3
|
Components
Service manual
81
250D7Y1B
Sky Air Advance-series
ESIE19-13A – 2020.05
2
Supply nitrogen to the refrigerant circuit. The nitrogen pressure MUST NOT
exceed 0.02 MPa.
3
Wrap a wet rag around the high pressure switch and solder the high pressure
switch pipe to the high pressure switch.
a
c
b b
a
High pressure switch
b
Faston connector
c
High pressure switch pipe
CAUTION
Overheating the pressure switch will damage or destroy it.
4
After soldering is done, stop the nitrogen supply after the component has
cooled‑down.
5
Connect the Faston connectors to the high pressure switch.
6
Add
refrigerant
to
the
refrigerant
circuit,
see
142].
Is the problem solved?
Action
Yes
No further actions required.
No
Return to the troubleshooting of the
specific error and continue with the
next procedure.
3.7 Inverter PCB
3.7.1 Checking procedures
INFORMATION
It is recommended to perform the checks in the listed order.
To perform a power check of the inverter PCB
Prerequisite:
Stop the unit operation via the user interface.
Prerequisite:
Turn OFF the respective circuit breaker.
Prerequisite:
Remove the required plate work, see
Summary of Contents for Sky Air Advance RZA200D7Y1B
Page 1: ...Service manual Sky Air Advance series RZA200D7Y1B RZA250D7Y1B ...
Page 190: ......
Page 191: ......
Page 192: ...ESIE19 13A 2020 05 Copyright 2020 Daikin Verantwortung für Energie und Umwelt ...