background image

12

Deterioration risk: The water tank must be filled 

before the appliance is switched on or connected 

to a power supply.

Set-Up and Use

7.1   Commissioning

Figure 10: 

 Diagram showing PV connections

At the time of commissioning, complete all relevant 

sections of the Benchmark Checklist located on the 

inside back pages of this document. 

The following commissioning procedures only detail the 

required steps to be taken for the potable water loop. 

1) 

Before making any mains connections to the 

 

inlet control group, flush the mains pipework 

 

out to ensure all debris has been removed so as 

 

not to damage the strainer within the 

 

combination valve.

2) 

Make final mains connection on combination 

 

valve and check all connections and joints to 

3) 

Before turning on the mains supply to the  

 

 

water heater a hot water tap should be opened, 

 

preferably on the same floor or the floor below 

 

where the water heater is located.

4) 

Check the pre-charge in the expansion  vessel 

 

and ensure it is at least 3 bar. Note actual 

 

pressure on label on expansion vessel. 

5) 

Turn on the supply to the water heater and fill 

 

until water runs from the open hot water tap. 

 

Continue to flush the system until all debris has 

 

been removed. 

6) 

Close the hot water tap.

7) 

Check all joints for leaks, even those not 

 

having been altered especially when replacing a 

 

vented water heater.

8) 

Open temperature and pressure relief valve 

 

to ensure proper discharge and check after 

 

closing that valve is not dripping.

9) 

Open expansion relief valve to ensure proper 

 

discharge and check after closing that valve is 

 

not dripping.

10) 

Check all shower outlets, toilet cisterns and 

 

other draw off points for leaks or dripping 

 

(especially when replacing a vented unit). 

 

Open all water outlets to purge air from

 

pipework and ensure proper operation.

11) 

Instruct user in the operation of the unit and 

 

hand over this manual advising the owner of 

 

annual service requirements.

12) 

Complete the technical data label on the 

 

water heater with legible and permanent 

 writing.

Set-Up and Use

This function enables the appliance to operate in 

auto-production mode, which means that it will use the 

energy produced by the PV function to supply the heat 

pump as well as the electrical back-up, in order to heat 

the water in the tank. 

The connection is made between the PV Inverter and 

connectors 1 and 2 on the electronics board. 

- Remove the appliance lid.

- Remove the black cover from the electronic board.  

6.9.1.2 Connecting the PV Function

- Connect the PV function cable to connector 1 on the 

  electronic board.

- If the PV function regulator has two control contacts, 

  connect them to Entrée 1 and 2 on the electronic 

  board (see Figure 9).

- Terminal 1: a low level of electrical energy is 

  produced by the PV function.

- Terminal 2: a high level of electrical energy is 

  produced by the PV function.

2

1

PV max

PV éco

Voltage-free Contacts to PV Inverter

Tair

Tdégiv
Teau

HP

Caution: Connectors 1 and 2 are for 

VOLTAGE FREE CONTACTS only. They 

must NEVER be connected to 230V.

Red Jumper to 

be removed

Summary of Contents for EDL200UK-630RF

Page 1: ...Air Source Heat Pump Water Heater Installation and User Instructions RD01144 2 Important This manual must be left with user after Installation Edel RF...

Page 2: ...ture reference Installers are required to carry out installation commissioning and ser vicing work in accordance with the Benchmark Code of Practice which is available from the Heating and Hot Water I...

Page 3: ...Electrical Connections 11 6 9 1 1 Electricity Provider Contact 11 6 9 1 2 Connecting the PV Function 11 7 Set Up and Use 12 7 1 Commissioning 12 7 2 Using your Hot Water Heat Pump 13 7 3 Control Box 1...

Page 4: ...and or user This appliance can be used by children aged 8 years and above and persons with reduced physical sensory or mental capabilities or lack of experience and knowledge if they have been given s...

Page 5: ...installation If in any doubt please call the appropriate help desk Disregarding the instructions given in this manual in its entirety and any relevant regulations standards and codes of practice will...

Page 6: ...must be taken when placing the water heater in a garage or outbuilding All exposed pipework must be correctly insulated to avoid frost damage The position and orientation of the water heater should b...

Page 7: ...2 15 22 9 0 8 28 18 1 0 35 27 1 4 G3 4 22 28 9 1 0 35 18 1 4 42 27 1 7 G1 28 35 9 1 4 42 18 1 7 54 27 2 3 Dimplex recommend an annual maintenance inspection is carried out on the water heater In hard...

Page 8: ...on vessel membrane before filling the cylinder The pre charge should be greater than or equal to 3 bar 6 2 Cold Water Inlet with Inlet Group The discharge pipe should not be connected to a soil discha...

Page 9: ...dwellings occupied by people with impaired vision or mobility con sideration should be given to the installation of a suita ble safety device to warn when discharge takes place e g electronically oper...

Page 10: ...2 5 25 0 External terminal X 1 51 0 51 0 Total System Calculated Pressure Drop 320m3 hr 207 7 Pa 6 7 1 Worked Example The pressure drop information provided is for 160mm semi rigid Ubbink ducting othe...

Page 11: ...hoose load shedding level 1 the electrical back up is prevented from running If you choose load shedding level 0 both the electrical back up and the heat pump will be prevented from running see Sectio...

Page 12: ...ischarge and check after closing that valve is not dripping 9 Open expansion relief valve to ensure proper discharge and check after closing that valve is not dripping 10 Check all shower outlets toil...

Page 13: ...ature remains in the authorised 7 C to 35 C range Outside of this range electrical backup ensures that the domestic hot water is heated The domestic hot water temperature provided by the heat pump is...

Page 14: ...This function can be programmed to run between 1 and 99 days and is effective as soon as the number of days has been confirmed HOLIDAYS HOLI RETURN 8 Set number of days in standby mode Enter HOLIDAY...

Page 15: ...exisitng programme MONDAY Set Up and Use Frost PT Frost Protection Mode ECO Heat Pump Only Running CONF Heat Pump Only Running electrical back up if needed 7 10 Programming Heating time for the tank v...

Page 16: ...al until the screen displays Inst Menu Press the Clock and Menu buttons simultaneously Keep both buttons pressed down until the screen goes blank 7 11 1 PV Mode Setting Description Unit Range Factory...

Page 17: ...emperature reaches 43o C The heat pump will complete the remaining charge to set temperature 7 11 2 3 Minimum Temperature To C Min No To C Min 43 o c Select Mode Enter It is possible to allow the oper...

Page 18: ...f locking for accessing the menus In the Installer menu turn the dial to Locking LOCKING LOCKING NO Select No Enter NO Locking is not activated but manual locking is possible by pressing Menu for 3 se...

Page 19: ...ers The Counters menu shows the number of start ups from the heat pump and the electrical backup In the Installer menu turn the dial to Counters Counter No 1 Number of start ups from the heat pump Cou...

Page 20: ...heater and the thermostat 10 The immersion heater boss can also be used for access to view the internal components of the cyl inder 11 Re commission unit see chapter 7 1 8 2 Heat Pump Any work on the...

Page 21: ...ich would reduce the cross sectional area of the conductor 4 Ensured the conductors are tightly and securely connected to the controls or immersion heater 5 Ensured the bared conductors are correctly...

Page 22: ...higher than the volume in the tank The time period the appliance operates is not too short 12hrs minimum if connected to piping The water temperature is not set too low Condensates are not drain ing T...

Page 23: ...045 2 Expansion vessel fixing kit R00094 2 DN16 3 4 BSP x 1000 flex pipe R00095 1 1 2 BSP T P valve R00020 1 15 x 22 straight PE tundish R00047 1 Temp sensor 25 C 1243950 C3S PCB Controller 1244096 70...

Page 24: ...aintained continuously at the standard set temperature if no signal or control is connected to the external control switch OVER PRESS Heat pump pressure too high No water in tank Water is too hot 75 C...

Page 25: ...being in contact with a part which vibrates Replace expansion valve The compressor is not working and safety temperature is activated Weakness in compressor Replace compressor ERR 02 Incorrect temper...

Page 26: ...mation 9 1 Warranty Limits Please read the following statements carefully as it affects your warranty Please ensure that the installer has fully completed the Benchmark Checklist on the inside back pa...

Page 27: ...d Water supply being other than cold domestic water such as rainwater or water from a well or which has particularly hostile or abnormal properties which do not comply with the national rules and curr...

Page 28: ...28 B C D E A 152 Figure 11 Edel Air Source Water Heater Dimensions for reference only Technical Data and Product Fiche 10 Technical Data and Product Fiche Air Intake Air Discharge...

Page 29: ...d Product Fiche Cylinder is tested in accordance with EN12897 2006 GDC Group Ltd Edel Air Source Water Heater Product Fiche Reference EDL200UK 630RF EDL270UK 630RF Load Profile Primary M L Energy Rati...

Page 30: ...2 kW 240V Ventilation Air flow rate 320 to 400 m3 h Air temperature 7 C to 35 C Max air pipe length rigid piping 20m in total intake and rejection Condensates flow rate 0 3 L h Condensates drainage p...

Page 31: ...31 Power Supply Green Yellow Black Blue Brown Black Blue Blue Black Sensors Black Black Black Black Blue Black Blue Brown Black Brown Communication Bus Display 1 2 Red Fan B1244454 F HPS DV...

Page 32: ...Red Blue Blue Black Brown Blue Green Yellow Blue Black Blue Blue Red Red Blue HTS WTS HPS High Pressure Switch C25 Compressor Start Capacitor C2 Fan Capacitor C4 Valve F Fan DV Defrost Valve RE Immer...

Page 33: ...33 Notes...

Page 34: ...and pressure relief valve and expansion valve been fitted and discharge tested Yes No The tundish and discharge pipework have been connected and terminated to Part G of the Building Regulations Yes A...

Page 35: ...mments Signature SERVICE 3 Date Engineer Name Company Name Telephone Number Comments Signature SERVICE 4 Date Engineer Name Company Name Telephone Number Comments Signature SERVICE 5 Date Engineer Nam...

Page 36: ...plex reserve the right to revise products literature and guarantee terms without prior notice due to a policy of continuous improvement www KIWA co uk www HWA co uk To speak to customer services pleas...

Reviews: