9 Commissioning

Installation manual

15

AZAS100~140MUV/Y
Sky Air Active-series
4P743507-1 – 2023.08

2

Turn ON the power and leave it on for 6 hours.

Result: 

The  compressor  will  heat  up  and  evaporate  any

refrigerant in the compressor.

3

Measure the insulation resistance again.

9

Commissioning

Please  provide  the  eco  design  data  according  to  (EU)2016/2281  to
the customer. This data can be found in the installer reference guide
or via the Daikin website.

NOTICE

ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.

9.1

Checklist before commissioning

1

After the installation of the unit, check the items listed below.

2

Close the unit.

3

Power up the unit.

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

In case a wireless user interface is used: The 

indoor unit

decoration panel

 with infrared receiver is installed.

The 

outdoor unit

 is properly mounted.

The following 

field wiring

 has been carried out according

to this document and the applicable legislation:

▪ Between the local supply panel and the outdoor unit

▪ Between the outdoor unit and the indoor unit (master)

▪ Between the indoor units

There are NO 

missing phases

 or 

reversed phases

.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed according to this document, and have NOT been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

9.2

To perform a test run

This task is only applicable when using the BRC1E52 user interface.

▪ When  using  BRC1E51,  see  the  installation  manual  of  the  user

interface.

▪ When using BRC1D, see the service manual of the user interface.

NOTICE

Do NOT interrupt the test run.

INFORMATION

Backlight.

  To  perform  an  ON/OFF  action  on  the  user

interface,  the  backlight  does  not  need  to  be  lit.  For  any
other  action,  it  needs  to  be  lit  first.  The  backlight  is  lit  for
±30 seconds when you press a button.

1

Perform introductory steps.

#

Action

1

Open the liquid stop valve and gas stop valve by
removing the cap and turning counterclockwise with a
hex wrench until it stops.

2

Close the service cover to prevent electric shocks.

3

Turn ON power for at least 6 hours before starting
operation to protect the compressor.

4

On the user interface, set the unit to cooling operation
mode.

2

Start the test run.

#

Action

Result

1

Go to the home menu.

Cool

Set to

28

°C

2

Press at least 4 seconds.

The Service Settings menu
is displayed.

3

Select Test Operation.

Return

Setting

Service Settings                   1/3

Test Operation

Maintenance Contact

Field Settings

Demand

Min Setpoints Differential

Group Address

4

Press.

Test Operation is
displayed on the home
menu.

Cool

Return

Setting

Test Operation

5

Press within 10 seconds.

Test run starts.

3

Check operation for 3 minutes.

4

Check operation of the airflow direction.

#

Action

Result

1

Press.

Return 

Setting 

Return

Setting

Air Volume/direction

Air Volume

Direction

Position 0

Low

2

Select Position 0.

Return 

Setting 

Return

Setting

Air Volume/direction

Air Volume

Direction

Low

Position 0

Summary of Contents for Sky Air Active Series

Page 1: ...Installation manual Sky Air Active series English Installation manual Sky Air Active series AZAS100MUV AZAS125MUV AZAS140MUV AZAS100MUY AZAS125MUY AZAS140MUY...

Page 2: ...A B C 250 300 1000 A B C E 250 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 HD HU 250 1500 HU HD HU 300 1500 B D E HB HD HB HU 300 1000 1000 500 HU HB HU 300 1250 1000 500 HB HU HB H...

Page 3: ...e Outdoor unit 17 11 2 Piping diagram Outdoor unit 18 11 3 Wiring diagram Outdoor unit 19 1 About this document Target audience Authorised installers INFORMATION This appliance is intended to be used...

Page 4: ...l the required fuses or circuit breakers Secure the electrical wiring with cable ties so that the cables do NOT come in contact with sharp edges or piping particularly on the high pressure side Do NOT...

Page 5: ...h the instructions from this manual See 9 Commissioning 415 3 About the box Keep the following in mind At delivery the unit MUST be checked for damage and completeness Any damage or missing parts MUST...

Page 6: ...rging refrigerant 412 1 3 If necessary remove the piping intake rear plate This is e g necessary in the following cases 5 1 Connecting the refrigerant piping 48 6 4 To connect the electrical wiring to...

Page 7: ...ly a 4 3 2 To install the outdoor unit 4 M12 4 3 3 To provide drainage INFORMATION If necessary you can use a drain plug kit field supply to prevent drain water from dripping NOTICE If drain holes of...

Page 8: ...ection d Rear connection 1 Remove the following plates For details see 4 2 1 To open the outdoor unit 46 Remove the service cover a and the piping intake front plate b In case the refrigerant piping i...

Page 9: ...the indoor unit cover the stop valves A B see above with sealing material to prevent condensed water on the stop valves from moving to the indoor unit NOTICE Any exposed piping might cause condensatio...

Page 10: ...eck the pressure for at least 1 hour 5 If you do NOT reach the target vacuum or CANNOT maintain the vacuum for 1 hour do the following Check for leaks again Perform vacuum drying again NOTICE Make sur...

Page 11: ...a round crimp style terminal Details are described in Guidelines when connecting the electrical wiring in the installer reference guide 6 4 To connect the electrical wiring to the outdoor unit NOTICE...

Page 12: ...rging additional refrigerant typically consists of the following stages 1 Determining if and how much you have to charge additionally 2 If necessary charging additional refrigerant 3 Filling in the fl...

Page 13: ...accelerate the defrosting process other than those recommended by the manufacturer Be aware that the refrigerant inside the system is odourless 7 3 Completely recharging refrigerant 7 3 1 To determin...

Page 14: ...Applicable legislation on fluorinated greenhouse gases requires that the refrigerant charge of the unit is indicated both in weight and CO2 equivalent Formula to calculate the quantity in CO2 equival...

Page 15: ...e of the compressor is OK There are NO damaged components or squeezed pipes on the inside of the indoor and outdoor units There are NO refrigerant leaks The correct pipe size is installed and the pipe...

Page 16: ...ote Operation will be impossible Turn OFF the power recheck the wiring and switch two of the three electrical wires L4 The air inlet or air outlet is blocked U0 The stop valves are closed U2 There is...

Page 17: ...rvice space between the unit and obstacles A B C D and E eB Maximum distance between the unit and the edge of obstacle E in the direction of obstacle B eD Maximum distance between the unit and the edg...

Page 18: ...ort Service port with 5 16 flare Stop valve Filter Check valve Solenoid valve Heat sink PCB Capillary tube Electronic expansion valve 4 way valve High pressure switch LPS Low pressure switch Compresso...

Page 19: ...l Optional Part n Part n Description Description A1P Printed circuit board main A2P Printed circuit board noise filter BS1 BS3 A1P Push button switch on PCB C A1P Y only Capacitor DS1 A1P Dipswitch E...

Page 20: ...11 Technical data Installation manual 20 AZAS100 140MUV Y Sky Air Active series 4P743507 1 2023 08 L L A L B NA NB E U V W X A A1P A2P Connector...

Page 21: ......

Page 22: ......

Page 23: ......

Page 24: ...4P743507 1 2023 08 Copyright 2023 Daikin 4P743507 1 0000000O Verantwortung f r Energie und Umwelt...

Reviews: