background image

Instructions

© Danfoss | DCS (CC) | 2018.07  | 7

FRCC.PI.059.A1.02

• Avoid flare-type connections and exercise great 
care while brazing (use only state-of-the-art 
practices); apply a nitrogen gas flow to prevent 
oxidation inside the tubing, especially when 
HFC refrigerants are being used. All brazing ma-
terial is to contain a minimum of 5% silver.
• When brazing, protect the valves and all other 
unit components from torch heat damage 
(painted surfaces, gaskets, connecting box).

• Note that it is not necessary to remove com-
pressor shut-off valves for connection to the 
system, hence no need to replace associated 
gaskets. 

• Be sure to connect the required safety and control 
devices onto compressor shut-off valves or fittings.

• In case of oil return through the Schrader fitting 
on the compressor shell, make sure the internal 
valve is removed.

5 - Leak detection

Never use oxygen or dry air in order to avoid the 
risk of fire or explosion.

• Perform a leak detection test on the complete 
system by means of: a dry nitrogen pressure test, 
a mixture of nitrogen and the refrigerant to be 
used in the system, a helium leak test and/or a 
deep vacuum test.

• The test should be long enough in duration to 
ensure the absence of any slow leaks in the sys-
tem.

• Use tools specifically designed for detecting leaks.

• The low side test pressure must not exceed 1.1 
x Ps pressure indicated on the compressor name-
plate.

• For high side test pressure, do not exceed the pres-
sure indicated on the condensing unit nameplate. 

• Whenever the condensing unit is equipped 
with suction and liquid shut-off valves, these 
valves are to remain in the closed position while 
performing the leak test (condensing unit leak 
test already performed in the factory).

• Should a leak be discovered, proceed with re-
pair steps and repeat the leak detection. 

• When a deep vacuum leak detection test is se-
lected, observe the following:
  1) The level to reach is 500 μm Hg.
  2) Wait 30 min.
  3) If pressure increases rapidly, the system is 
not airtight. Locate and repair leaks. Restart the 
vacuum procedure, followed by steps 1, 2, etc.
  4) If pressure increases slowly, the system 
contains moisture inside. Break the vacuum with 
nitrogen gas and restart the vacuum procedure, 
followed by steps 1, 2, etc.
  5) Connect the compressor to the system by 
opening the valves. 
  6) Repeat the vacuum procedure, followed by 
steps 1, 2, etc.
  7) Break the vacuum with nitrogen gas. 
  8) Repeat the vacuum procedure, steps 1, 2; 
a vacuum of 500 μm Hg (0.67 mbar) should be 
reached and maintained for 4 hours. This pres-
sure is to be measured in the refrigeration sys-
tem, and not at the vacuum pump gauge.

 Do not use a megohmeter or apply power to the 

compressor while it is under vacuum, as this may 
cause motor winding damage (motor burn-out).

 Do not use colored leak detection fluids. Do 

not use chlorofluorocarbon in leak testing sys-
tems designed for HFC fluids.

6 - Vacuum dehydration procedure

Whenever possible (if shut-off valves are pre-
sent), the condensing unit must be isolated from 
the circuit. It is essential to connect the vacuum 
pump to both the LP & HP sides, in order to avoid 
dead-ending system parts.

Recommended procedure:
  1) Once leak detection has been completed,
  2) Pull down the system under a vacuum of 
500 μm Hg (0.67 mbar).
  3) When the vacuum level of 500 μm Hg has 
been reached, the system must be isolated from 
the pump.
  4) A vacuum of 500 μm Hg (0.67 mbar) has 
to be reached and maintained for 4 hours. This 
pressure is to be measured in the refrigeration 
system, and not at the vacuum pump gauge.

If pressure increases, restart the leak-detection 
procedure (refer to the «Leak detection» section 
of this manual if necessary).

Vacuum pump:
A two-stage vacuum pump with gas ballast 
valve (0,04-mbar standing vacuum) shall be 
used; its capacity is to be consistent with system 
volume. 
Never use the compressor as a vacuum pump. It 
is recommended to use large-diameter connec-
tion lines and to connect these lines to the shut-
off valves, rather than to the Schrader connec-
tion.
This recommendation allows avoiding excessive 
pressure losses.

Moisture level:
At the time of commissioning, system moisture 
content may be as high as 100 ppm. During ope-
ration, the liquid line filter dryer must reduce this 
level to < 20 ppm.

Additional notes:
• To improve moisture removal, the temperature 
of the system should not be lower than 10°C.

• A proper vacuum procedure is even more im-
portant with HFC and polyolester lubricant than 
it has “traditionally” been with HCFC (R22) or CFC 
and mineral oil.

• For further details, please refer to TI 3-026.

 Do not use a megohmeter or apply power to 

the compressor while it is under vacuum, as this 
may cause motor winding damage (motor burn-
out).

7 - Electrical connections

• Make sure the main power supply to the sys-
tem has been switched off and isolated, in ac-
cordance with applicable regulations, before 
performing
any electrical connection.
• Please refer to Figs 5 and 6 for typical wiring 
connections and examine the specific wiring 
diagram located in the electrical box cover.

For further details, refer to the condensing unit 
guidelines.

• Note that Maneurop® compressors fitted on 
condensing units are protected against overhea-
ting and overloading by an internal safety motor 
protector. However, an external manual reset 
overload is recommended for protecting the cir-
cuit against over-current.

• The “must trip” value of this overload relay must 
be set in accordance with power line sizing and 
design and shall never exceed the “A max.” value 
stamped on the nameplate.

• On units equipped with an electrical box, all 
electrical connections (condenser fan motor, 
compressor motor, pressure control switch, 
crankcase heater, etc.) have already been wired at 
the factory. For single-phase compressors, start-
and-run capacitors are included in the connec-
ting box.

• The connecting box is equipped with screw type 
terminal blocks, for both power and control lines as 
well as earth terminals for grounding connections.

• All electrical components must be selected as 
per local standards and condensing unit compo-
nent requirements.

8 - Filling the system

• Before charging the refrigerant, verify that the 
oil level is between 1/4 and 3/4 on the com-
pressor oil sight glass and/or ensure that the oil 
charge of the original compressor is sufficient as 
regards system dimension and piping design:
  - An additional quantity of oil might be neces-
sary for line lengths (back and forth) in excess of 
20 m.
  - In the event additional oil is required, use 
only an approved lubricant (refer to the «Intro-
duction» section of this manual).

• Make sure the refrigerant used to fill the system 
is compatible with compressor design. Refer to 
the 

«Introduction»

 section of this manual for an 

approved list of refrigerants.

• Compressor switched off: the liquid refrigerant 
is charged into the condenser and/or liquid re-
ceiver in the liquid phase (compulsory for refri-
gerant blends).The charge must be asclose to 
the nominal system charge as possible in order 
to avoid both low pressure operations and ex-
cessive superheating at start-up. Throughout 
this operation, both compressor service valves 
must remain closed.

• To the extent possible, maintain the refrigerant 
charge below 2.5 kg per cylinder. Above this li-
mit, install a system, such as a pump-down cycle 
or suction line accumulator, to prevent against 
liquid flood-back into the compressor.

• Be sure that the refrigerant charge is suitable 
for both winter and summer operations.

9 - Verification before commissioning

 Ensure that all service valves are in the open 

position before start-up. A closed discharge or 
suction service valve may cause serious damage 
to the compressor and/or compromise safety 
device operation, thereby resulting in potential 
injury to personnel.

Summary of Contents for Optyma OP-LCQN048

Page 1: ... MTZ050 MTZ056 MTZ064 MTZ072 MTZ080 836 5 1200 800 OP MGRN108 OP MGRN121 OP MGRN136 MTZ064 MTZ072 MTZ080 693 5 1500 870 OP MGRN171 OP MGRN215 OP MGRN242 OP MGRN271 MTZ100 MTZ125 MTZ144 MTZ160 836 5 1500 870 LBP application 50 Hz Compressor H W D OP LCQN048 NTZ048 545 630 650 OP LCQN068 NTZ068 705 900 900 OP LCQN096 OP LCQN108 OP LCQN136 NTZ096 NTZ108 NTZ136 836 5 1200 800 OP LGQN096 OP LGQN108 OP ...

Page 2: ...0 Evaporating Temperature C R407C Ambient Temperature C 35 0 10 20 30 40 50 30 25 20 15 10 5 0 5 10 15 Evaporating Temperature C R452A Ambient Temperature C 35 0 10 20 30 40 50 30 25 20 15 10 5 0 5 10 15 Evaporating Temperature C R407F Ambient Temperature C 0 10 20 30 40 50 30 25 20 15 10 5 0 5 10 15 20 Evaporating Temperature C R134a Ambient Temperature C SH 10 K SC 0 K MBP Fig 1a 45 0 10 20 30 4...

Page 3: ...Instructions Danfoss DCS CC 2018 07 3 FRCC PI 059 A1 02 1 x coil height Min clearance 2 x unit length Fig 2 Fig 3 Fig 4 ...

Page 4: ...Instructions 4 Danfoss DCS CC 2018 07 FRCC PI 059 A1 02 SINGLE PHASE MODELS THREE PHASE MODELS ...

Page 5: ...Instructions Danfoss DCS CC 2018 07 5 FRCC PI 059 A1 02 For R404A models Factory setting HP bar MBP 28 8 LBP 28 3 LP bar ...

Page 6: ... stored in an ambient temperature of below 35 C 31 F or above 50 C 122 F Ensure that the condensing unit and its packa ging are not exposed to rain and or a corrosive flammable atmosphere 3 Safety measures prior to assembly All installation and servicing is to be performed by qualified personnel in compliance with all pertinent practices and safety procedures The condensing unit must be located in...

Page 7: ...tent with system volume Never use the compressor as a vacuum pump It is recommended to use large diameter connec tion lines and to connect these lines to the shut off valves rather than to the Schrader connec tion This recommendation allows avoiding excessive pressure losses Moisture level At the time of commissioning system moisture content may be as high as 100 ppm During ope ration the liquid l...

Page 8: ...s fan opera tions water flow water filter etc liquid refrige rant flow and pressure drops solenoid valve filter dryer expansion valve etc refrigerant charge Low refrigerant charge the correct refrige rant charge is given by the liquid sight glass indication the condenser delta T in relation to the refrigerant pressure tables pressure tempe rature the superheat and the sub cooling etc if additional...

Page 9: ...User advisory Insist that all service operations only be per formed by qualified personnel The condensing unit tubing and compressor surface temperatures may exceed 100 C 212 F and cause severe bodily burns Special precau tion must be taken when working around the compressor and refrigerant tubing Moreover a compressor in operation can generate very cold surface temperatures as low as 45 C 49 F th...

Reviews: