Trial Operation and Testing

1.

Trial operation and testing

1-1 Measure the supply voltage and make sure that it falls in the specified range.
1-2 Trial operation should be carried out in either cooling or heating mode.

For heat pump

• In cooling mode, select the lowest programmable temperature; in heating mode, select the highest programmable 

temperature.
1) Trial operation may be disabled in either mode depending on the room temperature.
2) After trial operation is complete, set the temperature to a normal level (26°C to 28°C in cooling mode, 20°C to 24°C 

in heating mode).

3) For protection, the system disables restart operation for 3 minutes after it is turned off.

1-3 Carry out the test operation in accordance with the operation manual to ensure that all functions and parts, 

such as louver movement, are working properly.

• The air conditioner requires a small amount of power in its standby mode.  If the system is not to be used for some 

time after installation, shut off the circuit breaker to eliminate unnecessary power consumption.

• If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original operation 

mode when the circuit breaker is opened again.

2.

Fault diagnosis by LED on outdoor unit PCB

NOTE

Error detection should be done using the remote control fault diagnosis.

3.

Test items 

Diagnosis

LED is flashing

Normal -> check the indoor unit

LED is ON

Turn the power OFF and then ON again and check the LED within approx. 3 min-
utes. (If the LED display recurs, the outdoor unit PCB is fault.)

LED is OFF

CASE1: 

Supply voltage (For power saving)

CASE2:

 Power supply fault

CASE3:

 Turn the power OFF and then ON again and check the LED within 

approx. 3 minutes. (If the LED display recurs, the outdoor unit PCB is fault.)

Test items

Symptom

Check

Indoor and outdoor units are installed properly on solid bases.

Fall, vibration, noise

No refrigerant gas leaks.

Incomplete cooling/heating 
function

Refrigerant gas and liquid pipes and indoor drain hose extension are 
thermally insulated.

Water leakage

Draining line is properly installed.

Water leakage

System is properly earthed.

Electrical leakage

Electric wires are connected correctly.

Incomplete cooling/heating 
function

The specified wires are used for inter-unit wiring.

Inoperative or burn damage

Indoor or outdoor unit’s air inlet or air outlet has clear path of air.
Stop valves are opened.

Incomplete cooling/heating 
function

Indoor unit properly receives remote control commands.

Inoperative

3PEN386698-4L.book  Page 16  Thursday, April 27, 2017  8:43 AM

Summary of Contents for RXM42M3V1B9

Page 1: ...INSTALLATION MANUAL R32 Split Series Models RXM42M3V1B9 RXM50M3V1B9 RXM60M3V1B9 ARXM50M3V1B9 3PEN386698 4L book Page 1 Thursday April 27 2017 8 43 AM...

Page 2: ...ente por B de acuerdo con el Certificado C 06 Nota delineato nel A e giudicato positivamente da B secondo il Certificato C 07 A B C 08 Nota tal como estabelecido em A e com o parecer positivo de B de...

Page 3: ...ivt intygats av E Fastsatt modul F vilket ocks framg r av Certifikat G Riskkategori H Se ven n sta sida 12 som det fremkommer i A og gjennom positiv bed mmelse av B if lge Sertifikat C som det fremkom...

Page 4: ...astunud temperatuur M C Jahutusaine N Surve turvaseadme seadistus P bar Tootmisnumber ja tootmisaasta vaadake mudeli andmeplaati 21 PS K bar TS TSmin L C TSmax PS M C N P bar 22 Maksimalus leistinas s...

Page 5: ...nections or wires Improper connections or securing of wires may result in abnormal heat build up or fire When wiring the power supply and connecting the wiring between the indoor and outdoor units pos...

Page 6: ...erant circuit will be high please keep the inter unit wire away from copper pipes that are not thermally insulated This appliance is intended to be used by expert or trained users in shops in light in...

Page 7: ...ages and sounds Noises may be heard even if they are more than 3m away depending on radio wave conditions 8 In coastal areas or other places with salty atmosphere of sulfate gas corrosion may shorten...

Page 8: ...t Failure to do so may result in reduced performance The suggested shortest pipe length is 1 5m in order to avoid noise from the outdoor unit and vibration Mechanical noise and vibration may occur dep...

Page 9: ...Unit Installation 1 Installing outdoor unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawings 2 If drain work is necessary...

Page 10: ...mage to the flare nuts and gas leakage After the piping work is finished after checking for gas leaks open the stop valves or the compressor might break down Align the centres of both flares and tight...

Page 11: ...oint may exists Check all pipe joints and retighten nuts as needed then repeat steps 2 through 4 1 Connect projection side of charging hose which comes from gauge manifold to gas stop valve s service...

Page 12: ...product contains fluorinated greenhouse gases Do not vent gases into the atmosphere Refrigerant type GWP value factory refrigerant charge of the product see unit name plate additional refrigerant amo...

Page 13: ...liquid piping and to provide insulation dimensions as below 3 Use separate thermal insulation for gas and liquid refrigerant pipes NOTE Piping and other pressure containing parts shall comply with the...

Page 14: ...unit ON OFF switch for at least 5 seconds The operation will start Forced cooling operation will stop automatically after around 15 minutes To stop the operation press the indoor unit ON OFF switch Us...

Page 15: ...ses may be produced by the indoor unit due to the outdoor fan turning on and off when using facility settings Do not place humidifiers or other items which might raise the humidity in rooms where faci...

Page 16: ...oor unit Doing so may cause electric shock or fire Do not turn ON the safety breaker until all work is completed 1 Strip the insulation from the wire 20mm 2 Connect the inter unit wire between the ind...

Page 17: ...ace with a wire stop 1 Safe handling of high voltage part Turn the circuit breaker off and wait for 10 minutes before servicing 1 1 To prevent electrical shock Check the voltage of max DC50V between D...

Page 18: ...OR E H HEATER RC RECEIVER F U FU FOR CHARACTERISTICS REFER TOPCBINSIDE YOUR UNIT FUSE S C LIMIT SWITCH FG CONNECTOR FRAMEGROUND S L FLOAT SWITCH H HARNESS S NPH PRESSURESENSOR HIGH H P LED V L PILOT L...

Page 19: ...e connector for standby electricity saving 5 Turn on the main power supply CAUTION Before connecting or disconnecting the selective connector for standby electricity saving make sure that the main pow...

Page 20: ...the circuit breaker is opened again 2 Fault diagnosis by LED on outdoor unit PCB NOTE Error detection should be done using the remote control fault diagnosis 3 Test items Diagnosis LED is flashing No...

Page 21: ...3PEN386698 4L book Page 1 Thursday April 27 2017 8 43 AM...

Page 22: ...3PEN386698 4L book Page 2 Thursday April 27 2017 8 43 AM...

Page 23: ...3PEN386698 4L book Page 3 Thursday April 27 2017 8 43 AM...

Page 24: ...3P386698 4L 2017 04 Copyright 2017 Daikin 3PEN386698 4L book Page 1 Thursday April 27 2017 8 43 AM...

Reviews: