background image

AZQS7 AZQS100~14  AZQS100~140A7W1B
Split System air conditioners
4PW68422-1 – 03.2011

Installation manual

10

Precaution for pumping-down operation

The outdoor unit is equipped with a low pressure switch or a low
pressure sensor to protect the compressor.

Take the following steps to perform the pumping-down operation.

Preliminary measures

Make sure to cut off power supply.
Open the front panel and cover the PCB and terminal board with
insulation sheet to avoid electric shock by accidental touching of
live parts.

Close the front panel before leaving the outdoor unit. You cannot
leave the unit unattended in case the front panel remains opened.

Turn on the power supply and carry out pumping-down operation
according to the following procedure.

Pump down operation

AZQS100~140_W1

AZQS71~140_V1

(a)

 If after finishing pumping-down operation the outdoor unit does not operate, 

not even when the remote controller switch is turned on, the remote controller 
may or may not indicate 

"

U4

"

. But this is not a malfunction.

After finishing the pumping-down operation, make sure to
have removed the insulation sheet that was placed in the
switch box as a protective measure like in chapter

"Preliminary measures" on page 10

.

When in need of operation, turn off the main power supply
and turn it on again. Make sure that stop valves both on
liquid and gas side are open and be sure to operate the
unit in cooling operation during test run.

E

LECTRICAL

 

WIRING

 

WORK

Precautions on electrical wiring work

Before obtaining access to terminal devices, all supply circuits
must be interrupted.

Use only copper wires.

The wiring between the indoor unit and outdoor unit must be for
220~240 V.

A main switch or other means for disconnection, having a
contact separation in all poles, must be incorporated in the fixed
wiring in accordance with relevant local and national legislation.
Do not turn on the main switch until all the wiring is completed. 

For W1
Make sure to connect power supply cables in normal phase. If
connected in reverse phase, the remote controller of the indoor
unit indicates 

"

U1

"

  and the equipment cannot operate. Change

any two of the three power supply cables (L1, L2, L3) to correct
phase.
If the contact in the magnetic switch should be forcibly turned on
while the equipment is inoperative, the compressor will burn out.
Never try to forcibly turn on the contact.

Never squeeze bundled cables into a unit.

Fix cables so that cables do not make contact with the pipes
(especially on high pressure side).

Secure the electrical wiring with clamping material as shown in
the figure below so that it does not come in contact with the
piping, particularly on the high-pressure side.
Make sure no external pressure is applied to the terminal
connectors.

When installing the earth leakage breaker make sure that it is
compatible with the inverter (resistant to high frequency
electrical noise) to avoid unnecessary opening of the earth
leakage breaker.

As this unit is equipped with an inverter, installing a phase
advancing capacitor not only will deteriorate power factor
improvement effect, but also may cause capacitor abnormal
heating accident due to high-frequency waves. Therefore, never
install a phase advancing capacitor.

Never short-circuit the low pressure switch or low pressure
sensor during pump-down operation.

Procedure

Precaution

1

Make sure that stop valves 
both on liquid and on gas side 
are open.

2

Push the BS1 pumping-down 
operation button on the PC 
board of the outdoor unit. 

Compressor and outdoor fan 
will start operation 
automatically.
The indoor unit fan may 
automatically start running.
Please pay attention to this.

3

Once compressor operation 
stops after 3 or 5 minutes

(a)

close the stop valve on the 
liquid side and gas side 
securely. (See 

"How to use 

the stop valve" on page 7

)

Never leave the outdoor unit 
unattended with opened front 
panel when power supply is 
on.

4

Turn off the power supply.

Procedure

Precaution

1

Make sure that stop valves 
both on liquid and on gas side 
are open.

2

Push the BS4 pumping-down 
operation button on the PC 
board of the outdoor unit 
(±8 seconds).

Compressor and outdoor fan 
will start operation 
automatically.
The indoor unit fan may 
automatically start running.
Please pay attention to this.

3

Close the stop valve on the 
liquid side securely about 2 
minutes after the compressor 
started operation. (See 

"How 

to use the stop valve" on 
page 7

)

Never leave the outdoor unit 
unattended with opened front 
panel when power supply is 
on.
In case the stop valve on the 
liquid side is not securely 
closed during compressor 
operation, pumping-down 
operation cannot be executed.

4

Once compressor operation 
stops after 2 to 5 minutes

(a)

close the stop valve on the 
gas side securely. (See 

"How 

to use the stop valve" on 
page 7

)

5

Turn off the power supply.

All field wiring and components must be installed by a
licensed electrician and must comply with relevant
European and national regulations.

All components procured on the site and all electric
construction should comply with the applicable local
and national codes.

High voltage
To avoid electrical shock, make sure to disconnect the
power supply 1 minute or more before servicing the
electrical parts. Even after 1 minute, always measure
the voltage at the terminals of main circuit capacitors
or electrical parts and, before touching, make sure
that those voltages are 50 V DC or less.

To persons in charge of electrical wiring work:

Do not operate the unit until the refrigerant piping is
complete. (Running it before the piping is ready will break
the compressor.)

Summary of Contents for Siesta AZQS100A7V1B

Page 1: ...INSTALLATION MANUAL AZQS71A2V1B AZQS100A7V1B AZQS125A7V1B AZQS140A7V1B AZQS100A7W1B AZQS125A7W1B AZQS140A7W1B Split System air conditioners ...

Page 2: ...50 Hz 220 240 V R410A 1 2 4 5 6 3 1 3 2 4 5 A B A E B C D H H1 L1 A A B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 A A B1 B1 B1 B1 B1 B1 B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 1 1 2 L1 L3 L2 L1 L3 L2 1 2 3 4 5 6 ...

Page 3: ...ıÂÙÈÎ fi ÙÔ B Û ÌÊˆÓ Ì ÙÔ ÈÛÙÔ ÔÈËÙÈÎfi C 08 Nota tal como estabelecido em A e com o parecer positivo de B de acordo com o Certificado C 09 Примечание как указано в A и в соответствии с положительным решением B согласно Свидетельству C 10 Bemærk som anført i A og positivt vurderet af B i henhold til Certifikat C 11 Information enligt A och godkänts av B enligt Certifikatet C 12 Merk som det fremkom...

Page 4: ...llation work may result in accidents due to fall of equipment Make certain that all electrical work is carried out by qualified personnel according to the local laws and regulations and this installation manual using a separate circuit Insufficient capacity of the power supply circuit or improper electrical construction may lead to electric shocks or fire Make sure that all wiring is secure using ...

Page 5: ...vels of salt such as that near the ocean Where voltage fluctuates a lot such as that in factories In vehicles or vessels Where acidic or alkaline vapour is present Provide a logbook In accordance with the relevant national and international codes it may be necessary to provide a logbook with the equipment containing at least info on maintenance repair work results of tests stand by periodes etc In...

Page 6: ...strong wind blows continuously on the face of the unit the fan can start rotating very fast until it breaks Refer to the figures for installation of this unit in a place where the wind direction can be foreseen Turn the air outlet side toward the building s wall fence or screen Set the outlet side at a right angle to the direction of the wind 3 Prepare a water drainage channel around the foundatio...

Page 7: ...ipe disposal from the outdoor unit causes trouble for example if the drain water may splash on people provide the drain piping using a drain socket optional Make sure the drain works properly INSTALLATION SERVICING SPACE The numerical figures used in here represent the dimensions for the 71 100 125 140 class models Figures between indicate the dimensions for the 100 125 140 class models Unit mm Re...

Page 8: ... L H 0 L 1 2H 150 250 1 2H L 200 300 H L Installation impossible Installation shall be done by a licensed refrigeration technician the choice of materials and installation shall comply with the applicable national and international codes In Europe EN378 is the applicable standard that shall be used To persons in charge of piping work Be sure to open the stop valve after piping installing and vacum...

Page 9: ...repair paint to the edge and the surrounding end surfaces to prevent rusting Preventing foreign objects from entering Plug the pipe through holes with putty or insulating material procured locally to stop up all gaps as shown in the figure Insects or small animals entering the outdoor unit may cause a short circuit in the electrical box Cautions for handling stop valve The stop valves for indoor o...

Page 10: ... material If the temperature is higher than 30 C and the humidity is higher than RH 80 then the thickness of the sealing materials should be at least 20 mm in order to avoid condensation on the surface of the sealing Be sure to insulate the liquid and gas side field piping and the refrigerant branch kit The highest temperature that the gas side piping can reach is around 120 C so be sure to use in...

Page 11: ...cedure for leak test Leak test must satisfy EN378 2 1 Evacuate the pipes and check vacuum 1 No pressure increase for 1 minute 2 Break the vacuum with a minimum of 2 bar of nitrogen Never pressurize more than 4 0 MPa 3 Conduct leak test by applying soap water etc to the connecting part of the pipes 4 Discharge nitrogen 5 Evacuate and check vacuum again 1 6 If the vacuum gauge no longer rises the st...

Page 12: ...s relate to the refrigerant piping length as in Maximum total one way piping length of the table in paragraph Allowable pipe length and height difference on page 5 Table 2 Total charging amount unit kg NOTE National implementation of EU regulation on certain fluorinated greenhouse gases may require to provide the appropriate official national language on the unit Therefore an additional multilingu...

Page 13: ...side Make sure no external pressure is applied to the terminal connectors When installing the earth leakage breaker make sure that it is compatible with the inverter resistant to high frequency electrical noise to avoid unnecessary opening of the earth leakage breaker As this unit is equipped with an inverter installing a phase advancing capacitor not only will deteriorate power factor improvement...

Page 14: ...easons be sure to observe the following instruction Do not connect wires of different gauge to the same power supply terminal Looseness in the connection may cause overheating When connecting wires of the same gauge connect them according to the below figure Use the correct screwdriver to tighten the terminal screws Small screwdrivers can damage the screw head and prevent appropriate tightening Ov...

Page 15: ...e unit returns to normal operation 10 Check all functions according to the operation manual AZQS 71V1 100V1 125V1 140V1 100W1 125W1 140W1 Minimum circuit amps MCA a a Stated values are maximum values see electrical data of combination with indoor units for exact values 18 9 27 6 28 8 17 1 18 3 Recommended field fuse A 20 32 20 Wire type b b Only in protected pipes use H07RN F when protected pipes ...

Page 16: ...may have run out If the remote controller shows E3 E4 or L8 as an error code there is a possibility that either the stop valves are closed or that air inlet or air outlet are blocked If the error code U2 is displayed on the remote controller check for voltage imbalance If the error code U4 or UF is displayed on the remote controller check the inter unit branch wiring connection If the error code L...

Page 17: ...or discharge for V1 models only R3T Thermistor discharge pipe for W1 models only R3T Thermistor suction pipe for V1 models only R4T Thermistor suction pipe for W1 models only R4T Thermistor coil for V1 models only R5T Thermistor power module for W1 models only R5T Thermistor coil middle for V1 models only R6T Thermistor liquid R10T Thermistor fin RC Signal receiver circuit S1NPL Pressure sensor lo...

Page 18: ......

Page 19: ......

Page 20: ...4PW68422 1 03 2011 Copyright 2011 Daikin ...

Reviews: