MK2 CLEAR ROOF PANEL (Optional)

 

12

 

TOP PLATE

 

JACK STUD

 

RIDGE BEAM

 

30mm CLOUT

 

RIDGE FLASHING

 

ROOFING SCREWS

 

PRESSED ROOF SHEET

 

CLEAR ROOF

 

FLAT ROOF

 

Step 2:

 

Position clear roof and flat roof sheet (or second clear panel). The flat roof sheet underlaps one sheet and overlaps the other. 
The clear roof panel 

overlaps 

both roof sheets. Ensure sheet joins are flush at the outside edge then rivet flat sheets to pressed 

sheets. Two rivets per join. Centralise roof at the other end and screw in place.

 

 

Step 3:

 

Ensure ridge beam is straight, then nail the clear panel and flat roof sheet (or second clear panel) to ridge beam using one 
30mm clout per pan. Position on ridge beam and screw in place using six 50mm roofing screws. Screw one 50mm roofing 
screw into ridge beam through each rib on overlap, (one screw per sheet). Mould the soft edge on the flashing down into the 
pans of the roof sheet to prevent roof leaks.

 

Step 4:

 

Continue to fasten roof sheets as per step 4 on previous page (pg10)

 

Note:

 

When screwing through the clear panel, pre

-

drill a 6mm hole.

 

Step 1:

 

Leave a gap where the Clear Panel is to be fitted. Position the next Roof Sheet. Ensure it overlaps correctly, then rivet togeth-
er, one rivet in the centre and one approximately 600 mm down from the centre on both sides. Fit remaining Roof Sheets, 
overlapping and riveting as you go. Nail on first Roof Sheet (refer step 3 on page 10).

 

Summary of Contents for SHEDS MK2

Page 1: ...Quality Built In ASSEMBLY INSTRUCTIONS MK2 BASE SIZE 2545mm x 1715mm...

Page 2: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools wi...

Page 3: ...150m 0 710 x 0 240m 1 Fixed Window Frame Glaze Beads Glass Louvre Window Frame Glass Over Panel For Gable ends only Window Hardware Pack 2 000m 1 000m 1 000m 1 175m 1 Roof Sheets Flat Roof Sheet Clea...

Page 4: ...LLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW 45 45 785 2545 45 45 45 FRONT WALL 883 45 795 45 785 45 45 1205 2545 45 45 45 BACK WALL 883 45 1205 1900 or 1870 for Raised Base Plate only 1900 or 1870...

Page 5: ...e over onto its base Pieces of timber from the packaging may be used to temporarily brace the frame before rolling it over Position 1 625 End Wall Nogs 883m down from Top Plate and nail in place If fi...

Page 6: ...N To Tack To Tack on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be re positioned the nails can easily be prized out If a win...

Page 7: ...tack in place Re peat with remaining sheet Step 4 Nailing Off Nail one 30mm Clout each side of the Rib two per Pan into the Top Plates and Bottom Plates Nail Wall Sheets to mid wall Nogs one per pan...

Page 8: ...ll holes in each corner and nail Window Frame to framing using 50mm nails Step 4 If the Window is in the gable end tempo rarily position the Over Panel above Win dow Frame Following the same angle as...

Page 9: ...tom Plates and hard against Stud Attach Door Jamb Flashing with three rivets into Rib on the outside and three 30mm clouts into studs on the inside Repeat with the other Door Jamb Step 3 Fit Corner Fl...

Page 10: ...hole in right hand end of track 45mm in from outside edge of Corner Flashing Predrill hole in left hand end of track 45mm from outside of door jamb 60mm for Security door option Screw door stops in u...

Page 11: ...to Back Top Plate Repeat at the front Note The 6 x 50mm Clouts on end ribs are covered by the Barge Flashings Step 2 Position first Roof Sheet centrally over Ridge Beam on the right hand end of shed w...

Page 12: ...r panel to ridge beam using one 30mm clout per pan Position on ridge beam and screw in place using six 50mm roofing screws Screw one 50mm roofing screw into ridge beam through each rib on overlap one...

Page 13: ...straight then rivet to Roof one rivet every second Rib Note MK2 shown Note MK2 shown MK2 FLOOR Optional Step 1 Place shed in final position Check the diagonal measurements are the same and the shed is...

Page 14: ...into Joists Measure and cut Floor Flashing 110 to fit in between Door Jamb Flash ings and nail in place using 50mm Clouts MK2 HASP STAPLE Using six rivets and one 50mm clout attach hasp to Door Jamb F...

Page 15: ...on a purpose built floor concrete cob bles ply etc the Wall Sheets will protrude 20mm below the Base Plate This will stop water flowing in between the Base Plate and Floor The Floor should be made 15...

Page 16: ...rried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the d...