Figure 25 B13 sliding rail assembly - 2U systems
1. B13 sliding rail (2)
2. velcro strap (2)
3. screw (4)
4. washer (4)
Install the rails
The rails are labeled left and right, and cannot be interchanged. The front side of each
rail is labeled Left Front or Right Front when the rail faces the cabinet front.
Procedure
1. Determine where to mount the system, and mark the location at the front and
back of the cabinet.
Note
Install the left rail assembly first.
2. Fully extend the rear sliding bracket of the rail.
3. Position the rail end piece labeled Left Front facing inward and orient the rear
end piece to align with the holes on the rear cabinet flanges.
4. Push the rail straight toward the rear of the rack until the latch locks in place.
2U1N Configuration Equipment Installation
Install the rails
67
Summary of Contents for EMC VxFlex Ready Node 14G
Page 1: ...Dell EMC VxFlex Ready Node 14G Hardware Installation Guide 302 004 321 REV 03 ...
Page 6: ...FIGURES 6 Hardware Installation Guide ...
Page 8: ...TABLES 8 Hardware Installation Guide ...
Page 16: ...Before You Begin 16 Hardware Installation Guide ...
Page 18: ...1U1N Procedures 18 Hardware Installation Guide ...
Page 40: ...1U1N Configuration Equipment Installation 40 Hardware Installation Guide ...
Page 48: ...Install AC Power Cables 48 Hardware Installation Guide ...
Page 62: ...2U1N Procedures 62 Hardware Installation Guide ...
Page 74: ...2U1N Configuration Equipment Installation 74 Hardware Installation Guide ...