3

INSTALLATION OF THE RADIATOR

Turn the carton upside down and open the carton from

the bottom.  Remove the feet from the polystyrene

corner supports, and the plinth and accessories bag from

the polystyrene centre support.

2

Remove the clip containing the probe from the bottom

of the radiator. See Picture below.

1

(Do not discard the clip or remove probe from clip)

.

3

Fit the feet to the radiator by engaging the flanges on

the top of the foot with the slots in the base of the

radiator 

1

.  Push the foot towards the back of the radiator

until it is fully engaged 

2

.

Clip the probe onto the open side of the adjacent foot.

3

ASSEMBLY

2

2

4

The radiator is packed with the direct acting mains cable
clipped to the underside of the radiator ensuring it is secure

during transit.  The off peak mains cable will be secured with
cable ties.  Prior to installing the radiator, unclip the direct acting
mains cable (do not remove or discard these clips).

NOTE: If the off peak mains connection is required to be
made on the right hand side of the radiator, the pre-wired
cable must be passed behind the feet and secured using
the clips on the base of the radiator. For ease of access
this should be done while the radiator is still upside down
in the carton.  Similarly when the direct acting mains cable
is ready to be connected (See Section 23), if the connection
is required to be made on the left hand side of the radiator
the cable must be routed behind the feet.  DO NOT clip the
direct acting mains cable at this stage (See Section 23).
The cable clips are already fitted at the factory to allow
both mains cables to be attached, if required.

1

3

3

Summary of Contents for Eco-Response ER300

Page 1: ...eing fixed Some modern internal building materials are very low density block and require specialised fixing devices to provide a safe secure installation WARNING If during any reassembly of the radia...

Page 2: ...tions for Electrical Equipment The radiator is fitted with two flexible cables for connection to the fixed wiring of the premises through suitable switched connection boxes positioned adjacent to the...

Page 3: ...3 Circuit Diagram...

Page 4: ...theundersideoftheradiatorensuringitissecure during transit The off peak mains cable will be secured with cable ties Prior to installing the radiator unclip the direct acting mains cable do not remove...

Page 5: ...hat the mains supply cables are not damaged If they are to be replaced only heat resistant cable must be used min T85 Refer to sections 4 21 and 22 for fitting the off peak and radiant element cables...

Page 6: ...panel Fig 11D see Fig 11A for wall spacer bracket orientation 11E F Carefully guide the radiator towards the drilled hole and screw part way to the wall Fig 11E 11F 11D 11E 11F 11G NOTE UNDER NO CIRC...

Page 7: ...UMSTANCES SHOULD THESESCREWSBEREMOVED WITHOUT FIRST REMOVING ALL ENERGY RETENTION CELLS FROM THE RADIATOR Solid brick High density block walls These must be drilled and plugged with the Rawlplug No 10...

Page 8: ...l packaging Fig 13C taking care not to damage the insulation attached 13A 14 Lift out the elements from the base insulation and rotate forwards DO NOT DISCONNECT THE TERMINALS 14 13B 13c 15 Carefully...

Page 9: ...stalled DO NOT attempt to reposition the radiator without first unloading the energy retention cells and obtaining the services of a competent electrician 17 16B 19 In its factory default setting the...

Page 10: ...ng the cable Cut the mains cables to length Ensuring the electricity supply is disconnected connect the free end of the mains cable to a suitable double pole switch adjacent to the radiator reinstate...

Page 11: ...PCB Bracket from the bottom of the outer front Remove the wire from the connector block and earth screw Using a pair of pliers remove the cable grip from the bracket The replacement cable will be eith...

Page 12: ...electrical connections are secure Only then phone the customer help line for assistance Reconnect spur and switch on radiator CHECKPROCEDUREFORINSTALLERSFOLLOWINGINSTALLATION 2 To check the radiant pa...