background image

IM 1240-4 • INTELLIGENT EQUIPMENT 34 www.DaikinApplied.com

Installation

Ethernet LAN Configuration

NOTE: 

Ethernet LAN is one of three possible methods 

of cloud connectivity. The method of connectivity 

is specified at the time of order. You should 

only configure the gateway for Ethernet LAN 

connectivity if certain that Ethernet LAN was 

specified at the time of order. If unsure, contact the 

salesperson or Daikin Applied Controls Technical 

Response Center. Prior to configuring the gateway 

for Ethernet LAN, please refer to Appendix A of this 

document for required IT information.

The M2M Gateway is configured using a set of HTML interface 

pages within the Wind River Intelligent Device Platform. 

The table below indentifies the Wind River configuration 

parameters, along with the corresponding physical port 

on the M2M Gateway. For reference, it also includes the 

corresponding device connection to the M2M Gateway. 

Wind River 

configuration 

parameter

M2M Gateway port

Device Connection

LAN

ETH (which is eth0)

MTIII Unit Controller

wan

USB2 (which is eth1)

Local Network

wlan0

WLAN

WiFi

wwan

3G/GPRS

Cellular 

The following procedures should be used to configure the 

Intelligent Equipment solution for Ethernet LAN connectivity 

(

NOTE:

 it is the “wan” interface in the gateway that will be 

configured).

1.  Remove the USB-to-Ethernet converter from the 

envelope and connect it to an open USB port on the 

M2M Gateway (this is necessary because the M2M 

Gateway has a single Ethernet plug, which is connected 

to the MicroTech III controller, and, therefore, unavailable 

for the purpose of connecting to the local network).

a.  Connect the provided Ethernet patch cable to the 

USB-to-Ethernet adapter and to the local network 

(DHCP is enabled by default).

2.  Using a laptop computer and Ethernet cable, connect 

to the “ETH” port of the M2M Gateway (you will need to 

temporarily disconnect the Ethernet cable between the 

M2M Gateway and the MicroTech III controller, to make 

use of the “ETH” port on the M2M Gateway).

3.  Navigate to your laptop’s Local Area Connection settings 

screen and change the IP subnet mask to 

255 .255 .0 .0

and set the IP address to be compatible with the default 

M2M Gateway IP address of 

https://172 .31 .255 .1

 

(example compatible address: 172.31.255.7). For 

more information on how to change your computer’s IP 

settings, consult the Operating System’s “Help” files. 

4.  Temporarily disable the wireless adapter(s) on the 

computer, as these may prevent accessing the HTML 

Interface page. 

5.  Open a web browser and type, https://172.31.255.1, then 

press enter.

a.  When prompted, enter the User Name: “service”.
b. 

Enter the unique password that was provided with 

the Gateway hardware and press ENTER.

c.  This opens the Wind River Intelligent Device 

Platform configuration page in the gateway (

Figure 

75 on page 35

).

NOTE: 

If you will use DHCP for your local network 

configuration, please proceed to step 8. 

6.  Click the ‘Network’ tab
7. 

Locate the ‘wan Configuration’ section (

Figure 76 on 

page 36

)

a. 

Under wan Configuration select ‘Static IP’ for 

Connection Type

b.  Ensure that Interface = eth1

c.  Enter the IP, Subnet, and Gateway address 

information

d.  Under wan DNS Servers enter your network’s 

primary DNS server and click ‘Add’ (NOTE: If you 

prefer to use a public DNS server, use 8.8.8.8 or 

4.2.2.2)

e.  If a secondary DNS server address is to be 

entered, enter it after the page has reloaded and 

click ‘Add’ and enter the secondary address.

8.  Click the ‘Save Changes’ button in the lower right corner 

of the page. Then, click 

‘Apply Changes’

.

a. 

IMPORTANT:

 Allow the page to refresh

b. 

Confirm that there is number in parentheses next 

to “Review Changes”. If so, proceed to step 7; if 

not, repeat steps 5 and 6.

9.  Click the ‘Apply Changes’ button in the lower right-hand 

corner of the screen. The page will automatically refresh 

when complete (this can take as much as two minutes).

10.  Click the ‘Multiwan’ tab

a.  Scroll to the bottom of the page and Click ‘Add 

New Interface’ (

Figure 77 on page 36

)

b.  Name the interface, “wan” (must match the name 

of the interface configured in step 5.

c.  Click ‘Add new interface’

Summary of Contents for AGZ-D

Page 1: ...des IM 1219 Intelligent Equipment for Daikin Pathfinder and Trailblazer Air cooled Chillers Magnitude Magnetic Bearing Chillers Rebel and Maverick II Commercial Packaged Rooftops RoofPak Applied Packa...

Page 2: ...MTIII 12 M2M Connection to WMC 12 M2M Connection to EMM 12 Connection of Power Supply 13 Connection of EMM to Split Core CT s 14 Connection of EMM to Rogowski Coil CT s 14 Connection of Rogowski Coil...

Page 3: ...ponents consist of one Machine to Machine M2M Gateway one Energy Management Module EMM Antenna and three Current Transformers CT s Hazardous Information Messages Recognize Safety Symbols Words and Lab...

Page 4: ...on of appropriately sized CT s See Table 1 for CT sizing and specifications In the case of a unit ordered with Intelligent Equipment the CT s will be factory installed within the unit control panel Fo...

Page 5: ...grommet 2 grounding harnesses 1 3 wire voltage harness wire ties wire tie hangers 12 self tapping sheet metal screws 1 section of 600V rated heat shrink tubing Upon receiving verify that all component...

Page 6: ...controlled CAUTION Static sensitive components Can cause equipment damage Discharge any static electrical charge by touching the bare metal inside the control panel before performing any service work...

Page 7: ...On AWS models locate IE Hardware as space allows within control enclosure Figure 6 and Figure 7 provide the typical layout of AWS small and large enclosures On WMC chillers only the M2M gateway and ga...

Page 8: ...PMENT 8 www DaikinApplied com Installation Figure 3 Component Locations AGZ D Large Panel Figure 4 Component Locations AGZ E Large Panel Figure 5 Component Locations AWV Large Panel Figure 6 Component...

Page 9: ...just created using a 7 64 drill bit Finally attach the EMM to the backplane using 4 of the provided 6 sheet metal screws 5 16 head Installing Power Supply Prior to installing any Intelligent Equipmen...

Page 10: ...arks just created using a 1 8 drill bit Finally attach the fuse block to the backplane using 2 of the provided 8 sheet metal screws 5 16 head Fuses can be reinstalled but the covers should remain off...

Page 11: ...NT Figure 13 AGZ Large Enclosure Knockout Location Rear of Enclosure Figure 14 AWV Large Enclosure Knockout Location Rear of Enclosure Figure 15 AWS Small Enclosure Knockout Location Rear of Enclosure...

Page 12: ...e a minimum of 5 inches of clearance between all cables and conductors with 300V rated insulation or less and areas of the control enclosure containing higher voltage components and conductors NOTICE...

Page 13: ...icroTech III AGZ D or AGZ E unit connect the Line brown conductor to terminal TB1 11B and the Neutral blue conductor to terminal TB1 32B Figure 21 On a MicroTech III AWV or AWS unit connect the Line b...

Page 14: ...ered terminal Figure 25 Figure 24 Hinged Cover Screw Locations Figure 25 Connection of EMM to CT s Connection of EMM to Rogowski Coil CT s Not on Gateway on the Go IE Express or WMC kits Chillers with...

Page 15: ...should be connected to terminal TB2 42 or TB2 43 and terminal GND Vin on the power supply should be connected to terminal TB2 81 TB2 83 or TB2 84 Figure 29 On an AWV chiller terminal Vin on the power...

Page 16: ...ted to EMM terminal CT_B on phase L2 and the Rogowski Coil CT connected to EMM terminal CT_C on phase L3 Figure 32 Ensure that the Load indicator on the CT is oriented correctly The molded arrow on th...

Page 17: ...connect the VinA Tan VinB Orange and VinC Violet terminals on the EMM to the Load terminals on the Fuse Block Figure 33 If needed remove the plastic protective shield from Power Distribution Block 1 P...

Page 18: ...minal on the EMM itself Figure 35 Connect the free ring terminals for both the M2M and EMM to the nearest available grounding lug in the control enclosure Figure 36 Once all connections are made to th...

Page 19: ...d CAUTION Static sensitive components Can cause equipment damage Discharge any static electrical charge by touching the bare metal inside the control panel before performing any service work Never unp...

Page 20: ...Figure 39 Figure 39 3G and WLAN Connections LAN Installation If Applicable LAN Connection If using the local area network LAN for cloud connectivity a USB to Ethernet Adapter must be used for connecti...

Page 21: ...2M bracket is designed for installation on the inside of the lower left internal enclosure door Figure 42 and the EMM bracket is designed for installation on the inside of the lower right internal enc...

Page 22: ...eable in the operation of the equipment being controlled WARNING Care must be taken to ensure a minimum of 5 inches of clearance between all cables and conductors with 300V rated insulation or less an...

Page 23: ...and areas of the control enclosure containing higher voltage components and conductors In RoofPak installations all non 600V rated wires Ethernet Coax USB must be wrapped in the 600V rated insulation...

Page 24: ...smaller diameter hole should be present on the inside of the enclosure Again using the step drill bit drill this hole on the inside of the enclosure to a 5 8 diameter Drill no deeper than necessary t...

Page 25: ...ause equipment damage Discharge any static electrical charge by touching the bare metal inside the control panel before performing any service work Never unplug cables circuit board terminal blocks or...

Page 26: ...58 On a MicroTech III Maverick II unit connect the Line brown conductor to terminal TB1A 1 2 3 or 4 and the Neutral blue conductor to terminal TB1A 5 6 7 8 or 9 Figure 59 On a MicroTech III RPS RPR RD...

Page 27: ...e must go to terminal labeled CT and the black wire must go to the associated lettered terminal Figure 62 Figure 61 Hinged Cover Screw Locations Figure 62 Connection of EMM to CT s Installing CT s Not...

Page 28: ...gure 66 Once all connections are made to the line voltage side of the EMM close the hinged cover and reinstall the screws Figure 67 depicts an EMM with all high voltage terminations made and the hinge...

Page 29: ...nel knowledgeable in the operation of the equipment being controlled CAUTION Static sensitive components Can cause equipment damage Discharge any static electrical charge by touching the bare metal in...

Page 30: ...Figure 69 Figure 69 3G and WLAN Connections LAN Installation If Applicable LAN Connection If using the local area network LAN for cloud connectivity a USB to Ethernet Adapter must be used for connect...

Page 31: ...ateway defect Simply click the advanced menu link within the browser then accept the security exception a When prompted enter the User Name service b Enter the unique password that was provided with t...

Page 32: ...the M2M Gateway 14 Reconnect the Ethernet cable between the M2M Gateway and the MicroTech III controller NOTE Be certain that the IT staff has allowed incoming and outgoing Internet traffic on TCP po...

Page 33: ...Installation www DaikinApplied com 33 IM 1240 4 INTELLIGENT EQUIPMENT Figure 73 Wireless Configuration Screen Figure 74 Wireless Signal Strength...

Page 34: ...croTech III controller to make use of the ETH port on the M2M Gateway 3 Navigate to your laptop s Local Area Connection settings screen and change the IP subnet mask to 255 255 0 0 and set the IP addr...

Page 35: ...r in parentheses next to Review Changes If so proceed to step 15 if not repeat steps 8 14 18 Click the Apply Changes button in the lower right hand corner of the screen The page will automatically ref...

Page 36: ...IM 1240 4 INTELLIGENT EQUIPMENT 36 www DaikinApplied com Installation Figure 76 WAN Configuration Settings Figure 77 Add New Interface Selection...

Page 37: ...ag which opens the unit details screen Figure 82 Click the Commissioning Procedure button You will then receive a message indicating that you have 30 days to complete the commissioning procedure Figur...

Page 38: ...IM 1240 4 INTELLIGENT EQUIPMENT 38 www DaikinApplied com Installation Figure 83 Thirty Day Message Figure 84 Commissioning Procedures Screen...

Page 39: ...E Your browser will likely notify you of a security risk related to an unsigned security certificate This is expected and does not indicate a gateway defect Simply click the advanced menu link within...

Page 40: ...IM 1240 4 INTELLIGENT EQUIPMENT 40 www DaikinApplied com Troubleshooting Figure 85 M2M Gateway Home Page Figure 86 Verify Cellular Signal Strength...

Page 41: ...Under Time Zone verify that the indicated Time Zone is accurate If so continue to step 5 6 If the Time Zone is inaccurate use the list to select the correct Time Zone then click Save Changes a After...

Page 42: ...IM 1240 4 INTELLIGENT EQUIPMENT 42 www DaikinApplied com Troubleshooting Figure 87 System Tab Figure 88 Time Updated to Time Zone Figure 89 Keypad Controls Figure 90 Date Time Schedules Menu...

Page 43: ...cation Wi Fi connection cannot be established Check antenna connection to magnetic base Check antenna connection to WLAN connection on Gateway Check signal strength through WebIF Verify Wi Fi IP addre...

Page 44: ...following information as necessary prior to a technician going to the jobsite and commissioning the gateway A CAT 5E Ethernet communication cable with an extra feet of coiled cable and a RJ45 connect...

Page 45: ......

Page 46: ...nt to its standard terms and conditions of sale including Limited Product Warranty Consult your local Daikin Applied Representative for warranty details To find your local Daikin Applied Representativ...

Reviews: