step 1:

 

Position  Right

-

hand  Door  Track  (107)  on  the  front  wall  with  the 

top of the track 7mm below the top of the timber frame. The left

-

hand end should be 20mm to the right of centre of shed. (Ie Door 
tracks will be 40mm apart) 

 

 

Pre

-

drill a hole in the centre of the track and screw in place using 

one 45mm door track screw. Remove ALL drill filings

 

Note:  Ensure  Door  Track  screws  are  screwed  in  horizontal    and 

screwed  hard  into  flashing.  Protruding  screw  heads  can 
cause door rollers to bind on the screw heads.

 

 10

 

MK4A DOORS

 

Step 3:

 

Position left hand Door Track (107). Follow Steps 1 and 2 to hang 
left hand Door. Where Door Tracks meet in the centre, adjust up 
and  down  so  that  the  Doors  fit  snuggly  together,  then  rivet  in 
place. 

 

Step 2:

 

Hang right hand door in Door Track. At the right hand end of Door 
Track,  adjust  up  or  down  so  that  the  Door  hangs  parallel  with 
shed. Fit one rivet at right hand end to hold in place. Repeat with 
left hand end of track.

 

Note: Only use rivets at each end of track.

 

Step 4:

 

Remove  Doors.  Pre

-

drill  and  screw  another  2  screws  between 

the  centre  screw  and  the  rivets  at  each  end  of  tracks(5  screws 
per track). Screw tracks using 45mm door track screws.

 

Step 5:

 

Clean  out  ALL  drill  filings.  Also  make  sure  the  Wheels  are 
cleaned of drill filings. Re

-

hang Doors.  

 

Fit outer door stops. Predrill a hole at each end of track, into rib of cladding 

and screw outer door stops in using  one Roofing screw per stop.

 

Fit inner door stops. Predrill a hole 45mm each side of doorway centre and 

screw inner door stops in using  one Roofing screw per stop.

 

Note–

 

adjust    centre  door  stops  left  and  right  to  ensure  doors  close      

correctly.

 

MK4A DOORS

 

Step 5:

 

Bottom Door Guide: Slide the Door to open position. Place  the 
Door Guide (108) over the Guide Brackets on the door. Ensure 
it is 20mm from centre of door opening. 

 

Step 6:

 

Lift the door guide up approximately 3mm so that the Door will 
Slide freely. Pre

-

drill a hole through the door guide and the end 

rib of the cladding and screw in place using a 45mm screw. 

 

Step7:

 

Slide the door to the centre, ensuring that it slides freely. Pre

-

drill and insert a screw in the other end of the Door Guide. 
Check that the Door is not binding in the middle then pre

-

drill 

and fix with 3 more screws, one in the centre of the guide and 
the other 2 evenly spaced between (5 screws per guide)  into 
the door step flashing and rib. Repeat with 2nd door.

 

Note:

 

For sheds with Raised Base Plate option the Door Step Flash-
ing will protrude down past the Bottom Plate.

 

Attach Door Guide with rivets.

 

DOOR

 

GUIDE   

 

DOOR       

 

CLADDING

 

BOT-

PLATE

 

GUIDE BRACKET

 

7mm

 

45mm

 

Centre of 

 

Doorway

 

Centre of Doorway

 

Summary of Contents for SHEDS MK4A

Page 1: ...Quality Built In ASSEMBLY INSTRUCTIONS MK4A BASE SIZE 4 210mm x 2545mm...

Page 2: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools wi...

Page 3: ...0 710 x 0 240m 1 Fixed Window Frame Glaze Beads Glass Louvre Window Frame Glass Over Panel Window Hardware Pack 2 830m 1 415m 1 415m 1 175m 1 Roof Sheets Flat Roof Sheet Clear Roof Panel Ridge Flashin...

Page 4: ...Base Plate only YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW 1 810 45 45 45 45 1185 1185 1660 4210 45 45 45 FRONT WALL 45 45 45 45 1343 1343 1343 4210 45 45 45 BACK WALL 1900...

Page 5: ...75mm nails per end Note If fitting a window there will be no centre stud on the window side Instead nail in a full length nog 2 405 in Gable or 4 120 in Back Wall using window studs 883 to get correct...

Page 6: ...ack on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be re positioned the nails can easily be prized out If a window is require...

Page 7: ...lap as shown in fig 1 Ensuring Wall Sheet is flush with top of Top Plate tack in place Re peat with remaining three sheets Step 4 Nailing Off Nail one 30mm Clout each side of the Rib two per Pan into...

Page 8: ...ill holes in each corner and nail Window Frame to framing using 50mm nails Step 4 If the Window is in the gable end tempo rarily position the Over Panel above Win dow Frame Following the same angle as...

Page 9: ...tom Plates and hard against Stud Attach Door Jamb Flashing with three rivets into Rib on the outside and three 30mm clouts into studs on the inside Repeat with the other Door Jamb Step 3 Fit Corner Fl...

Page 10: ...gs Also make sure the Wheels are cleaned of drill filings Re hang Doors Fit outer door stops Predrill a hole at each end of track into rib of cladding and screw outer door stops in using one Roofing s...

Page 11: ...ed with pieces of timber from the packaging Step 3 Starting from the left hand end centralize Roof on Ridge Beam Ensure Roof is tight against end Wall Sheets predrill then nail one 50mm Clout through...

Page 12: ...ews Screw one 50mm roofing screw into ridge beam through each rib on overlap one screw per sheet Mould the soft edge on the flashing down into the pans of the roof sheet to prevent roof leaks Step 4 C...

Page 13: ...Rib MK4A FLOOR Step 1 Place shed in final position Check the diagonal measurements are the same and the shed is level before fitting Floor It is recommended that the shed is anchored down with either...

Page 14: ...Door without the weather strip Slide hook onto square shaft and secure with a lock washer Hook Lock Washer Step 2 Once doors are hung position the Locking Stays so they slide into the Locking Brackets...

Page 15: ...Plate This will stop water flowing in between the Base Plate and Floor The Floor should be made 15mm smaller than Base Size Note Although it is not essential fitting Damp Proof Course in between the B...

Page 16: ...rried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the d...

Reviews:

Related manuals for SHEDS MK4A