Verify the return to operational condition
Once corrective maintenance has taken place, verify that the control valve is working
properly by following the steps below.
Procedure
1. Inspect all bolts used to secure the control valve in-line to ensure that proper
mounting procedures have been followed and that flange connections are leak-
free.
2. Evaluate the system setup to ensure that all components are in the correct
operating sequence.
3. Evaluate the system setup to ensure that all components are in the correct
sequence for accurate product measurement. Some components are isolation
valves, strainers, flow straighteners, turbine meters, downstream sections, etc.