OP000470
Operation
3-18
8.
If dirt or mud builds up in the track frame, raise each
track and rotate and clean that track.
Make sure that the material buildup has been cleared.
See Figure 38 and Figure 39.
9.
The excavator can travel in water that comes up to
center of upper carriage rollers. Make sure that footing
is solid so the machine will not sink.
NOTE:
If the machine is submerged to the point that
water or mud gets into the swing bearing or
center joint, stop machine operation. Remove
the machine from the submerged location to
firm, dry ground. Do not operate until proper
inspection and maintenance have been
completed. Refer to the Shop Manual or contact
your distributor.
FG007574
Figure 38
CAUTION!
When using the boom and arm to lift any portion
of the machine, roll the bucket until the round base
is against the ground. The angle of the arm to the
boom should be at 90°.
Figure 39
FG007575
90 ~ 100
Summary of Contents for DX27Z