Refilling refrigerant

Check the type of refrigerant to be used on the machine nameplate.

Precautions when adding R410A
Fill from the liquid pipe in liquid form.

R410A is a mixed refrigerant, so adding it in gas form may cause the refrigerant composition to change, preventing normal 

operation.
1) 

Before filling, check whether the cylinder has a siphon attached or not. (It should have something like “liquid filling siphon 

attached” displayed on it.)

Filling a cylinder with an attached siphon

Stand the cylinder upright when filling.

There is a siphon pipe inside, so the cylinder 

need not be upside-down to fill with liquid.

Filling other cylinders

Turn the cylinder 

upside-down when filling.

• 

Be sure to use the R410A tools to ensure pressure and to prevent foreign objects entering.

7. 

Refrigerant piping work 

7-1. Cautions on pipe handling

• 

Protect the open end of the pipe from dust and moisture.

• 

All pipe bends should be as gentle as possible. Use a pipe bender for 
bending.

7-2. Selection of copper and heat insulation materials

When using commercial copper pipes and fittings, observe the following:

• 

Insulation material: Polyethylene foam
Heat transfer rate: 0.041 to 0.052W/mK (0.024 to 0.030Btu/fth°F (0.035 
to 0.045kcal/mh°C))
Be sure to use insulation that is designed for use with HVAC Systems.

• 

ACR Copper only.

• 

Be sure to insulate both the gas and liquid piping and observe the 
insulation dimensions as below.

Wall

If no flare cap is 

available, cover 

the flare mouth 

with tape to keep 

dirt and water out.

Be sure to 

place a cap.

Rain

Gas side

Piping size

O.D. 3/8 inch

(9.5mm)

O.D. 1/2 inch

(12.7mm)

O.D. 5/8 inch

(15.9mm)

O.D. 1/4 inch

(6.4mm)

1-3/16 inch (30mm)

or more

1-9/16 inch (40mm)

or more

1-15/16 inch (50mm)

or more

1-3/16 inch (30mm)

or more

0.031 inch (0.8mm)

(C1220T-O)

0.039 inch (1.0mm)

(C1220T-O)

0.031 inch (0.8mm)

(C1220T-O)

I.D. 15/32-19/32 inch

(12-15mm)

I.D. 9/16-5/8 inch

(14-16mm)

I.D. 5/8-13/16 inch

(16-20mm)

I.D. 5/16-13/32 inch

(8-10mm)

13/32 inch

(10mm) Min.

Minimum bend radius

Piping thickness

Thermal insulation size

Thermal insulation

thickness

Liquid side

• 

Use separate thermal insulation pipes for gas and liquid refrigerant pipes.

Gas pipe

Liquid pipe

Gas pipe 
insulation

Liquid pipe 
insulation

Finishing tape

Drain hose

English

01_EN_3P500432-5E.indd   8

10/17/2019   4:40:24 PM

Summary of Contents for RX15RMVJU

Page 1: ...DAIKIN ROOM AIR CONDITIONER INSTALLATION MANUAL R410A Split Series Installation manual Manuel dinstallation Manual de instalaci n MODELS RX15RMVJU RX18RMVJU9 RX24RMVJU RX15RMVJUA RX18RMVJU9A RX24RMVJ...

Page 2: ...hazard could occur leading to serious injury or death Do not ground units to water pipes gas pipes telephone wires or lightning rods as incomplete grounding can cause a severe shock hazard resulting i...

Page 3: ...getting into the system b Tight R410A does not contain any chlorine does not destroy the ozone layer and does not reduce the earth s protection again harmful ultraviolet radiation R410A can contribut...

Page 4: ...ble gas leaks in the surrounding area 7 In coastal areas or other places with a salty atmosphere or one containing sulfate gas corrosion may shorten the life of the air conditioner 8 Since water will...

Page 5: ...lt in reduced performance The suggested shortest pipe length is 10ft 3m in order to avoid noise from the outdoor unit and vibration Mechanical noise and vibration may occur depending on how the unit i...

Page 6: ...all facing one side Walls facing two sides Top view Top view More than 5 7 8 150 More than 11 13 16 300 More than 1 15 16 50 Walls facing three sides unit inch mm unit inch mm Top view More than 3 15...

Page 7: ...vice life The drying material may dissolve and damage the system Incomplete flaring may result in refrigerant gas leakage 4 Refrigerant piping CAUTION Use the flare nut fixed to the main unit This is...

Page 8: ...ssure drop check for leaks make repairs and perform the pressure test again 2 Connect the gauge manifold s charging hose to the gas stop valve s service port 3 Fully open the gauge manifold s low pres...

Page 9: ...insulation materials When using commercial copper pipes and fittings observe the following Insulation material Polyethylene foam Heat transfer rate 0 041 to 0 052W mK 0 024 to 0 030Btu fth F 0 035 to...

Page 10: ...2 3 1 2 3 Follow local codes for wiring and safety devices between outdoor unit and power source Ground Firmly x the wires with the terminal screws Recommend using AWG14 stranded and insulated wire fo...

Page 11: ...r power supply wiring When using stranded wires make sure to use the round crimp style terminal for connection to the power supply terminal block Stranded wire Round crimp style terminal Arrow view Fl...

Page 12: ...tion In order to protect the environment be sure to pump down when relocating or disposing of the unit 1 Remove the valve cap from the liquid stop valve and gas stop valve 2 Carry out forced cooling o...

Page 13: ...ter about 30 minutes To stop the operation press Trial Operation and Testing 1 Trial operation and testing Refer to the installation manual for the indoor unit 2 Test items Test items Symptom Check In...

Page 14: ...Two dimensional bar code is a manufacturing code 3P500432 5E M19B232 1912 HT...

Reviews: