When handling explosive or flammable materials the collector should be located
so as to avoid external heat sources, e.g. from nearby processes or extreme
direct sunlight.
The collector is not designed to support site-installed ducts, interconnecting
piping or electrical services. All ducts, piping or electrical services must be
adequately supported.
All external equipment connected to the outlet (e.g. ducting) should be correctly
sealed. This can be achieved by applying a continuous 5 mm bead of sealing
compound to the mounting surface, along each side of the hole pattern. For
non-Donaldson equipment please also check supplier’s IOM manual for any
specific requirements.
As mist particles coalesce and form larger droplets, the droplets become large enough
to run down the filter element. During operation, the droplets will drain on both the
inside and outside of the filter element. The filtered air exits the filter element into the
clean air chamber, where it exits through the clean air outlet and can be recirculated
into the environment.
General guidance to lifting
Refer also to figure 2.
The collector should be lifted using the four lifting points provided.
During all lifting operations a crane or fork lift with an adequate SWL (safe
working load) must be used. (Refer to lifting label located adjacent to lifting
points for weight of equipment supplied by Donaldson).
Slings with an adequate SWL (safe working load) must be used. (Refer to
lifting label located adjacent to lifting points for weight of equipment supplied
by Donaldson).
Use clevis connectors, not hooks, on lifting slings.
Use spreader bar to prevent damage to collector casing.