Start up

Preliminary checks / leakage test
Setting air pressure switch
Selecting fuel

Burner start up simultaneously involves
starting up installation by the fitter or his
representative; only they can guarantee
boiler house compliance with currently
accepted practices and regulations in
force.
The fitter must first be in possession of
a “ certificate of gas fuel conformity ”
issued either by the approved body or
distributor and also have leak-tested
and drained pipework upstream from
the quarter-turn hand-operated valve.
Also, the fuel oil suction pipe must be
filled completely, drained and
pressurized, if booster is available.

Preliminary checks

Check the following:

nominal available voltage and
electrical frequency and compare
them with values found on
identification plate,

polarity between phase and neutral

previously tested earth wire
connection,

lack of potential between neutral
and earth,

motor rotation directions,

thermal relay only in

manual (H)

position and intensity setting.

Cut off electrical supply.

Make sure there is no current.

Close liquid and gas fuel valves.

Read boiler and regulator
manufacturer service instructions.

Check the following:

boiler is full of pressurized water,

circulator(s) work(s),

mixing valve(s) open,

combustion air supply to the boiler
house and combustion product
exhaust pipe are working correctly
and compatible with burner
capacity and fuels,

draught operator working correctly
on exhaust pipe,

protective fuses outside burner are
present, calibrated and set,

boiler regulator circuit is set.

For

fuel oil

tank fuel oil level,

suction pipe full,

suction and return hose position,

boost pressure not exceeding 2bars,

control and prefilter valves positions.

For

gas

gas type and distribution pressure
are suited to the burner.

Leakage test
Fuel oil

This is performed during start up
while burner is working.

Gas

Connect manometer upstream from
the gas manifold.

Open and close the quarter-turn
hand-operated valve.

Check supply pressure and its
long-term stability.

Use a purpose designed foam to
check air-tightness of gas manifold
connections, including external filter.

No leak should be found.

Drain pipework downstream from the
quarter-turn hand-operated valve
whilst taking care to protect the gas
valve intake.

Reclose drain valve, remove
manometer, close pressure take-off.

Selecting fuel

On delivery, fuel is selected manually
via the

S4

switch on

TC

.

Optionally, fuel can be remote
controlled.

Choice of fuel

When both fuels are available:

Set in the following order:

1. Domestic liquid fuel according to the
nominal power and the output of the
boiler.
2. Gas fuel - natural or propane

gas.

Without modifying the setting of the
nominal gas flow’s cam precised in fuel,
control and adjust  the combustion
quality in acting on the valve.
This procedure enables to fully use
boiler and burner.

Setting air pressure switch

Check the connection of the flexible
piping. The

+

on the pressure

connector to the

+

on the pressure

switch. The other pipe should be
already connected.

Remove transparent cover. Unit
includes a

x

index and graduated

mobile disk.

Provisionally set pressure controller
to the minimum value shown on
graduated disk.

Summary of Contents for C 100 B 517

Page 1: ...0306 13 013 497A C 75 C 100 B 517 8 EN ES Instrucciones de montaje servicio Quemadores bicombustible 2 24 Operating instructions Dual fuel burners 26 48...

Page 2: ...a mayor prudencia en particular evitando todo contacto directo con las zonas no aisladas y circuitos el ctricos Evitar contactos de agua en las partes el ctricas del quemador En caso de inundaci n inc...

Page 3: ...ntactor motor del ventilador K5 K6 K7 Temporizadores M1 Motor de ventilaci n SA1 En le cajet n visualizaci n del programa de los fallos piloto rojo encendido y pulsador de rearme TC Cuadro de control...

Page 4: ...les del poder calor fico de los gases naturales Funcionan con Sistemas AGP en dos etapas progresivas o modulante con ayuda de un regulador de potencia PI o PID opci n Se adaptan a dos generadores en c...

Page 5: ...bobinas de las v lvulas est n obligatoriamente en posici n vertical alta Importante Cuando se utiliza una rampa de gas VGD montada a la izquierda es necesario girar 180 el regulador SKP70 Para ello De...

Page 6: ...lizarse en conformidad con las normas en vigor La toma el ctrica debe conectarse y verificarse Consultar el esquema el ctrico para la conexi n del quemador y de la regulaci n De f brica el quemador de...

Page 7: ...o de la carga H y de los acontecimientos ocurridos Estas longitudes tienen en cuenta la presencia de una v lvula manual de un cuarto de vuelta una v lvula antiretorno y cuatro codos La depresi n m xim...

Page 8: ...la potencia nominal del quemador y de los combustibles la presencia y funcionamiento del regulador de tiro en el conducto de evacuaci n de humos la presencia calibrado y ajuste de las protecciones el...

Page 9: ...l tornillo y de la tuerca C posteriormente la hermeticidad Montar la alargadera del tornillo de ajuste de los difusores Pasar los cables de encendido e ionizaci n a trav s de la tapa Colocar el pasaca...

Page 10: ...res marcados B seg n la orientaci n del obturador E Ajuste de f brica 5 ranuras abiertas hacia el exterior 1 ranura hacia el interior en 3 difusores marcado A seg n la orientaci n del obturador E Fija...

Page 11: ...5 5 5 3 75 4 5 5 0 6 0 6 0 7 5 8 5 10 14 15 17 16 5 18 18 18 13 13 14 18 5 15 18 15 5 17 5 15 C 100 500 550 600 650 700 800 900 1000 43 50 46 30 50 50 55 00 59 00 67 40 75 80 84 80 4 5 5 0 5 0 5 0 5...

Page 12: ...a de la caldera y de los valores indicados en la tabla adjunta m Para ello Accionar las levas a mano o con la llave La posici n angular se lee en las cifras rojas respecto al ndice10 situado en cada l...

Page 13: ...lida 16 Toma de presi n pa depu s de V1 a ambos lados 17 Indicador de marcha V1 V2 opcional 18 Tubos de toma de presi n pBr pL pF Puesta en funcionamiento Descripci n Ajustes V lvula gas V lvula MB VE...

Page 14: ...Br 15 Brida de salida 16 Tubos de toma de presi n pBr pL pF La v lvula VGD asociada a un regulador SKP70 permite obtener una relaci n constante caudal de gas respecto a caudal de aire El regulador tie...

Page 15: ...15 0306 13 013 497A ES Note...

Page 16: ...ridad o 1 er tiempo de seguridad para quemador con piloto t3 Tiempo de preencendido corto transformador terminal 16 t3 Tiempo de preencendido largo transformador terminal 15 t4 Intervalo entre tensi n...

Page 17: ...tato de aire est en reposo la tensi n el ctrica en el terminal 12 se aplica al terminal 4 Los termostatos limitador y de seguridad y el presostato de gas m nimo est n cerrados la tensi n el ctrica en...

Page 18: ...de los interruptores del TC A2 Ubicaciones normalizadas 48x48 48x96 mm para instalar un regulador de potencia opcional B10 Puente de medici n A DC corriente de c lula colocada al lado del contactor mo...

Page 19: ...ficio de una toma de presi n El quemador funciona al caudal min Observar la calidad de encendio Comprobar ver tabla la presi n de pulverizaci n la posici n de la leva VII Accionar el interruptor S7 2...

Page 20: ...a caldera la apertura del circuito de regulaci n limitador y seguridad la intensidad del rel t rmico del motor de ventilaci n C75 3 1A 400V C100 3 5 A 400V C lula Verificar la c lula en simulaci n y d...

Page 21: ...humos recomendado por el constructor de la caldera para obtener el rendimiento til exigido Seg n las pruebas de combusti n accionar con el quemador en funcionamiento el caudal nominal mediante el torn...

Page 22: ...r y retirar el cuerpo del quemador prestando atenci n a los hilos el ctricos Desmontar la rampa de gas y despu s el separador Aflojar desde los tres tornillos del ca n Cambiar el ca n Volver a montarl...

Page 23: ...rrado Cableado entre contactor y motor defectuoso Motor defectuoso Controlar el cableado Cambiar el motor z 1 El motor gira en posici n en posici n 1 Presostato de aire desajustado o defectuoso Fallo...

Page 24: ...de las v lvulas de control y del prefiltro Controlar el vac o de los tubos la presi n de pulverizaci n y la bomba de cebado Limpiar el filtro de la bomba y del prefiltro Cambiar los difusores la bomb...

Page 25: ...25 0306 13 013 497A Note ES...

Page 26: ...supply to the burner must include an isolating transformer and appropriate protection 30mA circuit breaker and fuse Burner must be able to be isolated from the system via a multipole switch complying...

Page 27: ...otection device K1 Fan motor protection device K5 K6 K7 Time delay units M1 Fan motor SA1 The control unit displays program cycle faults red light illuminated and reset pushbutton TC Control panel T1...

Page 28: ...nto account They operate with AGP system at two progressive rates or modulating with PI or PID power regulator option They fit generators in accordance with EN 303 1 Standard requirements Three fixed...

Page 29: ...ifold C flange When fitting gas manifold valve coils must be in the vertical top position Important When using a left mounted VGD gas train it is necessary to pivot the SKP70 regulator 180 To do this...

Page 30: ...em to gas manifold must be performed by a qualified technician Pipe section must be calculated so that load loss does not exceed 5 of distribution pressure External filter must be horizontally mounted...

Page 31: ...ording to length L and suction or load height H and chance mishaps These lengths include the presence of a quarter turn hand operated valve a check valve and four elbows Maximum negative pressure of 0...

Page 32: ...er are present calibrated and set boiler regulator circuit is set For fuel oil tank fuel oil level suction pipe full suction and return hose position boost pressure not exceeding 2bars control and pre...

Page 33: ...the gas supply line Re assemble Check that the screw and the nut C are securely tightened subsequently for leaks Assemble the extension part of the diffusor setting screw Pass the ignition cables thr...

Page 34: ...nd 0 slots inside on 5 diffusers indicated B according to the shutter position E Factory setting 5 slots open to the outside 1 slot inside on 3 diffusers A according to shutter E position Fix the baff...

Page 35: ...5 4 5 4 5 4 5 5 5 3 75 4 5 5 0 6 0 6 0 7 5 8 5 10 14 15 17 16 5 18 18 18 13 13 14 18 5 15 18 15 5 17 5 15 C 100 500 550 600 650 700 800 900 1000 43 50 46 30 50 50 55 00 59 00 67 40 75 80 84 80 4 5 5...

Page 36: ...l gas oil kW kW III IV I C 75 200 350 450 500 650 750 20 4 6 10 11 17 28 30 35 52 57 C 100 240 500 600 700 850 1000 10 7 8 10 9 10 34 40 50 60 90 Start up Description Settings Combustion air Cam Facto...

Page 37: ...pressure pBr 15 Outlet flange 16 Pressure pa take off after V1 both sides 17 On indicator V1 V2 optional 18 pBr pL pF pressure take off pipes Setting gas pressure switch Remove transparent cover Unit...

Page 38: ...tion G 1 8 for gas pressure pBr 15 Outlet flange 16 pBr pL pF pressure take off pipes The VGD valve associated with SKP70 regulator ensures a constant gas flow air flow ratio and is quick acting The r...

Page 39: ...39 0306 13 013 497A EN Notes...

Page 40: ...7 T10 Interval between start and air pressure monitoring without flap movement time T11 OPEN position air flap movement time T1 2MINI position air flap movement time T13 Accepted postcombustion time T...

Page 41: ...s applied to terminal 8 air pressure switch is off voltage at terminal 12 is applied to terminal 4 limit and safety thermostats and min gas pressure switch are off voltage at terminal 4 is applied to...

Page 42: ...s for installation of a power regulator option B10 Measuring bridge A DC of cell current located next to the motor protection device F10 Fuse of the control panel TC Green indicators H1 OIL fuel H4 GA...

Page 43: ...ge dimension Y you may be required to change air flows and spray pressure If so check combustion values Important No longer change dimension Y Check operation during ignition and when increasing or re...

Page 44: ...nd inform the agent of these results Switch on burner in automatic mode Convey information required for operation to those concerned Place the boiler house plate in full view Start up Setting of the f...

Page 45: ...ommended boiler manufacturer smoke temperature value in order to obtain the required effective output According to combustion value with burner working at nominal rate turn screw V on valve MB VEF or...

Page 46: ...en pump unit Check the following atomization pressure absence of leaks in systems coupling between pump and motor state of hose Checking gas filter The external or valve filter integrated or pocket mu...

Page 47: ...r Motor not working Contactor closed Faulty wiring between contactor and motor Faulty motor Check wiring Replace motor z 1 Motor working in position in 1 position No ignition arc Misadjusted or faulty...

Page 48: ...itch Check pressure pipes Check if cell is clean Change control and safety unit 1 No ignition arc Ignition electrodes short circuiting Damaged ignition cables Faulty ignition transformer Control and s...

Page 49: ...49 0306 13 013 497A EN Notes...

Page 50: ...50 0306 13 013 497A...

Page 51: ...51 0306 13 013 497A...

Page 52: ...52 0306 13 013 497A Fabriqu en EU Made in EU Hergestellt in EU Document non contractuel Non contractual document Angaben ohne Gew hr CUENOD 18 rue des Buchillons Ville la Grand F 74100 Annemasse...

Reviews: