2.4 Installation / Operation
2.4.1 Installing and Operating the 2017, Upconverter Section
1.) Connect a -10 dBm to -40 dBm signal to IF In, J4 (Figure 2.1)
2.) Connect the RF OUT, J5, to the external equipment
3.) Connect 100-240 ±10% VAC, 47 - 63 Hz to AC1 on the back panel.
4.) Set the desired output frequency (See Section 2.5 Menu Settings).
5.) Set the input level (See Section 2.5 Menu Settings).
6.) Set the gain (See Section 2.5 Menu Settings).
7.) To power the SSPB (+24 VDC, 2.5 amps, max) from the 2017 install a 3 amp 1/4” fuse in F2.
CAUTION!!! INSTALLING A FUSE IN F2 PUTS +24 VDC, 2.5 AMP POWER
ON THE CENTER PIN AND MAY DAMAGE EQUIPMENT IF IMPROPERLY
CONNECTED TO EQUIPMENT THAT CANNOT HANDLE THIS VOLTAGE
OR HAS A DC PATH TO GROUND.
8.) Be sure DS6 (green, DC Power) is on and DS2 (red, Alarm) is off (Figure 2.2).
2.4.2
Installing and Operating the 2017, Downconverter Section -
1.) Connect a -70 dBm to -20 dBm signal to RF In, J2 (Figure 2.1)
2.) Connect the IF OUT, J1, to the external equipment
3.) Connect 90- 260 VAC, 47 - 63 Hz to AC1 on the back panel.
4.) Set the desired input frequency (See Section 2.5 Menu Settings).
5.) Set the gain to get an output level in the 0 to -20 dBm range (See Section 2.5 Menu Settings).
6.) To power the LNB (+24 VDC, 2.5 amps, max) from the 2017 install a 1 amp 1/4” fuse in F1.
CAUTION!!! INSTALLING A FUSE IN F1 PUTS +24 VDC, 0.5 AMP POWER
ON THE CENTER PIN AND MAY DAMAGE EQUIPMENT IF IMPROPERLY
CONNECTED TO EQUIPMENT THAT CANNOT HANDLE THIS VOLTAGE
OR HAS A DC PATH TO GROUND.
7.) Be sure DS6 (green, DC Power) is on and DS2 (red, Alarm) is off (Figure 2.2).
8.) AC Fuse - The fuse is a 5 mm X 20 mm, 2 amp slow blow (Type T) and is inserted in the far slot in
the drawer below the AC input as shown in Figure 2.3. There is a spare fuse in the near slot. If a fuse
continues to open, the power supply is most likely defective.
2017-93 Manual, Rev D
Page 12
05/19/10