19
3.4 Installation
3.4.1. Installation Location
Make sure that the installation location meets the following conditions:
• The installation site must be suitable for the size and weight of the battery.
• Must be installed on a firm surface to sustain the weight of battery.
• The area is water proof.
• There are no flammable or explosive materials
• The ambient temperature is within the range from 0°C to 45°C.
• The temperature and humidity is maintained at a constant level.
• There is minimal dust and dirt in the area.
• Installation must be vertical or tilted backwards by maximum 15° - avoid forward or sideways tilt.
3.4.2. Mounting to a wall
• Choose suitable firm wall with thickness greater than 80mm.
• Use the mounting frame as a template, mark the hole position.
• Drill 8 holes according to the hole position, it is ø10 with depth 60mm.
• Hammer the M8 screws to the above holes, and screw the nut.
• NOTE: Do not position screws flush to the wall - leave 10 to 20 mm exposed.
• Fix the mounting frame to the 8 screws.
•
Raise the battery a little higher than the mounting frame whilst maintaining the balance of the battery.
Hang the battery on the frame through the match hooks.