7 Electrical installation

Installation manual

13

50A
R32 Split series
3P600450-5L – 2021.12

WARNING

▪ Do  NOT  use  locally  purchased  electrical  parts  inside

the product.

▪ Do  NOT  branch  the  power  supply  for  the  drain  pump,

etc.  from  the  terminal  block.  This  could  result  in
electrical shock or fire.

WARNING

Keep  the  interconnection  wiring  away  from  copper  pipes
without thermal insulation as such pipes will be very hot.

DANGER: RISK OF ELECTROCUTION

All  electrical  parts  (including  thermistors)  are  powered  by
the power supply. Do NOT touch them with bare hands.

DANGER: RISK OF ELECTROCUTION

Disconnect  the  power  supply  for  more  than  10  minutes,
and  measure  the  voltage  at  the  terminals  of  main  circuit
capacitors  or  electrical  components  before  servicing.  The
voltage MUST be less than 50 V DC before you can touch
electrical  components.  For  the  location  of  the  terminals,
see the wiring diagram.

AC

DC

DC

-

+

e

f

g

h

i

j

a

b

k

c

d

l

a

DB1 diode bridge

b

S90 thermistor lead wire

c

LED A

d

S40 thermal overload relay lead wire

e

S20 (white) room A electronic expansion valve coil

f

S21 (red) room B electronic expansion valve coil

g

S80 (white) 4-way valve lead wire connector

h

S70 fan motor lead wire

i

S99 heating lock

j

S91 (red) liquid thermistor lead wire

k

S92 (white)gas thermistor lead wire

l

Multimeter (DC voltage range)

7.1

Specifications of standard wiring
components

Component

Power supply
cable

Voltage

220~240 V

Phase

1~

Frequency

50 Hz

Wire type

3-core cable 2.5 mm

2

H05RN-F (60245 IEC 57)

H07RN-F (60245 IEC 66)

3-core cable 4.0 mm

2

H07RN-F (60245 IEC 66)

Interconnection cable
(indoor↔outdoor)

4-core cable 1.5 mm

2

 or

2.5 mm

2

 and applicable for

220~240 V

H05RN-F (60245 IEC 57)

Recommended circuit breaker

16 A

Component

Residual current device

MUST comply with

applicable legislation

7.2

To connect the electrical wiring to
the outdoor unit

1

Remove the switch box cover (2 screws).

2

Connect the wires between the indoor and outdoor units so that
the  terminal  numbers  match.  Make  sure  to  match  the  symbols
for piping and wiring.

3

Make sure to connect correct wiring to correct room (A to A, B
to B).

e

-A

a

-A

a

-B

e

-B

b

c

d

1

2

3

L

N

1

2

3

f

a

Terminal for room (A, B)

b

Circuit breaker

c

Residual current device

d

Power supply wire

e

Interconnection wire for room (A, B)

f

Wire retainer

4

Tighten  the  terminal  screws  securely  using  a  Phillips
screwdriver.

5

Check that the wires do not disconnect by pulling them lightly.

6

Firmly secure the wire retainer to avoid external stress on wire
terminations.

7

Pass  the  wiring  through  the  cutout  on  the  bottom  of  the
protection plate.

8

Make  sure  the  electrical  wiring  does  not  contact  with  the  gas
piping.

1

2

3

1 2 3 1 2 3

1

2

3

L

N

A

B

Summary of Contents for 2MXM40A2V1B

Page 1: ...Installation manual R32 Split series English Installation manual R32 Split series 2MXM40A2V1B 2MXM50A2V1B ...

Page 2: ...uina v platném znění Smjernice kako je izmijenjeno irányelv ek és módosításaik rendelkezéseit z późniejszymi poprawkami 18 19 20 21 22 23 24 25 Directivelor cu amendamentele respective Direktive z vsemi spremembami Direktiivid koos muudatustega Директиви с техните изменения Direktyvose su papildymais Direktīvās un to papildinājumos Smernice v platnom znení Değiştirilmiş halleriyle Yönetmelikler 01...

Page 3: ...n sallittu lämpötila TS TSmin Alhaisin matalapainepuolen lämpötila L C TSmax Suurinta sallittua painetta PS vastaava kyllästyslämpötila M C Kylmäaine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maximální přípustný tlak PS K bar Minimální maximální přípustná teplota TS TSmin Minimální teplota na nízkotlaké straně L C TSmax Saturovaná teplota odpovída...

Page 4: ...iunile noastre skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z našimi navodili on vastavuses järgmis t e standardi te ga või teiste normatiivsete dokumentidega kui neid kasutatakse vastavalt meie juhenditele съответстват на следните стандарти или други нормативни документи при условие че се използват съгласно нашите инструкции atitinka žemiau nurodytus...

Page 5: ...commissioning 15 10 2 Checklist during commissioning 16 10 3 Trial operation and testing 16 10 3 1 To perform a test run 16 11 Maintenance and service 16 12 Disposal 16 13 Technical data 16 13 1 Wiring diagram 16 13 1 1 Unified wiring diagram legend 16 13 2 Piping diagram Outdoor unit 17 1 About the documentation 1 1 About this document INFORMATION Make sure that the user has the printed documenta...

Page 6: ...un air will be sucked in This will cause abnormal pressure in the refrigeration cycle which may result in equipment damage and even injury CAUTION Do NOT open the valves before flaring is complete This would cause refrigerant gas leakage DANGER RISK OF EXPLOSION Do NOT start the unit if it is vacuumed Charging refrigerant see 6 Charging refrigerant 411 WARNING The refrigerant inside the unit is mi...

Page 7: ...tes after the power supply is turned off because of high voltage risk Please note that some sections of the electric component box are hot Make sure you do NOT touch a conductive section Do NOT rinse the unit This may cause electric shocks or fire DANGER RISK OF ELECTROCUTION Use this compressor on a grounded system only Turn the power off before servicing the compressor Reattach the switch box co...

Page 8: ...nal installation site requirements of the outdoor unit in cold climates Protect the outdoor unit against direct snowfall and take care that the outdoor unit is NEVER snowed up a b c c d a Snow cover or shed b Pedestal c Prevailing wind direction d Air outlet It is recommended to provide at least 150 mm of free space below the unit 300 mm for heavy snowfall areas Additionally make sure the unit is ...

Page 9: ...ble for refrigerant Use phosphoric acid deoxidised seamless copper for refrigerant Foreign materials inside pipes including oils for fabrication must be 30 mg 10 m Refrigerant piping diameter Class 40 Liquid piping 2 Ø6 4 mm 1 4 Gas piping 2 Ø9 5 mm 3 8 Class 50 Liquid piping 2 Ø6 4 mm 1 4 Gas piping 1 Ø9 5 mm 3 8 1 Ø12 7 mm 1 2 INFORMATION Usage of reducers might be required based on the indoor u...

Page 10: ...side occupied spaces non permanent joints are NOT allowed for R32 refrigerant except for site made joints directly connecting the indoor unit to piping Site made joints directly connecting piping to indoor units shall be of non permanent type CAUTION Do NOT connect the embedded branch piping and the outdoor unit when only carrying out piping work without connecting the indoor unit in order to add ...

Page 11: ...gas 5 3 2 To perform vacuum drying DANGER RISK OF EXPLOSION Do NOT start the unit if it is vacuumed NOTICE Connect the vacuum pump to both the service ports of the gas stop valves 1 Vacuum the system until the pressure on the manifold indicates 0 1 MPa 1 bar 2 Leave as is for 4 5 minutes and check the pressure If the pressure Then Does not change There is no moisture in the system This procedure i...

Page 12: ...refrigerant piping is connected and checked leak test and vacuum drying 1 Connect the refrigerant cylinder to the service port 2 Charge the additional refrigerant amount 3 Open the gas stop valve 6 5 To fix the fluorinated greenhouse gases label 1 Fill in the label as follows b Contains fluorinated greenhouse gases 2 1 1 1 2 2 kg tCO2 eq GWP kg 1000 kg kg GWP XXX RXXX a f c d e a If a multilingual...

Page 13: ...or lead wire k S92 white gas thermistor lead wire l Multimeter DC voltage range 7 1 Specifications of standard wiring components Component Power supply cable Voltage 220 240 V Phase 1 Frequency 50 Hz Wire type 3 core cable 2 5 mm2 H05RN F 60245 IEC 57 H07RN F 60245 IEC 66 3 core cable 4 0 mm2 H07RN F 60245 IEC 66 Interconnection cable indoor outdoor 4 core cable 1 5 mm2 or 2 5 mm2 and applicable f...

Page 14: ...setting Prerequisite The main power supply MUST be turned off 1 Remove the top plate of the outdoor unit 2 screws on sides 2 Remove the electric box cover by sliding it Be careful not to bend the electric box hook 3 Cut the jumper J23 J26 J24 J23 J6 J22 J8 a b e c d a Top plate b Electric box cover c PCB jumpers d PCB e Electric box 4 Reinstall the electric box cover and the top plate in reverse o...

Page 15: ...klist Next to the commissioning instructions in this chapter a general commissioning checklist is also available on the Daikin Business Portal authentication required The general commissioning checklist is complementary to the instructions in this chapter and can be used as a guideline and reporting template during the commissioning and hand over to the user NOTICE ALWAYS operate the unit with the...

Page 16: ...nutes During cooling operation frost may form on the gas stop valve or other parts This is normal INFORMATION Even if the unit is turned OFF it consumes electricity When the power turns back on after a power break the previously selected mode will be resumed 11 Maintenance and service NOTICE General maintenance inspection checklist Next to the maintenance instructions in this chapter a general mai...

Page 17: ...tor M C Compressor motor M F Fan motor M P Drain pump motor Symbol Meaning M S Swing motor MR MRCW MRM MRN Magnetic relay N Neutral n N Number of passes through ferrite core PAM Pulse amplitude modulation PCB Printed circuit board PM Power module PS Switching power supply PTC PTC thermistor Q Insulated gate bipolar transistor IGBT Q C Circuit breaker Q DI KLM Earth leak circuit breaker Q L Overloa...

Page 18: ... j A B A B k l l m n o o p q r s t n m i h g c c 2MXM50 A Room A k Field piping liquid B Room B l Liquid stop valve a 4 way valve ON heating m Thermistor liquid b High pressure switch with automatic reset n Filter c Muffler o Motor operated valve d Discharge pipe thermistor p Muffler e Compressor q Outdoor air temperature thermistor f Accumulator r Heat exchanger g Branch pipe M Fan motor h Thermi...

Page 19: ......

Page 20: ...3P600450 5L 2021 12 Copyright 2021 Daikin Verantwortung für Energie und Umwelt ...

Reviews: