RP_RPH Baghouse
25
Support Installation
Reference Typical Foundation Anchor drawing shipped with the collector prior to starting assembly.
Prepare the foundation or support framing in the selected location. Locate and install anchors.
Anchors must comply with local code requirements and be capable of supporting dead, live, wind, seismic and other
applicable loads.
Anchor sizes shown are provisional, as final anchor sizing will depend on jobsite load conditions, equipment location,
foundation/framing design variables and local codes.
Consult a qualified engineer for final selection of suitable anchors.
Temporary support is required until all legs and cross-bracing are in place.
High Inlet Installation
1. After the collector housing is upright and secure, remove the braces from
the high inlet opening on the collector.
2. Place 1/4-in diameter, rope-type sealant toward the inside and outside
edge of the bolt pattern in a figure 8 pattern on the inlet section mounting
flanges.
3. Lift high inlet into position and secure with the hardware provided.
Inlet Scroll Installation
1. After the collector housing is upright and secure, remove
the temporary vertical supports from the inlet scroll
opening on the collector.
2. Place 1/4-in diameter, rope-type sealant toward the
inside and outside edge of the bolt pattern in a figure 8
pattern such that sealant will be on inside and outside
edge of all flange bolt holes on the inlet-section scroll
mounting flanges.
3. Lift inlet scroll into position and secure with the hardware
provided.
High Inlet Installation
high inlet
mounting
flange
high inlet
sealant
inlet scroll
mounting
flange
temporary
vertical
support
sealant
inlet
scroll
Inlet Scroll Installation