Duratuf KIWI KL1 Assembly Instructions Manual Download Page 5

KL1 TIMBER FRAME

 

5

 

Step 2:

 

Select  one  1.715m  Base  Plate  (Green),  one 
1.715m  Top  Plate  (Red).  Stand  up  End  frame 
with  the  Stud  side  of  the  frame  on  the  ground. 
Nail  1.715m  plates  to  frame  using  two  nails  per 
join. Ensure Green joins to Green and Red joins 
to  Red.  Repeat  with  other  end  frame.  Position 
1.625m  Back  Wall  Nog  .883m  down  from  the 
Top Plate and nail in place.

 

4

 

3

 

2

 

5

 

Step  1:  End  Walls:

 Select one 1.210m End Base Plate 

(Green),  one  1.210m  End  Top  Plate  (Red)  and 
two Studs (Yellow). Lay out Plates and two Studs 
on  a  flat  surface  and  nail  together  using  two 
75mm nails per join. Position 1.120m Nog .883m 
down  from  Top  Plate  and  nail  in  place.  Repeat 
with other end wall.

 

Step 3:

 

Select  one  1.715m  Base  Plate  (Green)  and  the 
Ridge  Beam  (90  x  45).  Nail  in  place.  Ensure 
Green joins to Green.

 

Step 4:

 

Carefully  roll  the  frame  over  so  that  the  Ridge 
Beam  and  Base  Plate  (Green)  are  on  the 
ground.  Select  a  stud  (Yellow)  and  one  .785m 
Nog. Nail in Stud using the .785m nog to get the 
correct  position  top  and  bottom.  Position 
nog  .883m  down  from  the  Top  Plate  and  nail  in 
place.

 

Step 5:

 

Carefully roll frame over onto its base. If fitting a 
Kiwi  Floor,  fit  Floor  Joists  now.  Place  the  joist 
centrally and nail in place using three 75mm nails 
per end.

 

1

 

Note:

 

Studs and Nogs surrounding a window opening are to be fitted once the wall cladding is nailed in place.

 

Note:

 

For sheds with the Raised Floor Modification option the studs will be 1.780m long to allow the Wall Sheets to pro-
trude 20mm below the Bottom Plate. Refer to Raised Floor Modification section (Page 15).

 

Summary of Contents for KL1

Page 1: ...Quality Built In ASSEMBLY INSTRUCTIONS KL1 BASE SIZE 1715mm x 1210mm...

Page 2: ...checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools wi...

Page 3: ...580m 0 603 x 0 603m 0 588 x 0 150m 1 Fixed Window Frame Glaze Beads Glass Louvre Window Frame Glass Window Hardware Pack 1 450m Clear Roof Panel Security Single Door Hardware Pack Alarm MA20 Shed lig...

Page 4: ...RAME 4 1 810 YELLOW YELLOW YELLOW YELLOW YELLOW 45 45 1120 1210 45 45 45 END WALL 883 45 45 795 1715 90 45 45 FRONT WALL 883 45 785 1900 or 1870 for Raised Base Plate only 1945 or 1915 for Raised Base...

Page 5: ...p 3 Select one 1 715m Base Plate Green and the Ridge Beam 90 x 45 Nail in place Ensure Green joins to Green Step 4 Carefully roll the frame over so that the Ridge Beam and Base Plate Green are on the...

Page 6: ...el Use either crayon or ink to mark steel TERMS EXPLANATION To Tack To Tack on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be...

Page 7: ...th the LIP on the right hand side Over lap as shown in fig 1 Ensuring Wall Sheet is flush with top of Top Plate tack in place Step 4 Nailing Off Nail one 30mm Clout each side of the Rib two per Pan in...

Page 8: ...Lay out the two window studs 883mm and Nog 634mm on a flat surface Position Nog and nail in place using 2x 75mm nails at each end Step 6 From the inside of the shed slide Louvre Glass into Louvre Uni...

Page 9: ...lashing 106 to fit in between Door Jambs Position the Door step Flashing in between the Door Jambs at bottom of doorway nail through top of flashing using three 30mm Clouts Repeat with the Overdoor Fl...

Page 10: ...f the Door Guide 20mm in from outside of the right hand corner flashing Step 6 Lift the door guide up approximately 3mm so that the Door will Slide freely Pre drill a hole through the door guide and t...

Page 11: ...ground it may be necessary to temporarily brace the shed with pieces of timber from the packaging Step 3 Position roof so that the front overhang measures 140mm Line up Ribs on the Roof Sheets with R...

Page 12: ...to the Barge Flashing at each end Repeat with other Spouting Step 2 Centralise Barge Flashing on end and rivet in place one rivet into every second Rib Fit two rivets through top of Barge into Rib Re...

Page 13: ...a Floor Board on top of Bottom Plates and Joist and push up against end wall Mark out where Studs are Cut checkouts with Electric Jigsaw so Floor Board will fit around Studs Step 3 Re position Floor...

Page 14: ...ote See below for security option 14 SECURITY DOOR Optional Step 2 Once door is hung position the Locking Stays so they slide into the Locking Brack ets easily Screw Locking Stays to Door Jamb Step 1...

Page 15: ...lthough it is not essential fitting Damp Proof Course in between the Base Plate and the Floor will give added protection against moisture CLEAN UP Remove all swarf drill filings with a soft brush or r...

Page 16: ...rried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the d...

Reviews: