Piping installation
Installer and user reference guide
75
RWEYQ8~14T9Y1B
VRV IV water-cooled system air conditioner
4P452191-1B – 2020.10
Connection with VRV DX indoor units and Hydrobox units
H3
1
2
H1
H2
3
5
4
a
b
b
c
d
e
a
Outdoor unit
b
VRV DX indoor unit
c
Multi branch selector unit (BS*)
d
Low temperature (LT) Hydrobox unit
e
High temperature (HT) Hydrobox unit
Pipe
Maximum length (actual/
equivalent)
Longest pipe from the outdoor unit or the last multi-
outdoor piping branch (1+2, 1+3, 1+5)
120 m/140 m
(a)
Longest pipe after the first branch (2, 3, 5)
40 m/—
In case of a multi-outdoor setup: longest pipe from
the outdoor unit to the last multi-outdoor piping
branch (4)
10 m/13 m
Total pipe length
300 m/—
(a) If the equivalent piping length is more than 90 m, size up the main liquid piping