3.0 INSTALLATION
1.) Location that can withstand the unit's weight.
a.) Sometimes it is necessary to reinforce the ceiling with crossbeam or framework.
b.) Use suspension bolts to install the unit and make sure the bolts can withstand the weight
distribution.
2.) Location that minimize the drain piping and field piping distance.
3.) Location that minimize the ducting length.
4.) Location where there is
no direct heat and air is
allowed to circulate.
5.) It is suggestable to place
the unit higher than the
floor level, for ease of
drain piping. The base
should be 4” [100mm]
higher and leveled. Fix
the unit to the base with
anchor bolts. It is also
suggestable to place
vibrating isolation
component between the
unit and the base.
6.) Check the levelness of
the ceiling using a level
gauge.
3.4 EVAPORATOR BLOWER UNITS CLEARANCE
3.4.1. VERTICAL CASING TYPE- VEB, EB
a.) VEB 108D, 125D, 145D, 160D, 190D, 220D, 250D
9