Installation manual CHARGESTORM® Connected
page
6
Figure 7 Cable schematics
Cables inside CHARGESTORM® Connected for the supply wires from top
to terminal blocks shall follow the black line while supply wires from the
bottom shall follow the grey line in Figure 7.
Figure 8 Terminal blocks marking
Step 5.1)
Only for IT-Nett: Install the CHARGESTORM® Connected according to Figure 9 or 10. L2
will be the return path in both the 1-phase and 2-phase installation.
Step 6) Connect network
–
In case Ethernet is used connect cable to RJ45-connector on the
control board located on the front panel. When cable is connected in both ends shall link and
activity led on the RJ45 connector be active. If 3G is in use, check that the SIM-card is installed on
the modem unit on the control board. Also check that the antenna cable is attached in both ends.
See schematics in chapter 11.
Step 7) Test
–
Activate power from the distribution panel, after closing and locking
CHARGESTORM® Connected with the key. Do not forget to put the cover on the key-lock. Green
connector symbol shall be active on the front panel after turning on power. Follow directives in
chapter 8.
Figure 9 1-Phase IT-Nett
installation
Figure 10 2-Phase IT-Nett
installation