![Daikin FHA100AVEB8 User Reference Manual Download Page 75](http://html.mh-extra.com/html/daikin/fha100aveb8/fha100aveb8_user-reference-manual_2460428075.webp)
20
|
Commissioning
Installer and user reference guide
75
FHA-A(9)
Split system air conditioner
4P708119-1 – 2022.11
20 Commissioning
NOTICE
General commissioning checklist.
Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during commissioning
and hand-over to the user.
In this chapter
20.1 Overview: Commissioning
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
20.2 Precautions when commissioning
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50 hours before reaching smooth operation and
stable power consumption.
NOTICE
Before starting up the system, the unit MUST be energised for at least 6 hours to
avoid compressor breakdown during startup.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
Summary of Contents for FHA100AVEB8
Page 89: ......
Page 90: ......
Page 91: ......
Page 92: ...4P708119 1 2022 11 Copyright 2022 Daikin Verantwortung für Energie und Umwelt ...