1. Preparations before shipment
1.1 Installation Site
1) Do not install the machine in a place of a high temperature difference or in areas that are
exposed to dust or direct sunlight, and consider the ventilation condition. Besides, it is
recommended to select a place of less vibration. However, if it's inevitable, take caution
not to affect the machine with the vibration.
Reinforc
※
ed foundation, reinforced ground, and dustproof screen
2) A 14-ton crane with a minimum lifting performance of 4m ~ 5m should be equipped in
the installation site. The installation personnel should take into consideration the
dynamic relation between crane and foundation.
If a crane meeting the above specification is not available, use alternatives such as
※
car crane, large forklift, etc., for moving the machine.
3) When determining the installation site, refer to the machine layout diagram to secure
room for installing the assemblies (chip conveyor, etc) as well as enough room for repair
(so that the doors are open/closed without interruption). Besides, secure enough room
between machines to facilitate the installation work of the chip conveyor.
4) The ideal operation condition is between 30% and 75% in humidity at 20 ºC.
- The temperature difference should be within ±2 ºC for 24 hours (1 day).
- The temperature difference between floor and 5m high from the floor should be within 1
ºC.
Ref 1) :
※