![background image](http://html.mh-extra.com/html/daikin/altherma-eblq05c2v3/altherma-eblq05c2v3_installation-and-maintenance-instructions-manual_501251036.webp)
5
x
Start-up
Installation and maintenance instructions
36
Daikin Altherma M ECH
2
O
Solar storage tank with heating controller
008.1446799_00 – 07/2019 – EN
1.
Check the cold water connection and, where necessary, fill
the potable water heat exchanger.
2.
Switch on the power supply to the Daikin Altherma M ECH
2
O.
3.
Wait for the start phase.
4.
After the start phase has completed, in heating mode,
evacuate the heating system, check the installation pressure
and adjust if necessary (max.
3 bar, see chap.
5.
Carry out a visual inspection for leaks on all joints internally.
Seal any leaks that occur in a professional manner.
6.
Set the rotary switch on the controller to the desired operating
mode.
7.
If a Daikin
solar system is connected, commission it
according to the enclosed instructions. After shutting off the
Daikin
solar system, again check the fill level in the
buffer storage tank.