(if equipped)
Remove shipping shims. See Figure 1a.
a.
Locate shipping shims (a) under generator frame.
b.
Loosen but do not remove limiter bolts (b).
c.
Pull label (c) and remove shims.
d.
Retighten limiter bolts. Torque to 120-144 in-lbs.
It is very important that these are removed before starting your generator.
IMPORTANT:
Before any attempt to start your generator be sure to check
engine oil (See Engine Operator's manual).
GROUNDING THE GENERATOR
A grounding lug is supplied with the generator for
use when required by local electrical ordinances.
Refer to article 250 of the National Electrical Code
to clarify any needed grounding information. Your
local electric company or a certified electrician
should be able to help you with this information.
9- ENG
D26563
Grounding Lug
TYPICAL INSTALLATION OF BATTERY
(Electric Start Units Only)
•
Recommended Battery for Electric Start: 12V - 45 A H. or 210 CCA (Cold
Cranking Amps)
•
Purchase battery and battery hardware separately, not included with unit.
1.
Place battery in rack with terminals
facing towards generator head.
2.
Place battery bracket (A) over battery as
shown in Figure 3 (opposite battery
terminals).
3.
Place "L" bolt (B) through top and
bottom brackets and secure with wing
nut (C).
4.
Locate the solenoid on the left side of
the unit. See Figure 4 and 5.
Figure 2
Figure 3
a
b
c
c
b
Figure 1a