Outdoor Unit Installation

3.

Flaring the pipe end 

1) Cut the pipe end with a pipe cutter.
2) Remove burrs with the cut surface facing 

downward so that the chips do not enter the pipe.

3) Put the flare nut on the pipe.
4) Flare the pipe.
5) Check that the flaring is properly made.

 WARNING

• Do not use mineral oil on flared part.
• Prevent mineral oil from getting into the system as this would reduce the lifetime of the units.
• Never use piping which has been used for previous installations. Only use parts which are delivered with the unit.
• Do never install a drier to this R410A unit in order to guarantee its lifetime.
• The drying material may dissolve and damage the system.
• Incomplete flaring may cause refrigerant gas leakage.

4.

Refrigerant piping

 CAUTION

• Use the flare nut fixed to the main unit. (To prevent cracking of the flare nut by aged deterioration.)
• To prevent gas leakage, apply refrigeration oil only to the inner surface of the flare. (Use refrigeration oil for R410A.)
• Use torque wrenches when tightening the flare nuts to prevent damage to the flare nuts and gas leakage.

Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand.  Then tighten them fully with the torque wrenches. 

(Cut exactly at 

right angles.)

 Remove burrs.

Set exactly at the position shown below.

A

Flaring

Die

Check

Flare’s inner 
surface must 
be flaw-free.

The pipe end must 
be evenly flared in 
a perfect circle.

Make sure that the 
flare nut is fitted.

A

0-0.5mm

Clutch-type

Flare tool for R410A

1.0-1.5mm

Clutch-type (Rigid-type)

1.5-2.0mm

Wing-nut type (Imperial-type)

Conventional flare tool

Torque wrench

Piping union

Flare nut

Flare nut tightening torque

 

Gas side

Liquid side

 

3/8 inch

1/4 inch

 32.7-39.9N 

l

 m 

14.2-17.2N 

l

 m

 

(333-407kgf 

l

 cm) 

(144-175kgf 

l

 cm)

Valve cap tightening torque

 

Gas side

Liquid side

 

3/8 inch

1/4 inch

 21.6-27.4N 

l

 m 

21.6-27.4N 

l

 m

  (220-280kgf 

l

 cm) 

(220-280kgf 

l

 cm)

Service port cap 

10.8-14.7N 

l

 m

tightening torque 

(110-150kgf 

l

 cm)

Do not apply refrigeration 

oil to the outer surface.

Flare nut

Apply refrigeration oil to 

the inner surface of the 

flare.

Do not apply refrigeration 

oil to the flare nut avoid 

tightening with over torque.

Spanner

[Apply oil]

[Tighten]

01_EN_3P203824-8H.fm  Page 5  Tuesday, October 26, 2010  8:33 PM

Summary of Contents for RXS20J2V1B

Page 1: ...ion manual R410A Split series Montaj k lavuzlar R410A Split serisi Installationsanleitung Split Baureihe R410A Manuel d installation S rie split R410A Montagehandleiding R410A Split systeem Manual de...

Page 2: ...e 2006 95 EC Electromagnetic Compatibility 2004 108 EC 3SB64564 12E Shinri Sada Manager Quality Control Department DAIKIN TCF 015 N4 09 2010 RXS20J2V1B RXS25J2V1B RXS35J2V1B RKS20J2V1B RKS25J2V1B RKS3...

Page 3: ...ls If refrigerant gas leaks during installation ventilate the area immediately Toxic gas may be produced if the refrigerant comes into contact with fire After completing installation check for refrige...

Page 4: ...8 In coastal areas or other places with salty atmosphere of sulfate gas corrosion may shorten the life of the air conditioner 9 Since drain flows out of the outdoor unit do not place under the unit a...

Page 5: ...necting the FVXS indoor unit the shortest piping length should be no less than around 2 5m 1 5m Min allowable length CAUTION Set the piping length from 1 5m to 20m Wrap the insulation pipe with the fi...

Page 6: ...door Unit Installation 1 Installing outdoor unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawings 2 If drain work is necess...

Page 7: ...re nuts to prevent damage to the flare nuts and gas leakage Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand Then tighten them fully with the torque wrenches Cut exactl...

Page 8: ...p valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve subsequently requires no operation 3 Do vacuum pumping an...

Page 9: ...on dimensions as below 3 Use separate thermal insulation pipes for gas and liquid refrigerant pipes Gas side Liquid side Gas pipe thermal insulation Liquid pipe thermal insulation O D 9 5mm O D 6 4mm...

Page 10: ...turned off Turn it off if has not been turned off 2 Remove the stop valve cover 3 Disconnect the selective connector for standby electricity saving 4 Turn on the main power supply CAUTION Before conne...

Page 11: ...ing the switch do not touch the terminal block It has a high voltage so doing so may cause electric shock After closing the liquid stop valve close the gas stop valve within 3 minutes then stop the fo...

Page 12: ...supply terminal board Precautions to be taken for power supply wiring Use a round crimp style terminal for connection to the power supply terminal board In case it cannot be used due to unavoidable r...

Page 13: ...tion in accordance with the operation manual to ensure that all functions and parts such as louver movement are working properly The air conditioner requires a small amount of power in its standby mod...

Page 14: ...1101 HT 3P203824 8H M09B389 Two dimensional bar code is a code for manufacturing 00_CV_3P203824 8H fm Page 2 Thursday October 7 2010 11 00 AM...

Reviews: