10 Commissioning

Installation manual

13

35A5V1B
R32 Split series
3P650253-15Q – 2022.12

3

Turn ON the main power supply.

10

Commissioning

NOTICE

General 

commissioning 

checklist.

 

Next 

to 

the

commissioning  instructions  in  this  chapter,  a  general
commissioning  checklist  is  also  available  on  the  Daikin
Business Portal (authentication required).

The  general  commissioning  checklist  is  complementary  to
the  instructions  in  this  chapter  and  can  be  used  as  a
guideline and reporting template during commissioning and
hand-over to the user.

NOTICE

ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.

10.1

Checklist before commissioning

1

After the installation of the unit, check the items listed below.

2

Close the unit.

3

Power up the unit.

The 

indoor unit

 is properly mounted.

The 

outdoor unit

 is properly mounted.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The 

refrigerant  pipes

  (gas  and  liquid)  are  thermally

insulated.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

The following 

field wiring

 has been carried out according

to  this  document  and  the  applicable  legislation  between
the outdoor unit and the indoor unit.

Drainage

Make sure drainage flows smoothly.

Possible consequence: 

Condensate water might drip.

The indoor unit receives the signals of the 

user interface

.

The  specified  wires  are  used  for  the 

interconnection

cable

.

The 

fuses, circuit breakers,

 or locally installed protection

devices  are  installed  according  to  this  document,  and
have NOT been bypassed.

10.2

Checklist during commissioning

To perform an 

air purge

.

To perform a 

test run

.

10.3

To perform a test run

Prerequisite: 

Power supply MUST be in the specified range.

Prerequisite: 

Test  run  may  be  performed  in  cooling  or  heating

mode.

Prerequisite: 

Test run should be performed in accordance with the

operation  manual  of  the  indoor  unit  to  make  sure  that  all  functions
and parts are working properly.

1

In  cooling  mode,  select  the  lowest  programmable  temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.

2

When  the  test  run  is  finished,  set  the  temperature  to  a  normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.

3

The  system  stops  operating  3  minutes  after  the  unit  is  turned
OFF.

INFORMATION

▪ Even if the unit is turned OFF, it consumes electricity.

▪ When the power turns back on after a power break, the

previously selected mode will be resumed.

11

Troubleshooting

11.1

Fault diagnosis using LED on
outdoor unit PCB

LED is…

Diagnosis

flashing

Normal.

▪ Check the indoor unit.

ON

▪ Turn  the  power  OFF  and  back  ON,  and

check  the  LED  within  approximately  3
minutes.
If  the  LED  is  ON  again,  the  outdoor  unit
PCB is faulty.

OFF

1

Supply voltage (for power saving).

2

Power supply fault.

3

Turn  the  power  OFF  and  back  ON,  and
check  the  LED  within  approximately  3
minutes.

If the LED is OFF again, the outdoor unit
PCB is faulty.

DANGER: RISK OF ELECTROCUTION

▪ When the unit is NOT operating, the LEDs on the PCB

are turned OFF in order to save power.

▪ Even  when  the  LEDs  are  OFF,  the  terminal  block  and

the PCB may be powered.

Summary of Contents for ARXD25A5V1B

Page 1: ...Installation manual R32 Split series English Installation manual R32 Split series ARXD25A5V1B ARXD35A5V1B...

Page 2: ...s instrukcij atbilst d m direkt v m vai regul m ja vien ie izstr d jumi tiek lietoti saska ar m su instrukcij m s v zhode s nasleduj cou imi smernicou ami alebo predpisom mi za predpokladu e sa v rob...

Page 3: ...N standby electricity saving function 12 10 Commissioning 13 10 1 Checklist before commissioning 13 10 2 Checklist during commissioning 13 10 3 To perform a test run 13 11 Troubleshooting 13 11 1 Faul...

Page 4: ...use refrigerant gas leakage DANGER RISK OF EXPLOSION Do NOT open the stop valves before the vacuum drying is finished Charging refrigerant see 6 Charging refrigerant 49 WARNING The refrigerant inside...

Page 5: ...efore you can touch electrical components For the location of the terminals see the wiring diagram Finishing indoor unit installation see 8 Finishing the outdoor unit installation 412 DANGER RISK OF E...

Page 6: ...tlet b Air inlet NOTICE The height of the wall on the outlet side of the outdoor unit MUST be 1200 mm It is recommended to install a baffle plate when the air outlet is exposed to wind It is recommend...

Page 7: ...shers field supply 20 mm 311 5 7 4 2 1 1 mm 2 1 1 a a 100 mm above expected level of snow 4 2 2 To install the outdoor unit 4 M8 M10 4 2 3 To provide drainage NOTICE If the unit is installed in a cold...

Page 8: ...ing installation of the refrigeration system joining of parts with at least one part charged shall be performed taking into account the following requirements inside occupied spaces non permanent join...

Page 9: ...ssure Then Does not change There is no moisture in the system This procedure is finished Increases There is moisture in the system Go to the next step 3 Vacuum the system for at least 2 hours to a man...

Page 10: ...tal length m of liquid piping 10 m 0 020 R Additional charge kg rounded in units of 0 01 kg INFORMATION Piping length is the one way length of liquid piping 6 4 To determine the complete recharge amou...

Page 11: ...measure the voltage at the terminals of main circuit capacitors or electrical components before servicing The voltage MUST be less than 50 V DC before you can touch electrical components For the loca...

Page 12: ...ume when the temperature rises again To cut jumper J6 1 Remove the top plate of the outdoor unit 2 Remove the front plate 3 Remove the drip proof cover 4 Cut jumper J6 on the outdoor unit PCB J6 J4 J9...

Page 13: ...consequence Condensate water might drip The indoor unit receives the signals of the user interface The specified wires are used for the interconnection cable The fuses circuit breakers or locally inst...

Page 14: ...n the unit Part numbering is by Arabic numbers in ascending order for each part and is represented in the overview below by in the part code Symbol Meaning Symbol Meaning Circuit breaker Protective ea...

Page 15: ...erminal strip block Y E Electronic expansion valve coil Y R Y S Reversing solenoid valve coil Z C Ferrite core ZF Z F Noise filter 14 Piping diagram 14 1 Piping diagram Outdoor unit M 7 0 CuT 7 0 CuT...

Page 16: ...ANBUL T RK YE Tel 0216 453 27 00 Faks 0216 671 06 00 a r Merkezi 444 999 0 Web www daikin com tr G lsuyu Mahallesi Fevzi akmak Caddesi Bur ak Sokak No 20 34848 Maltepe 3P650253 15Q 2022 12 Copyright 2...

Reviews: