Equipment Start-up
Initial start-up of the Incremental® conditioners by experi
-
enced personnel is usually the responsibility of the installing
contractor. This start-up consist of inspecting and operating
the equipment for all functions at the time of initial instal
-
lation and making necessary adjustments. It also includes
demonstrating its proper operation to the owner or his agent.
Note:
that unless otherwise specifically agreed to in writing,
Daikin includes no field labor, start-up service or the
like in the price of its equipment.
After the equipment leaves the factory, it may become
damaged or maladjusted during transportation or on the
job. Sometimes wires are disconnected accidentally or fan
motors move on their bases due to rough handling, causing
fans to strike. The correction of such conditions is part of
start-up.
CAUTION
Before starting equipment, make certain that:
1. Correct voltage has been supplied to the equipment.
2. The electrical plug from the control box has been
inserted into the receptacle.
During Start-up (applies only to standard equipment):
Note:
Direction of conditioner air may be adjusted by
repositioning the discharge grille(s) to change airflow
pattern in a room. The building superintendent or
assistant manager should be requested to make any
changes.