12 Commissioning
Installer reference guide
80
EJHA EHY32AA
Daikin Altherma Hybrid hydrosplit heat pump
4P531180-1 – 2018.06
6
If applicable, set the desired position of the 3-way valve (space
heating/domestic hot water). Use the and buttons to scroll to
Circuit.
7
Use the and buttons to set the desired position of the 3-way
valve.
Result:
SHC or Tank
To perform an automatic air purge
INFORMATION
Frost protection functions
. After first power-on, the unit
runs in "installer-on-site" mode (see
). When "installer-on-site"
mode ends, the unit's frost protection functions are
enabled, and you cannot start the air purge function if
Ta<4°C.
Prerequisite:
Make sure that the leaving water temperature home
page, room temperature home page, and domestic hot water home
page are turned OFF.
1
Set the user permission level to Installer. See
permission level to Installer" on page 56
2
Set the air purge mode: go to [A.7.3.1]
> Installer settings >
Commissioning > Air purge > Type.
3
Select Automatic and press
.
4
Go to [A.7.3.4]
> Installer settings > Commissioning > Air
purge > Start air purge and press
to start the air purge
function.
Result:
Air purging will start and the following screen will be
shown.
01:18
Tue
Air purge
Low
Speed
Stop
Adjust
Circuit
SHC
Scroll
To interrupt air purge
1
Press
and press
to confirm the interruption of the air
purge function.
12.4.2
To perform a test run
Prerequisite:
Make sure that the leaving water temperature home
page, room temperature home page, and domestic hot water home
page are turned OFF.
1
Set the user permission level to Installer. See
permission level to Installer" on page 56
2
Go to [A.7.1]:
> Installer settings > Commissioning > Test
run.
3
Select a test and press
.
Example:
Heating.
4
Select OK and press
.
Result:
The test run starts. It stops automatically when done
(±30 min). To stop it manually, press
, select OK and press
.
INFORMATION
In case of third-party gas boiler:
When starting up the system in a cold climate, it may be
required to start up with a small water volume. To do this,
gradually open the heat emitters. As a result, the water
temperature will gradually rise. Monitor the inlet water
temperature ([6.1.6] in the menu structure) and make sure
it does NOT drop below 15°C.
If the installation of the unit has been done correctly, the unit will
start up during test operation in the selected operation mode. During
the test mode, the correct operation of the unit can be checked by
monitoring leaving water temperature (heating mode) and tank
temperature (domestic hot water mode).
To monitor the temperature, go to [A.6] and select the information
you want to check.
During a heating test run, the unit will start up in hybrid operation.
The setpoint of the gas boiler during a heating test run is 40°C. Keep
in mind the 5°C overshoot that is possible during boiler operation,
especially in combination with floor heating loops.
12.4.3
To perform an actuator test run
Purpose of the actuator test run is to confirm the operation of the
different actuators (e.g., when you select pump operation, a test run
of the pump will start).
Prerequisite:
Make sure that the leaving water temperature home
page, room temperature home page, and domestic hot water home
page are turned OFF.
1
Set the user permission level to Installer. See
permission level to Installer" on page 56
2
Go to [A.7.4]:
> Installer settings > Commissioning >
Actuator test run.
3
Select an actuator and press
.
Example:
Pump.
4
Select OK and press
.
Result:
The actuator test run starts. It automatically stops when
finished. To stop it manually, press
, select OK and press
.
Possible actuator test runs
▪ Pump test
INFORMATION
Make sure that all air is purged before executing the test
run. Also avoid disturbances in the water circuit during the
test run.
▪ 3-way valve test
▪ Bottom plate heater test
▪ Bivalent signal test (in case of third-party gas boiler)
▪ Circulation pump test
▪ Gas boiler test (in case of EHY32AA gas boiler)
INFORMATION
The setpoint during a boiler test run is 40°C. Keep in mind
the 5°C overshoot that is possible during boiler operation,
especially in combination with floor heating loops.
12.4.4
Underfloor heating screed dryout
This function is used for drying out the screed of an underfloor
heating system very slowly during the construction of a house. It
allows the installer to program and execute this program.
Make sure that the leaving water temperature home page, room
temperature home page, and domestic hot water home page are
turned OFF.
INFORMATION
▪ If Emergency is set to Manual ([A.6.C]=0), and the unit
is triggered to start emergency operation, the user
interface will ask confirmation before starting. The
underfloor heating screed dryout function is active even
if the user does NOT confirm emergency operation.
▪ During underfloor heating screed dryout, pump speed