NOTICE

ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.

9.1

Checklist before commissioning

After  the  installation  of  the  unit,  first  check  the  items  listed  below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.

The 

indoor unit

 is properly mounted.

The 

outdoor unit

 is properly mounted.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The 

refrigerant  pipes

  (gas  and  liquid)  are  thermally

insulated.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

The following 

field wiring

 has been carried out according

to  this  document  and  the  applicable  legislation  between
the outdoor unit and the indoor unit.

Drainage

Make sure drainage flows smoothly.

Possible consequence: 

Condensate water might drip.

The indoor unit receives the signals of the 

user interface

.

The  specified  wires  are  used  for  the 

interconnection

cable

.

The 

fuses, circuit breakers,

 or locally installed protection

devices  are  installed  according  to  this  document,  and
have NOT been bypassed.

9.2

Checklist during commissioning

To perform an 

air purge

.

To perform a 

test run

.

9.3

To perform a test run

Prerequisite: 

Power supply MUST be in the specified range.

Prerequisite: 

Test  run  may  be  performed  in  cooling  or  heating

mode.

Prerequisite: 

Test run should be performed in accordance with the

operation  manual  of  the  indoor  unit  to  make  sure  that  all  functions
and parts are working properly.

1

In  cooling  mode,  select  the  lowest  programmable  temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.

2

When  the  test  run  is  finished,  set  the  temperature  to  a  normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.

3

The  system  stops  operating  3  minutes  after  the  unit  is  turned
OFF.

INFORMATION

▪ Even if the unit is turned OFF, it consumes electricity.

▪ When the power turns back on after a power break, the

previously selected mode will be resumed.

10

Troubleshooting

10.1

Fault diagnosis using LED on
outdoor unit PCB

LED is…

Diagnosis

flashing

Normal.

▪ Check the indoor unit.

ON

▪ Turn  the  power  OFF  and  back  ON,  and

check  the  LED  within  approximately  3
minutes.
If  the  LED  is  ON  again,  the  outdoor  unit
PCB is faulty.

OFF

1

Supply voltage (for power saving).

2

Power supply fault.

3

Turn  the  power  OFF  and  back  ON,  and
check  the  LED  within  approximately  3
minutes.
If the LED is OFF again, the outdoor unit
PCB is faulty.

DANGER: RISK OF ELECTROCUTION

▪ When  the  unit  is  not  operating,  the  LEDs  on  the  PCB

are turned off in order to save power.

▪ Even when the LEDs are off, the terminal block and the

PCB may be powered.

11

Disposal

NOTICE

Do  NOT  try  to  dismantle  the  system  yourself:  dismantling
of  the  system,  treatment  of  the  refrigerant,  oil  and  other
parts  MUST  comply  with  applicable  legislation.  Units
MUST  be  treated  at  a  specialised  treatment  facility  for
reuse, recycling and recovery.

12

Technical data

▪ A 

subset

  of  the  latest  technical  data  is  available  on  the  regional

Daikin website (publicly accessible).

▪ The 

full  set

  of  latest  technical  data  is  available  on  the  Daikin

Business Portal (authentication required).

12.1

Wiring diagram

The wiring diagram is delivered with the unit, located inside of
the outdoor unit (bottom side of the top plate).

Summary of Contents for ARXF50A5V1B

Page 1: ...plit series English Installation manual R32 split series ARXF50A5V1B ARXF60A5V1B ARXF71A5V1B RXF50B5V1B RXF60B5V1B RXF71A5V1B RXP50M5V1B RXP60M5V1B RXP71M5V1B ARXM50R5V1B ARXM60R5V1B ARXM71R5V1B RXM42R5V1B RXM50R5V1B RXM60R5V1B ...

Page 2: ...dosításaik rendelkezéseit z późniejszymi poprawkami 18 19 20 21 22 23 24 25 Directivelor cu amendamentele respective Direktive z vsemi spremembami Direktiivid koos muudatustega Директиви с техните изменения Direktyvose su papildymais Direktīvās un to papildinājumos Smernice v platnom znení Değiştirilmiş halleriyle Yönetmelikler 01 02 03 04 as set out in A and judged positively by B according to th...

Page 3: ...lämpötila TS TSmin Alhaisin matalapainepuolen lämpötila L C TSmax Suurinta sallittua painetta PS vastaava kyllästyslämpötila M C Kylmäaine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maximální přípustný tlak PS K bar Minimální maximální přípustná teplota TS TSmin Minimální teplota na nízkotlaké straně L C TSmax Saturovaná teplota odpovídající maximá...

Page 4: ...ised installers WARNING Make sure installation servicing maintenance repair and applied materials follow the instructions from Daikin and in addition comply with applicable legislation and are performed by qualified persons only In Europe and areas where IEC standards apply EN IEC 60335 2 40 is the applicable standard INFORMATION This document only describes installation instructions specific to t...

Page 5: ...he unit if it is vacuumed Charging refrigerant see 6 Charging refrigerant 49 WARNING The refrigerant inside the unit is mildly flammable but normally does NOT leak If the refrigerant leaks in the room and comes in contact with fire from a burner a heater or a cooker this may result in fire or the formation of a harmful gas Turn off any combustible heating devices ventilate the room and contact the...

Page 6: ...SK OF ELECTROCUTION Make sure that the system is earthed properly Turn off the power supply before servicing Install the switch box cover before turning on the power supply Commissioning see 9 Commissioning 412 DANGER RISK OF ELECTROCUTION DANGER RISK OF BURNING SCALDING CAUTION Do NOT perform the test operation while working on the indoor units When performing the test operation NOT only the outd...

Page 7: ...s positioned at least 100 mm above the maximum expected level of snow If necessary construct a pedestal See 4 2 Mounting the outdoor unit 47 for more details In heavy snowfall areas it is very important to select an installation site where the snow will NOT affect the unit If lateral snowfall is possible make sure that the heat exchanger coil is NOT affected by the snow If necessary install a snow...

Page 8: ...terial with a heat transfer rate between 0 041 and 0 052 W mK 0 035 and 0 045 kcal mh C with a heat resistance of at least 120 C Insulation thickness Pipe outer diameter Øp Insulation inner diameter Øi Insulation thickness t 6 4 mm 1 4 8 10 mm 10 mm 9 5 mm 3 8 10 14 mm 13 mm 12 7 mm 1 2 14 16 mm 10 mm 15 9 mm 5 8 16 20 mm 13 mm Øi Øi t Øp Øp If the temperature is higher than 30 C and the humidity ...

Page 9: ... for 4 5 minutes and check the pressure If the pressure Then Does not change There is no moisture in the system This procedure is finished If the pressure Then Increases There is moisture in the system Go to the next step 3 Vacuum the system for at least 2 hours to a manifold pressure of 0 1 MPa 1 bar 4 After turning the pump OFF check the pressure for at least 1 hour 5 If you do NOT reach the tar...

Page 10: ...licable language and stick it on top of a b Factory refrigerant charge see unit name plate c Additional refrigerant amount charged d Total refrigerant charge e Quantity of fluorinated greenhouse gases of the total refrigerant charge expressed as tonnes CO2 equivalent f GWP Global warming potential NOTICE Applicable legislation on fluorinated greenhouse gases requires that the refrigerant charge of...

Page 11: ... ARXF50 71A 20 A a ARXM50 71R RXM50 60R 16 A RXM42R 13 A Earth leakage circuit breaker MUST comply with applicable legislation a Electrical equipment complying with EN IEC 61000 3 12 European International Technical Standard setting the limits for harmonic currents produced by equipment connected to public low voltage systems with input current 16 A and 75 A per phase 7 2 To connect the electrical...

Page 12: ... specified range Prerequisite Test run may be performed in cooling or heating mode Prerequisite Test run should be performed in accordance with the operation manual of the indoor unit to make sure that all functions and parts are working properly 1 In cooling mode select the lowest programmable temperature In heating mode select the highest programmable temperature Test run can be disabled if nece...

Page 13: ...LED V L Pilot lamp light emitting diode HAP Light emitting diode service monitor green HIGH VOLTAGE High voltage IES Intelligent eye sensor IPM Intelligent power module K R KCR KFR KHuR K M Magnetic relay L Live Symbol Meaning L Coil L R Reactor M Stepper motor M C Compressor motor M F Fan motor M P Drain pump motor M S Swing motor MR MRCW MRM MRN Magnetic relay N Neutral n N Number of passes thro...

Page 14: ...CuT 9 5 CuT 6 4 CuT 9 5 CuT 6 4 CuT 6 4 CuT 6 4 CuT 6 4 CuT 4 0 CuT 4 0 CuT 9 5 CuT 12 7 CuT 12 7 CuT RXP50M RXF50B ARXF50A b a c d f h g j1 j3 j2 k m m m m m n o e l i i M a Liquid field piping j3 Discharge pipe thermistor b Gas field piping k Heat exchanger c Liquid stop valve l 4 way valve ON heating d Gas stop valve m Muffler e Liquid receiver n Compressor f Filter o Accumulator g Electronic e...

Page 15: ...2 7 CuT 12 7 CuT 6 4 CuT RXP60M RXP71M RXF60B RXF71A ARXF60A ARXF71A b a c d f h g j1 j3 j2 k m m m m m n M o e l i i i a Liquid field piping j3 Discharge pipe thermistor b Gas field piping k Heat exchanger c Liquid stop valve l 4 way valve ON heating d Gas stop valve m Muffler e Liquid receiver n Compressor f Filter o Accumulator g Electronic expansion valve HPS High pressure switch automatic res...

Page 16: ...0 CuT 4 0 CuT 6 4 CuT 6 4 CuT 6 4 CuT l m j3 M n o e m m d c b a f h g j1 i i i j2 k ARXM71R a Liquid field piping j3 Discharge pipe thermistor b Gas field piping k Heat exchanger c Liquid stop valve l 4 way valve ON heating d Gas stop valve m Muffler e Liquid receiver n Compressor f Filter o Accumulator g Electronic expansion valve HPS High pressure switch automatic reset h Muffler with filter M ...

Page 17: ... CuT 9 5 CuT 9 5 CuT 9 5 CuT 9 5 CuT 6 4 CuT 6 4 CuT 6 4 CuT 6 4 CuT 6 4 CuT 6 4 CuT 12 7 CuT 12 7 CuT 7 0 CuT 7 0 CuT 7 0 CuT 7 0 CuT 7 0 CuT 7 0 CuT j3 b a c d f h g j1 i i i 4 0 CuT 4 0 CuT 4 0 CuT j2 m m m n M o e l k RXM42R a Liquid field piping j3 Discharge pipe thermistor b Gas field piping k Heat exchanger c Liquid stop valve l 4 way valve ON heating d Gas stop valve m Muffler e Liquid rec...

Page 18: ......

Page 19: ......

Page 20: ...STANBUL TÜRKİYE Tel 0216 453 27 00 Faks 0216 671 06 00 Çağrı Merkezi 444 999 0 Web www daikin com tr Gülsuyu Mahallesi Fevzi Çakmak Caddesi Burçak Sokak No 20 34848 Maltepe 3P645642 1A 2021 03 Copyright 2020 Daikin Verantwortung für Energie und Umwelt ...

Reviews: