Installation manual

9

FCQ35~14 FCQH71~140C7VEB

Split System air conditioners

4PW31577-1B

5

Press Inspection/Test Operation button 

 4 times

(2 times for wireless remote controller) and operate at Test
Operation mode for 3 minutes.

6

Push air flow direction adjust button 

 to make sure

the unit is in operation.

7

Press Inspection/Test Operation button 

 and operate

normally.

8

Confirm function of unit according to the operation manual.

Test operation before installing decoration panel (See 

"Notes" on

page 10

)

1

Open the gas side stop valve.

2

Open the liquid side stop valve.

3

Electrify crank case heater for 6 hours.

4

Set to cooling operation with the wired remote controller and
start operation by pushing ON/OFF button.

5

Press Inspection/Test Operation button 

 4 times and

operate at Test Operation mode for 3 minutes.

6

Press Inspection/Test Operation button 

 and operate

normally.

7

Confirm function of unit according to the operation manual.

8

Turn off the main power supply after operation.

Precautions

1

In case something is wrong with the unit and it does not operate,
refer to the installation manual attached to the outdoor unit or
contact your dealer.

2

Refer to the installation manual attached to the outdoor unit in
case of Individual Operation System type.

3

Conduct test operation after installing decoration panel if the
wireless remote controller is used.

N

OTES

NOTE

Do not touch the drain pump, this may cause electrical
shock.

/TEST

SWING

/TEST

/TEST

/TEST

Downloaded from AC-Manual.com Manuals

Summary of Contents for FCQ35C7VEB x 3

Page 1: ...ION MANUAL FCQ35C7VEB FCQ50C7VEB FCQ60C7VEB FCQ71C7VEB FCQ100C7VEB FCQ125C7VEB FCQ140C7VEB FCQH71C7VEB FCQH100C7VEB FCQH125C7VEB FCQH140C7VEB Split System air conditioners Downloaded from AC Manual co...

Page 2: ...1500 3 2 4 5 1 50 100 2 1 3 4 950 1 1 5 35 35 3 5 0 75 675 850 175 300 mm 1 1 5 m 2 3 1 5 6 100 mm 1 0 675 mm 1 3 4 3 1 2 4 100 2 8 2 2 5 10 6 7 5 6 10 8 3 6 4 3 1 2 5 4 1 3 2 5 6 8 11 4 7 9 10 Downlo...

Page 3: ...instruc iunile noastre 19 skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z na imi navodili 20 on vastavuses j rgmis t e standardi te ga v i teiste normati...

Page 4: ...the air contains high levels of salt such as air near the ocean and where voltage fluctuates a lot e g in factories Also in vehicles or vessels When selecting the installation site use the supplied pa...

Page 5: ...t at a height over 2 7 m for FCQH100 140 units 3 2 m To avoid accidental touching it is recommended to install the unit higher than 2 5 m Refer to Field setting on page 8 and to the decoration panel i...

Page 6: ...urements of the ceiling opening Consult the builder for details The centre of the ceiling opening is indicated on the paper pattern for installation The centre of the unit is indicated on the unit cas...

Page 7: ...shown in the figure below use the supplied accessory parts Piping insulation procedure Cautions for brazing Be sure to carry out a nitrogen blow when brazing Brazing without carrying out nitrogen rep...

Page 8: ...ed up 75 mm Testing of drain piping After the piping work is finished check if drainage flows smoothly Add approximately 1 l of water gradually through the air discharge outlet Method of adding water...

Page 9: ...nect to the remote controller wiring terminal block Securely fix the wiring using a clamp as indicated in the figure After connection Attach the small sealing supplied with the unit around the cables...

Page 10: ...anual attached to the outdoor units Confirm the system type Pair type or multi system 1 remote controller controls 1 indoor unit standard system Simultaneous operation system 1 remote controller contr...

Page 11: ...ing the master and slave unit separately Procedure See figure 17 1 Change the Second code No to 02 individual setting so that the slave unit can be individually set Second code No is factory set to 01...

Page 12: ...wired remote controller and start operation by pushing ON OFF button 5 Press Inspection Test Operation button 4 times and operate at Test Operation mode for 3 minutes 6 Press Inspection Test Operation...

Page 13: ...lector switch MAIN SUB SS2 Selector switch wireless address set Connector for optional parts X24A Connector wireless remote controller X33A Connector adaptor for wiring X35A Connector group control ad...

Page 14: ...NOTES NOTES Downloaded from AC Manual com Manuals...

Page 15: ...2 3 1 2 3 4 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 4 4 P1 P2 P1 P2 P1 P2 P1 P2 P1 P2 P1 P2 P1 P2 P1 P2 P1 P2 P1 P2 1 2 3 1 2 3 1 2 3 5 6 1 2 3 1 2 1 2 3 1 2 3 1 2 3 5 6 1 2 3 5 6 4 8 4...

Page 16: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PW31577 1B Downloaded from AC Manual com Manuals...

Reviews: