6. CONTROL UNIT OPERATION

6.1. TO RAISE THE LEVELER

1. Park the transport vehicle with an open body in front of 

the leveler so that it is positioned squarely against dock 
bumpers.

2. Chock the vehicle wheels to prevent accidental depar-

ture.

3. Turn the main power switch ON to operate the leveler. 

4. Make sure the power led on the control unit is lit, then 

press the leveler control button. 

5. Keep the button pressed until the leveler platform is 

fully raised and the lip is extended. Then release the 
button and wait till the leveler platform lowers on the 
vehicle bed. The lip should have a minimum of 100 mm 
overlap on the vehicle bed surface. 

WARNING!

Keep the main power switch ON till the platform stops working and returns to the stored position!

CONTROL UNIT OPERA

TION

When loading or unloading is finished resume the stored 
position of the dock leveler by pressing and holding the 
leveler control button until the lip folds vertically down-

wards. Then release the button and wait till the platform 
returns to the stored position. After that turn the main 
power switch 0FF.

6.2. TO STORE THE LEVELER

Should any emergency arise halt the dock leveler in place by turning the main power switch OFF.

* Connection scheme refers to DoorHan operators of Shaft series only.

6.3. EMERGENCY STOP

WARNING!

To resume operations turn the main power switch ON and press the leveler RAISE button shortly.

Fig. 5.2. Connection scheme for lip inductive position sensor*

Shaft operator 

control post

Lip inductive 
position sensor

Shaft operator control board terminals

brown

black

blue

COM

OPEN

STOP

CLOSE

+24V

white

red

yellow

Summary of Contents for DCUH-1

Page 1: ...r s Manual DCUH 1 Control Unit for Electro Hydraulic Dock Leveler with Hinged Lip General Information 2 Safety Rules 2 Design 3 Installation 3 Electrical Connections 4 Control Unit Operation 5 Trouble...

Page 2: ...trol unit specifications Parameters Value Supply voltage 380 415 V 50 60 Hz Control voltage 24 VDC Max power of the hydraulic station 1 5 kW Operating temperature 20 50 Dimensions W u H u D 195 u 355...

Page 3: ...trol board Fig 3 1 Closed view Fig 4 1 Control unit installation Fig 3 2 Open view 1 1 2 2 3 DESIGN Mount the control unit so the distance between control unit bottom and dock floor is approximately 1...

Page 4: ...t won t be sup plied during the work L1 L2 L3 380 415 V U V W OUT 24 V M PE PE PE 380 415 V CONTACTOR PROTECTOIN RELAY TRANSFORMER ELECTROMAGNETIC VALVE COIL HYDRAULIC STATION MOTOR L1 L2 L3 N N Fig 5...

Page 5: ...ops working and returns to the stored position CONTROL UNIT OPERATION When loading or unloading is finished resume the stored position of the dock leveler by pressing and holding the leveler control b...

Page 6: ...board No jumper on terminals for safety devices Set the jumper Interlock switch open Check the interlock Leveler does not respond to pressing the control button Replace control board Leveler does not...

Page 7: ...cables to the dock leveler control unit Part name Part number 1 DCUH 1 main board PCB_DCUH1 M V 1 2 3 2 DCUH 1 control board PCB_DCUH1 BT V 1 0 3 Switch assembly DCU007 APPENDIX 3 2 1 Part name Length...

Page 8: ...tion on purchasing distribution and servicing contact DoorHan central office at 120 Novaya street Akulovo village Odintsovo district Moscow region 143002 Russia Phone 7 495 933 24 00 E mail info doorh...

Reviews: