background image

Operating Guide

Termix VVX-B – 7 Series BS

4.2 Start-up

Start-up, Indirect heating

Filling:

1: First fill

When carrying out first fill, the heat exchanger must be slowly filled
with water until it reaches working pressure.

2: Pressure gauge

The HE pressure gauge indicates the pressure of the HE system. This
instruction must be followed strictly, to avoid dangerous situations.

3: Supply hose

A ball valve with plug is installed in the HE return line. To fill the
system, the ball valve must first be closed, the plug removed and
a supply hose connected. On re-opening the ball valve, system
fill can commence.

4: Pre-pressure

When filling the system with water, the pressure gauge should be
observed closely. The expansion vessel is supplied pre-pressurised
to 0.5 bar. The pre-pressure required at each substation will
depend on system head (the distance between the lowest and
highest point in the system), for example:

5: Filling stop

Filling must stop when the pressure gauge shows a pressure
approximately 1-2 bar higher than the pre-pressure setting. The
ball valve is then closed, the hose removed and the plug put back
in.

Start-up:

1: Pump speed

Set the pump to highest speed before start-up.

2: Start pump

Start the pump and heat through the system.

3: Open shut-off valves

The shut-off valves should then be opened and the unit observed
as it enters service. Visual checking should confirm temperatures,
pressures, acceptable thermal expansion and absence of leakage.
If the heat exchanger operates in accordance with design, it can be
put to regular use.

4: Vent system

Switch off the pump and vent the installation after the radiators
have been warmed up.

5: Adjust pump speed

Set the pump to the lowest speed consistent with comfort and
electricity consumption.
Normally the change-over switch is set in the mid position (default).
However for systems with under floor heating or single pipe loop
systems, it may be necessary to turn the change-over switch
upwards.
Higher pump speeds are only used if the heating requirement
increases.

Re-tighten connections

After water has been added to the system and the system has been

put into operation, re-tighten

ALL

connections.

Pump

The pump must be switched off during system fill.

Height (m)

Pressure (bar)

0 – 5

0,5

5 – 10

1,0

10 – 15

1,5

15 – 20

2,0

6

DEN-GT

LGB40404

Summary of Contents for Termix VVX-B-7 BS Series

Page 1: ...t up 6 4 3 Electrical connections 7 5 0 Design 10 5 1 Design 10 5 2 Schematic diagram 11 6 0 Controls 12 6 1 Heating circuit 12 6 2 DHW temperature control 16 6 3 Other 17 6 4 Extras 18 6 5 Maintenanc...

Page 2: ...ump The temperature of the heating can be controlled thermostatically or by an electronic controller with an outdoor temperature sensor Depending on the application different heat exchangers dimension...

Page 3: ...eaks or other dangerous circumstances interrupt all energy sources to the station if possible and seek expert help In case of discoloured or bad smelling domestic hot water close all shut off valves o...

Page 4: ...be taken to mean the primary supply Connections 1 Domestic cold water DCW 2 Domestic hot water DHW 3 District heating DH return 4 District heating DH supply 5 Heating HE return 6 Heating HE supply Co...

Page 5: ...allation Clean and rinse Prior to installation all substation pipes and connections should be cleaned and rinsed Tightening Due to vibration during transport all substation connections must be checked...

Page 6: ...e ball valve is then closed the hose removed and the plug put back in Start up 1 Pump speed Set the pump to highest speed before start up 2 Start pump Start the pump and heat through the system 3 Open...

Page 7: ...bol Disconnection The substation must be electrically connected so that it can be disconnected for repairs Outdoor temperature sensor Outdoor sensors should be mounted so as to avoid exposure to direc...

Page 8: ...emperature The IMIT Thermostat is preset to 60 C shutting off the pump and the primary on off valve when the flow to the underfloor heating exceeds 60 C The IMIT Thermostat is if not already factory f...

Page 9: ...Operating Guide Termix VVX B 7 Series BS 4 3 3 Wiring diagram Radiator heating Underfloor heating LGB40404 DEN GT 9...

Page 10: ...gn description A Heat exchanger HE 9 Strainer 38 Expansion tank B Heat exchanger DHW 10 Circulator pump 41 Fitting piece energy meter 4 Safety valve 20 Filling drain valve 48 Air vent manual 7A Thermo...

Page 11: ...Shut off valve 1 Ball valve 20 Filling drain valve 48 Air vent manual 2B Double check valve WRAS 24 Delivered loose with unit 62B Pressure Absorber with non return valve 4 Safety valve 26 Pressure gau...

Page 12: ...low temperature in the heating circuit is controlled by the HE temperature controller 6 1 3 RAVK controller RAVK controller 35 75 C The temperature setting is as follows 1 30 C 2 40 C 3 52 C 4 64 C 5...

Page 13: ...as follows 1 35 C 2 55 C 3 75 C 4 95 C 5 100 C The values are intended as a guide Thermostatic control The temperature of the HE flow line is adjusted as follows To increase temperature turn the hand...

Page 14: ...ats it is recommended that thermostats be set for minimum temperature in each room 6 1 8 Outdoor temperature sensor ESMT Outdoor sensors should be mounted so as to avoid exposure to direct sunlight Th...

Page 15: ...ser interface switches to setting selection if the user interface is unlocked You can change the settings as they appear The selection of the control mode depends on the system type and the allocation...

Page 16: ...ler 20 60 The temperature setting is as follows 1 20 C 2 35 C 3 50 C 4 60 C 5 70 C The values are intended as a guide The AVTB operates at its best at DH supply temperatures of up to 90 C Thermostatic...

Page 17: ...uld be cleaned regularly by authorized personnel The frequency of cleaning would depend on operating conditions and the manufacturer s instructions 6 3 3 Pressure Absorber The Pressure Absorber reduce...

Page 18: ...er Do not forget the gaskets 4 Tighten connections After mounting of the energy meter remember to check and tighten all threaded connections Sensor pocket energy meter The sensors of the energy meter...

Page 19: ...Temperatures Checking of all temperatures such as DH supply temperature and DHW temperature Connections Checking all connections for leakages Safety valves The operation of the safety valves should b...

Page 20: ...f order or with too low setting Check circulation pump Defective or clogged non return valve Replace clean No electricity Check Wrong setting of automatic controls if any To adjust an electronic contr...

Page 21: ...manual The pump is set at too low speed of rotation Set the pump at higher speed of rotation Pressure drop the pressure drop on the radiator circuit shows lower than recommended operating pressure Fil...

Page 22: ...radiators in the system from heating up at the bottom It is extremely important to keep the supply temperature to the radiators as low as possible while maintaining a reasonable level of comfort The s...

Page 23: ...Operating Guide Termix VVX B 7 Series BS 8 0 Declaration 8 1 Declaration of conformity Category 0 with electrical equipment LGB40404 DEN GT 23...

Page 24: ...Operating Guide Termix VVX B 7 Series BS Produced by Gemina Termix A S 03 2018...

Reviews: