background image

6 Installation

Installer reference guide

16

2(A)MXM40+50M(3)(4)V1B(9)_2(A)MXF40+50A2V1B

R32 Split series

4P600463-2 – 2019.10

Stem cap

Piping Ø (mm)

Tightening torque (N∙m)

Liquid side

6.4

22~28

Gas side

9.5

33~39

12.7

49~59

To handle the service cap

▪ ALWAYS use a charge hose equipped with a valve depressor pin,

since the service port is a Schrader type valve.

▪ After  handling  the  service  port,  tighten  the  service  port  cap,  and

check for refrigerant leaks.

Item

Tightening torque (N∙m)

Service port cap

11~14

6.4.8

To connect the refrigerant piping to the
outdoor unit

Piping length.

 Keep field piping as short as possible.

Piping  protection.

  Protect  the  field  piping  against  physical

damage.

1

Connect the liquid refrigerant connection from the indoor unit to
the liquid stop valve of the outdoor unit.

a

c

b

a

b

a

Liquid stop valve

b

Gas stop valve

c

Service port

2

Connect  the  gas  refrigerant  connection  from  the  indoor  unit  to
the gas stop valve of the outdoor unit.

NOTICE

It  is  recommended  that  the  refrigerant  piping  between
indoor  and  outdoor  unit  is  installed  in  a  ducting  or  the
refrigerant piping is wrapped with finishing tape.

6.5

Checking the refrigerant piping

6.5.1

About checking the refrigerant piping

The outdoor unit's 

internal

 refrigerant piping has been factory tested

for  leaks.  You  only  have  to  check  the  outdoor  unit's 

external

refrigerant piping.

Before checking the refrigerant piping

Make  sure  the  refrigerant  piping  is  connected  between  the  outdoor
unit and the indoor unit.

Typical workflow

Checking  the  refrigerant  piping  typically  consists  of  the  following
stages:

1

Checking for leaks in the refrigerant piping.

2

Performing  vacuum  drying  to  remove  all  moisture,  air  or
nitrogen from the refrigerant piping.

If  there  is  a  possibility  of  moisture  being  present  in  the  refrigerant
piping  (for  example,  water  may  have  entered  the  piping),  first  carry
out  the  vacuum  drying  procedure  below  until  all  moisture  has  been
removed.

6.5.2

Precautions when checking the
refrigerant piping

INFORMATION

Also  read  the  precautions  and  requirements  in  the
following chapters:

▪ General safety precautions

▪ Preparation

NOTICE

Use  a  2-stage  vacuum  pump  with  a  non-return  valve  that
can  evacuate  to  a  gauge  pressure  of  −⁠100.7  kPa
(−⁠1.007  bar)(5  Torr  absolute).  Make  sure  the  pump  oil
does not flow oppositely into the system while the pump is
not working.

NOTICE

Use  this  vacuum  pump  for  R32  exclusively.  Using  the
same  pump  for  other  refrigerants  may  damage  the  pump
and the unit.

NOTICE

▪ Connect  the  vacuum  pump  to  the  service  port  of  the

gas stop valve.

▪ Make sure that the gas stop valve and liquid stop valve

are  firmly  closed  before  performing  the  leak  test  or
vacuum drying.

6.5.3

To check for leaks

NOTICE

Do NOT exceed the unit's maximum working pressure (see
"PS High" on the unit name plate).

NOTICE

Make  sure  to  use  a  recommended  bubble  test  solution
from  your  wholesaler.  Do  not  use  soap  water,  which  may
cause cracking of flare nuts (soap water may contain salt,
which  absorbs  moisture  that  will  freeze  when  the  piping
gets  cold),  and/or  lead  to  corrosion  of  flared  joints  (soap
water  may  contain  ammonia  which  causes  a  corrosive
effect between the brass flare nut and the copper flare).

1

Charge the system with nitrogen gas up to a gauge pressure of
at  least  200  kPa  (2  bar).  It  is  recommended  to  pressurize  to
3000 kPa (30 bar) in order to detect small leaks.

2

Check  for  leaks  by  applying  the  bubble  test  solution  to  all
connections.

3

Discharge all nitrogen gas.

6.5.4

To perform vacuum drying

Connect the vacuum pump and manifold as follows:

Summary of Contents for R32 Split Series

Page 1: ...Installer reference guide R32 Split series English Installer reference guide R32 Split series 2MXM40M4V1B 2MXM50M3V1B9 2AMXM40M4V1B 2AMXM50M4V1B 2AMXF40A2V1B 2AMXF50A2V1B 2MXF40A2V1B 2MXF50A2V1B...

Page 2: ...ping 16 6 5 2 Precautions when checking the refrigerant piping 16 6 5 3 To check for leaks 16 6 5 4 To perform vacuum drying 16 6 6 Charging refrigerant 17 6 6 1 About charging refrigerant 17 6 6 2 Pr...

Page 3: ...optional equipment and spare parts made or approved by Daikin WARNING Make sure installation testing and applied materials comply with applicable legislation on top of the instructions described in t...

Page 4: ...example national gas regulation and are executed only by authorised persons Installation space requirements NOTICE Pipework shall be protected from physical damage Installation of pipework shall be k...

Page 5: ...leaks ventilate the area immediately Possible risks Excessive refrigerant concentrations in a closed room can lead to oxygen deficiency Toxic gas may be produced if refrigerant gas comes into contact...

Page 6: ...installed in the fixed wiring WARNING ONLY use copper wires Make sure the field wiring complies with the applicable legislation All field wiring MUST be performed in accordance with the wiring diagra...

Page 7: ...rence data Format Digital files on http www daikineurope com support and manuals product information Latest revisions of the supplied documentation may be available on the regional Daikin website or v...

Page 8: ...ifferent models 4 2 1 Identification label Outdoor unit Location 5 Preparation 5 1 Overview Preparation This chapter describes what you have to do and know before going on site It contains information...

Page 9: ...ectrical servicing 250 300 mm NOTICE Do NOT stack the units on each other Do NOT hang the unit on a ceiling Strong winds 18 km h blowing against the outdoor unit s air outlet causes short circuit suct...

Page 10: ...r unit 412 for more details In heavy snowfall areas it is very important to select an installation site where the snow will NOT affect the unit If lateral snowfall is possible make sure that the heat...

Page 11: ...may cause accidents WARNING All wiring MUST be performed by an authorised electrician and MUST comply with the applicable legislation Make electrical connections to the fixed wiring All components pro...

Page 12: ...e installed directly on a concrete veranda or another solid surface as long as it provides proper drainage Fix the unit securely by means of foundation bolts in accordance with the foundation drawing...

Page 13: ...rk without connecting the indoor unit in order to add another indoor unit later 6 4 1 About connecting the refrigerant piping Before connecting the refrigerant piping Make sure the outdoor and indoor...

Page 14: ...rench b Spanner c Piping union d Flare nut Piping size mm Tightening torque N m Flare dimensions A mm Flare shape mm 6 4 15 17 8 7 9 1 R 0 4 0 8 2 45 90 2 A 9 5 33 39 12 8 13 2 12 7 50 60 16 2 16 6 6...

Page 15: ...valve parts required when handling the valve c d a b a Service port and service port cap b Valve stem c Field piping connection d Stem cap Keep both stop valves open during operation Do NOT apply exc...

Page 16: ...ove all moisture air or nitrogen from the refrigerant piping If there is a possibility of moisture being present in the refrigerant piping for example water may have entered the piping first carry out...

Page 17: ...ing additional refrigerant When the total liquid piping length is more than specified see later Completely recharging refrigerant Example When relocating the system After a leak Charging additional re...

Page 18: ...it name plate the determined additional amount 6 6 6 To charge additional refrigerant WARNING Only use R32 as refrigerant Other substances may cause explosions and accidents R32 contains fluorinated g...

Page 19: ...e interconnection wiring away from copper pipes without thermal insulation as such pipes will be very hot DANGER RISK OF ELECTROCUTION All electrical parts including thermistors are powered by the pow...

Page 20: ...nal numbers match Make sure to match the symbols for piping and wiring 4 Make sure to connect correct wiring to correct room A to A B to B e A a A a B e B b c d 1 2 3 L N 1 2 3 f a Terminal for room A...

Page 21: ...tdoor unit see To turn on ECONO mode prohibition setting 421 2 Cut the jumper J6 J26 J24 J23 J6 J22 J8 3 Reinstall the top plate and the electric box cover CAUTION When reinstalling the electric box c...

Page 22: ...fter the installation of the unit first check the items listed below Once all checks are fulfilled the unit must be closed Power up the unit after it is closed The indoor unit is properly mounted The...

Page 23: ...it operates properly please make sure the following is clear for the user Make sure that the user has the printed documentation and ask him her to keep it for future reference Inform the user that he...

Page 24: ...as a timer or connected to a circuit that is regularly turned ON and OFF by the utility DANGER RISK OF BURNING 10 3 Solving problems based on symptoms 10 3 1 Symptom Indoor units fall vibrate or make...

Page 25: ...d stop forced cooling There are 2 methods to perform forced cooling Method 1 Using the indoor unit ON OFF switch if present on the indoor unit Method 2 Using the indoor unit user interface 11 3 1 To s...

Page 26: ...or Q M Thermo switch R Resistor R T Thermistor RC Receiver S C Limit switch S L Float switch S NPH Pressure sensor high Symbol Meaning S NPL Pressure sensor low S PH HPS Pressure switch high S PL Pres...

Page 27: ...rates the product Applicable legislation All international European national and local directives laws regulations and or codes that are relevant and applicable for a certain product or domain Service...

Page 28: ...4P600463 2 2019 10 Copyright 2019 Daikin...

Reviews: