background image

Installation manual

2

EWWP014~065KAW1N

Packaged water-cooled water chillers

4PW30038-1

O

PERATION

 

RANGE

M

AIN

 

COMPONENTS

 

(refer to the outlook diagram supplied with the

unit)

1

Compressor

2

Evaporator

3

Condenser

4

Switchbox

5

Chilled water in

6

Chilled water out

7

Condenser water out

8

Condenser water in

9

Evaporator entering water temperature sensor

10 Freeze up sensor

11 Condenser entering water temperature sensor

12 Digital display controller

13 Power supply intake

14 Ball valve (field installed)

15 Water filter (field installed)

16 Air purge valve (field installed)

17 T-joint for air purge (field installed)

18 flowswitch (with T-joint) (field installed)

19 Main switch

S

ELECTION

 

OF

 

LOCATION

The units are designed for indoor installation and should be installed
in a location that meets the following requirements:

1

The foundation is strong enough to support the weight of the unit
and the floor is flat to prevent vibration and noise generation.

2

The space around the unit is adequate for servicing. 

3

There is no danger of fire due to leakage of inflammable gas.

4

Select the location of the unit in such a way that the sound
generated by the unit does not disturb anyone.

5

Ensure that water cannot cause any damage to the location in
case it drips out of the unit. 

I

NSPECTING

 

AND

 

HANDLING

 

THE

 

UNIT

At delivery, the unit should be checked and any damage should be
reported immediately to the carrier claims agent.

U

NPACKING

 

AND

 

PLACING

 

THE

 

UNIT

1

Cut the straps and remove the cardboard box from the unit.

2

Cut the straps and remove the cardboard boxes with waterpiping
from the pallet.

3

Remove the four screws fixing the unit to the pallet.

4

Level the unit in both directions.

5

Use four anchor bolts with M8 thread to fix the unit in concrete
(directly or using the floor standing supports).

6

Remove the service front plate.

C

HECKING

 

THE

 

WATER

 

CIRCUIT

The units are equipped with water inlets and water outlets for
connection to a chilled water circuit and to a hot water circuit. These
circuits must be provided by a licensed technician and must comply
with all relevant European and national regulations.

Before continuing the installation of the unit, check the following
points:

Additional components not delivered with the unit

1

A circulation pump must be provided in such a way that it dis-
charges the water directly into the heat exchanger.

2

Drain taps must be provided at all low points of the system to
permit complete drainage of the circuit during maintenance or in
case of shut down.

3

Vibration eliminators in all water piping connected to the chiller
are recommended to avoid straining the piping and transmitting
vibration and noise.

Additional water piping delivered with the unit

All additional water piping must be installed on the system according
to the piping diagram as mentioned in the operation manual. The
flowswitch must be connected as described on the wiring diagram.
See also chapter 

"Before starting" on page 4

.

LWC

Leaving water temperature condenser

LWE

Leaving water temperature evaporator

a

Glycol

b

Water

Continuous operation range

0

10

20

-10

-5

5

32

0

10

20

30

40

50

60

LWC

55

45

ZL

ZL

ZH

ZH

ZL

ZH

1.5

1.5

1.5

a    b

a    b

a    b

0

10

20

-10

-5

5

32

0

10

20

30

40

50

60

LWC

55

45

ZL

ZL

ZH

ZH

ZL

ZH

-2

-2

-2

a    b

a    b

a    b

EWWP014~035

EWWP045~065

Carton box 1

water piping evaporator

2x Ball valve

1x Water filter

1x Air purge

1x T-joint for air purge

2x Flowswitch pipe

1x Flowswitch
+
1x T-joint

Carton box 2

water piping condenser

2x Ball valve

1x Water filter

1x Air purge

1x T-joint for air purge

Summary of Contents for EWWP014KAW1N

Page 1: ...INSTALLATION MANUAL EWWP014KAW1N EWWP022KAW1N EWWP028KAW1N EWWP035KAW1N EWWP045KAW1N EWWP055KAW1N EWWP065KAW1N Packaged water cooled water chillers...

Page 2: ...fie utilizate n conformitate cu instruc iunile noastre 19 skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z na imi navodili 20 on vastavuses j rgmis t e st...

Page 3: ...ol application for leaving evaporator water down to 10 C or 5 C BMS Connection MODBUS J BUS BACNET Low noise operation kit field installation Features Voltage free contacts general operation pumpconta...

Page 4: ...t in both directions 5 Use four anchor bolts with M8 thread to fix the unit in concrete directly or using the floor standing supports 6 Remove the service front plate CHECKING THE WATER CIRCUIT The un...

Page 5: ...insulated to prevent condensation and reduction of the cooling capacity Protect the water piping against water freezing during winter period e g by using a glycol solution or heatertape It is very imp...

Page 6: ...evant Euro pean and national regulations The field wiring must be carried out in accordance with the wiring diagram supplied with the unit and the instructions given below Be sure to use a dedicated p...

Page 7: ...circuit The operation of the water chiller is then controlled by the Digital Display Controller Shut down by switching off the controller and the circuit breaker of the power circuit WARNINGS Emergenc...

Page 8: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PW30038 1...

Reviews: