Commissioning

It is strongly recommended that this detector should be commissioned by Duomo Commissioning Engineers or
engineers approved by Duomo to carry out this work. A quotation for commissioning or service will be provided upon
request. Fax site details and preferred date for commissioning to 01905 774296 and the Duomo Service Department will
fax back confirmation.

The benefits of this equipment being commissioned by Duomo are:

On board spares. If for whatever reason this equipment doesn't function correctly Duomo engineers will have spares on
board to ensure that the commissioning is successful.

A Duomo Commissioning Certificate is provided.

It is prudent to make electrical connection to the detector terminal plus when withdrawn and leave the plug off the
detector so that the Duomo Engineer is the first to power up the unit on site. This allows wiring to be checked prior to
commissioning and avoids damage due to incorrect connection. Guarantees for this product will become void if damage
is caused by the installer.

Technical specification

Power Supply

230V AC 50Hz +/- 10%

Secondary Battery

12V DC +/- 10%

Power Consumption

30W maximum @ 230V

Power Consumption

25W maximum @ 12V

Relay contact range

10A 230V resistive - 5A 30V DC resistive

1

st

pre-alarm

Can be set from 8% L.E.L. (120

ppm)

to 13% (250

ppm

) of LEL

Main alarm

Fixed at 20% L.E.L. / 300

ppm

Sensor fault

Short circuit, interruption, sensor deterioration

No. of remote sensors

16

MIcro switches to include/exclude sensors

1 per sensor

Monitored gas indication

Through illuminated display

Input signal

4 - 20mA

Device precision

1% FS

Reaction time

<10 seconds

Microprocessor

8 bytes

Working temperature

-10 °C to 45 °C

Start-up self diagnostic delay

90 seconds

Suitable for use with sensor type

SG500, SG590, SGM595, CO100A, CO200A, SG810

Maximum distance for sensor connection

100

m

Cable diameter for sensors

1

mm2

CSA

Dimemsions

360

mm

x 320

mm

x 135

mm

Protective rating

IP55

Guarantee

3 years from date of manufacture

Duomo gas proving systems - Duomo gas detection - Duomo carbon dioxide sensors - Duomo ventilation interlocks - Are available direct or from all major stockists - www.duomo.co.uk

Summary of Contents for BX116

Page 1: ...ly and alarm circuit wiring and the second is for connecting the sensor wiring This reduces the chance of incorrect site wiring The front panel has two banks of eight lights indicating in rotation which probe is currently monitoring and a bright display showing the LEL or PPM gas concentration measured Operation When the remote sensor detects the presence of the target gas a 4 20mA signal is sent ...

Page 2: ...ated 11 Main Alarm Zone 2 20 L E L concentration of gas detected in Zone 2 Main alarm relay actuated 12 LEL L E D This lights when the jumper switch for display data is set to read in lower explosive limit LEL 13 Zone 2 Indication These L E D s represent the Zone 2 sensors and flash when a sensor is connected 14 No of Sensors Switches DIP switches allowing you to select how many sensors can be att...

Page 3: ...ed using this particular board and therefore will not function correctly with any other Important Notes Always check the wiring before powering up the system Do not test this sensor with anything other than Duomo test gas see BX116 Operation section for further information Concentrations above this will damage the sensor and shorten sensor life The installation of this gas detector does not releas...

Page 4: ...play units The BX116 can display the current gas concentration detected in either LEL or ppm This is done by closing one of two jumpers on the PCB on the rear of the door of the unit Closing the upper jumper sets the unit to LEL Closing the lower jumper sets the unit to ppm Disabling or uninstalling sensors The BX116 can accept up to 16 sensors divided into two zones You should deselect the DIP sw...

Page 5: ...be performed for all pre alarm relays and main alarm relay together with L E D s and audible alarm The sequence will be a The 8 L E L 120ppm and Pre Alarm 1 L E D will be actuated The Pre Alarm 1 relay will be changed over b The 20 L E L 300ppm and Main Alarm L E D will be actuated The Main Alarm relay will be changed over The relevant Alarm L E D s will light to show which zones are in alarm By r...

Page 6: ...tion and the main gas valve is not closing There is no supply to the solenoid valve Check that the plug is inserted correctlty Check that the sensor wiring is correctly terminated at both the sensor and detector Check that 12V DC is present at the sensor The green light on the sensor should be illuminated Pressing the TEST button it is possible to check the efficiency of the device and if the sens...

Page 7: ...for this product will become void if damage is caused by the installer Technical specification Power Supply 230V AC 50Hz 10 Secondary Battery 12V DC 10 Power Consumption 30W maximum 230V Power Consumption 25W maximum 12V Relay contact range 10A 230V resistive 5A 30V DC resistive 1st pre alarm Can be set from 8 L E L 120ppm to 13 250ppm of LEL Main alarm Fixed at 20 L E L 300ppm Sensor fault Short ...